- Studies Postings
 

GI Active Requests

Last Updated: 2/27/2025    Download data as CSV

Generation Interconnection NumberIFS Queue NumberCurrent ClusterCluster GroupNearest Town or CountyStateTO at POIIn-Service Date (proposed) Commercial Operation DateCessation DateOriginal Generator Commercial Op. DateCapacity (MW)MAX Summer MWMAX Winter MWService TypeRequested Maximum Injection Capability (MW)Requested Network Resource Deliverability (MW)Nameplate CapacityGeneration TypeFuel Type Substation or LineRequest ReceivedDate WithdrawnStatusCause of DelayAssociated StudiesFacility ReportExecuted GIA
GEN-2024-SR9Surplus05 SOUTHWESTBeaver CountyOKOG&E 1/1/2027  150150150ER000Battery/StorageBeaver County Substation 345 kV1/26/2024 IA PENDING   
GEN-2024-SR8Surplus02 NEBRASKAGreely CountyNENPPD 12/31/2026  707070ER000Battery/StorageSpalding to North Loup 115kV4/3/2024 FACILITY STUDY STAGE   
GEN-2024-SR7Surplus05 SOUTHWESTBeaver CountyOKOG&E 6/1/2027  200200200ER000SolarBeaver County Substation 345 kV1/26/2024 IA PENDING   
GEN-2024-SR6Surplus04 SOUTHEASTJohnston CountyOKOG&E    200200200ER000Battery/StorageInterconnecting at Hugo - Sunnyside 345 kV transmission line2/20/2024 IA PENDINGEGF: GEN-2017-075 rc Ownership Transfer from Sunchase to Leeward Energy. Contact Gary Braun. 11/13/24 RC   
GEN-2024-SR5Surplus04 SOUTHEASTDrumrightOKOG&E 6/1/2026  176.9176.9176.9ER000Battery/Storage138 kV Greenwood Station2/7/2024 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2024-SR3Surplus04 SOUTHEASTLincoln CountyOKOG&E 5/1/2026  72.572.572.5ER/NR000Battery/Storage138 kV TRYON 3 (Bus # 5156752/1/2024 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2024-SR2Surplus04 SOUTHEASTFranklin CountyAROG&E 3/1/2027  72.572.572.5ER/NR000Battery/Storage161 kV BRANCH 5 (Bus # 515316)2/6/2024 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2024-SR17Surplus04 SOUTHEASTKayOKOG&E 5/1/2027  154.6154.6154.6ER000Battery/StorageTap Medford Tap – Coyote 138kV12/26/2024 None   
GEN-2024-SR16Surplus04 SOUTHEASTOologahOKAEP 12/31/2026  100100100ER/NR000Battery/StorageNortheastern 138kV12/3/2024 None   
GEN-2024-SR15Surplus05 SOUTHWESTYoakumTXSPS 5/1/2026  300300300ER000Battery/StorageMahoney 230kV Substation10/24/2024 None   
GEN-2024-SR14Surplus05 SOUTHWESTLea CountyNMXcel/SPS 4/1/2026  363636ER000Battery/StorageCunningham 115kV7/8/2024 None   
GEN-2024-SR13Surplus04 SOUTHEASTBryan CountyOKOG&E 6/1/2026  52.252.252.2ER/NR000Battery/StorageBrown 138kV Substation5/1/2024 IA PENDING   
GEN-2024-SR12Surplus01 NORTHLa Moure CountyNDWAPA 10/1/2026  202020ER000Battery/StorageEdgeley 115 kV Substation5/21/2024 IA PENDING   
GEN-2024-SR11Surplus04 SOUTHEASTGarfieldOKOGE 12/31/2025  200200200ER/NR000Battery/StorageWoodring 345kV Substation5/7/2024 IA PENDING   
GEN-2024-SR10Surplus02 NEBRASKALancasterNENPPD 12/31/2026  808080ER/NR000Battery/StorageMonolith 115kV4/22/2024 FACILITY STUDY STAGE   
GEN-2024-SR1Surplus04 SOUTHEASTChouteauOKGRDA 12/31/2025  848484ER000Solar345 kV bus of GRDA GREC 1 & 2 Substation11/29/2023 IA PENDING   
GEN-2024-GR6Replacement04 SOUTHEASTNewkirkOKOG&E 5/1/202712/1/2026 300300300ER000WindOpen Sky 345kV Substation7/25/2024 None   
GEN-2024-GR5Replacement04 SOUTHEASTChouteauOKGRDA 10/1/202610/1/2026 582542582ER000HybridGT/BatteryGREC #2 Interconnect Substation – 345kV8/2/2024 None   
GEN-2024-GR4Replacement03 CENTRALRivertonKSEDE 6/30/20263/15/2026 313131ER000ThermalRiverton 4527/25/2024 None   
GEN-2024-GR3Replacement05 SOUTHWESTLea CountyNMXcel/SPS 4/1/20274/1/2027 196196196ER000Solar230kV Cunningham Substation6/7/2024 None   
GEN-2024-GR1Replacement04 SOUTHEASTHarrahOKOG&E 12/31/202612/31/2026 492492492ER000ThermalCTGHorseshoe Lake 138kV1/8/2024 IA PENDING   
GEN-2024-092DISIS-2024-00105 SOUTHWESTRooseveltNMSPS6/1/202912/31/2029  199.5199.5199.5ER/NR000Battery/StoragePortales 115 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-091DISIS-2024-00103 CENTRALJasperMOEDE2/15/20283/1/2028  100100100ER/NR000Battery/Storage145 JOPLIN WEST 7TH 161 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-090DISIS-2024-00103 CENTRALClay MOEvergy2/15/20283/1/2028  100100100ER/NR000Battery/StorageSmithville 161 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-089DISIS-2024-00105 SOUTHWESTCuryNMSPS8/1/202912/1/2029  195195195ER/NR000WindPleasant Hills 230 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-088DISIS-2024-00103 CENTRALGreeneMOSPRM12/19/20251/1/2026  145145145ER/NR000ThermalGasMcCartney 161 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-087DISIS-2024-00104 SOUTHEASTRogersOKAEP11/1/202912/15/2029  510510510ER/NR000ThermalGasNortheastern 345 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-086DISIS-2024-00104 SOUTHEASTDukeOKWFEC1/31/20295/31/2029  120120120ER/NR000SolarRussell 138 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-085DISIS-2024-00103 CENTRALRushKSSUNC7/1/20299/1/2029  160160160ER/NR000SolarOtis 115 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-084DISIS-2024-00103 CENTRALLawrenceMOAEP9/25/202811/25/2028  167167167ER/NR000Battery/StorageReeds Spring - Aurora 161 kV Line10/30/2024 DISIS STAGE   
GEN-2024-083DISIS-2024-00104 SOUTHEASTChoctawOKWFEC9/30/202912/31/2029  250250250ER/NR000SolarHugo 345 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-082DISIS-2024-00101 NORTHWilliamsNDBEPC5/1/20293/1/2030  745745745ER000ThermalGasSpringbrook - Tande 345 kV Line10/30/2024 DISIS STAGE   
GEN-2024-081DISIS-2024-00101 NORTHWilliamsNDBEPC4/1/20282/1/2029  745745745ER000ThermalGasSpringbrook - Tande 345 kV Line10/30/2024 DISIS STAGE   
GEN-2024-080DISIS-2024-00105 SOUTHWESTClovisNMSPS10/1/202912/1/2029  250250250ER/NR000SolarSan Juan 230 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-079DISIS-2024-00105 SOUTHWESTClovisNMSPS10/1/202912/1/2029  250250250ER/NR000SolarSan Juan 230 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-078DISIS-2024-00105 SOUTHWESTStinnettTXSPS10/1/202912/1/2029  300300300ER/NR000SolarPringle 230 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-077DISIS-2024-00105 SOUTHWESTStinnettTXSPS10/1/202912/1/2029  300300300ER/NR000SolarPringle 230 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-076DISIS-2024-00103 CENTRALBurbonKSEvergy10/1/202912/1/2029  130130130ER/NR000SolarNeosho - LaCygne 345 kV Line10/30/2024 DISIS STAGE   
GEN-2024-075DISIS-2024-00104 SOUTHEASTSharonOKOGE10/1/202912/1/2029  300300300ER/NR000SolarWoodward 345 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-074DISIS-2024-00103 CENTRALJacksonMOEvergy11/1/202812/1/2028  200200200ER/NR000Battery/StorageDuncan Road 161 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-073DISIS-2024-00105 SOUTHWESTLeaNMSPS9/1/202812/1/2028  500500500ER/NR000HybridSolar/StorageCrossroads - Hobbs 345 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-072DISIS-2024-00103 CENTRALMitchellKSSUNC2/1/20294/1/2029  160160160ER/NR000SolarBeloit 115 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-071DISIS-2024-00105 SOUTHWESTCassTXAEP5/15/20277/1/2027  282828ER/NR000SolarWest Atlanta - Atlanta 69 kV Line10/30/2024 DISIS STAGE   
GEN-2024-070DISIS-2024-00104 SOUTHEASTOkfuskeeOKWFEC10/2/202812/29/2028  184.5184.5184.5ER/NR000WindPharoah 138 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-069DISIS-2024-00103 CENTRALCrawfordKSEvergy9/30/202812/31/2028  228228228ER/NR000HybridSolar/StorageFranklin 69 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-068DISIS-2024-00105 SOUTHWESTMorrisTXAEP10/2/202812/29/2028  300300300ER/NR000SolarLydia - Welsh 345 kV Line10/30/2024 DISIS STAGE   
GEN-2024-067DISIS-2024-00103 CENTRALCloudKSSUNC5/1/20297/1/2029  380380380ER/NR000SolarMeridian Way 230 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-066DISIS-2024-00103 CENTRALLawrenceMOEDE8/31/202912/31/2029  199199199ER/NR000Battery/StorageCPK446 5 161 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-065DISIS-2024-00102 NEBRASKADodgeNENPPD8/31/202912/31/2029  150150150ER/NR000Battery/StorageFREMONT7 115 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-064DISIS-2024-00103 CENTRALDadeMOEDE8/31/202912/31/2029  185185185ER/NR000HybridSolar/StorageCPK446 5 161 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-063DISIS-2024-00105 SOUTHWESTLambTXSPS10/31/202712/31/2027  256256256ER/NR000SolarPlant X 230 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-062DISIS-2024-00104 SOUTHEASTKingfisher OKWFEC11/1/202812/31/2028  230230230ER/NR000Battery/StorageDover SW 138 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-061DISIS-2024-00103 CENTRALCowleyKSWERE11/1/202812/31/2028  200200200ER/NR000Battery/StorageCreswell 138 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-060DISIS-2024-00104 SOUTHEASTNowataOKOGE12/15/20273/15/2029  250250250ER000WindNortheastern - Delaware 345kV Line10/30/2024 DISIS STAGE   
GEN-2024-059DISIS-2024-00101 NORTHStanleySDWAPA10/2/202812/29/2028  200200200ER/NR000WindOahe - Philip Tap 230 kV line10/30/2024 DISIS STAGE   
GEN-2024-058DISIS-2024-00104 SOUTHEASTNowataOKOGE10/2/202812/29/2028  200200200ER/NR000WindFarmland - Delaware 138 kV line10/30/2024 DISIS STAGE   
GEN-2024-057DISIS-2024-00105 SOUTHWESTCassTXAEP8/31/202912/31/2029  250250250ER/NR000SolarNWTXARK7 - WELSH 7 345 kV line10/30/2024 DISIS STAGE   
GEN-2024-056DISIS-2024-00104 SOUTHEASTNobleOKOGE8/31/202912/31/2029  120120120ER/NR000SolarCow Creek - Morrison 138 kV line10/30/2024 DISIS STAGE   
GEN-2024-055DISIS-2024-00103 CENTRALVernonMOWERE8/31/202912/31/2029  175175175ER/NR000SolarButler - Nevada 161 kV line10/30/2024 DISIS STAGE   
GEN-2024-054DISIS-2024-00103 CENTRALCooperMOWERE8/31/202912/31/2029  120120120ER/NR000SolarOverton - Sedalia East 161 kV line10/30/2024 DISIS STAGE   
GEN-2024-053DISIS-2024-00103 CENTRALNodawayMOWERE6/1/20311/1/2032  450.6425.1450.6ER/NR000ThermalGasMullin Creek 345 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-052DISIS-2024-00104 SOUTHEASTChoctawOKWFEC5/15/20277/1/2027  424242ER/NR000SolarUnger - West Bank Tap 138 kV Line10/30/2024 DISIS STAGE   
GEN-2024-051DISIS-2024-00102 NEBRASKALancasterNELES3/17/20285/17/2028  170170170ER/NR000Battery/StorageWaverly 115 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-050DISIS-2024-00105 SOUTHWESTCastroTXSPS11/30/202812/31/2028  300300300ER/NR000HybridSolar/StorageDeaf Smith - Plant X 230 kV line10/30/2024 DISIS STAGE   
GEN-2024-049DISIS-2024-00103 CENTRALFordKSSUNC10/1/202812/1/2028  199199199ER/NR000Battery/StorageHolcomb - Spearville 345 kV line10/30/2024 DISIS STAGE   
GEN-2024-048DISIS-2024-00103 CENTRALFordKSSUNC10/1/202812/1/2028  199199199ER/NR000Battery/StorageHolcomb - Spearville 345 kV line10/30/2024 DISIS STAGE   
GEN-2024-047DISIS-2024-00103 CENTRALMcPhersonKSEvergy1/1/20316/1/2031  114.958.79123.73ER/NR000ThermalGasJohns-Manville 115 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-046DISIS-2024-00105 SOUTHWESTHansfordTXSPS10/1/202912/1/2029  345345345ER/NR000SolarHitchland-Moore 230 kV line10/30/2024 DISIS STAGE   
GEN-2024-045DISIS-2024-00105 SOUTHWESTHansfordTXSPS10/1/202912/1/2029  345345345ER/NR000SolarHitchland - Moore 230kV line10/30/2024 DISIS STAGE   
GEN-2024-044DISIS-2024-00104 SOUTHEASTParish Caddo LAAEP5/15/20277/1/2027  363636ER/NR000SolarHosston - Plain Dealing 69 kV Line10/30/2024 DISIS STAGE   
GEN-2024-043DISIS-2024-00105 SOUTHWESTRooseveltNMSPS10/1/202912/31/2029  250250250ER/NR000WindCrossroads - Tolk 345 kV Line10/30/2024 DISIS STAGE   
GEN-2024-042DISIS-2024-00105 SOUTHWESTFloydTXSPS10/1/202912/31/2029  250250250ER/NR000WindTuco - Oklaunion 345 kV Line10/30/2024 DISIS STAGE   
GEN-2024-041DISIS-2024-00105 SOUTHWESTFloydTXSPS10/1/202912/31/2029  250250250ER/NR000WindTuco - Oklaunion 345 kV Line10/30/2024 DISIS STAGE   
GEN-2024-040DISIS-2024-00102 NEBRASKANemahaNEOPPD10/1/202912/31/2029  174174174ER/NR000SolarCooper - Nebraska City 345 kV line10/30/2024 DISIS STAGE   
GEN-2024-039DISIS-2024-00102 NEBRASKANemahaNEOPPD10/1/202912/31/2029  250250250ER/NR000SolarHumboldt - Auburn 161 kV line10/30/2024 DISIS STAGE   
GEN-2024-038DISIS-2024-00102 NEBRASKANemahaNEOPPD10/1/202912/31/2029  300300300ER/NR000SolarCooper - Monolith 345 kV line10/30/2024 DISIS STAGE   
GEN-2024-037DISIS-2024-00103 CENTRALNewtonMOAEP10/1/202912/31/2029  200200200ER/NR000WindFlint Creek - Brookline 345 kV line10/30/2024 DISIS STAGE   
GEN-2024-036DISIS-2024-00102 NEBRASKAColfaxNENPPD10/1/202912/31/2029  150150150ER/NR000WindSchuyler- North Bend 115 kV line10/30/2024 DISIS STAGE   
GEN-2024-035DISIS-2024-00101 NORTHBrownSDBEPC9/1/202712/30/2027  270270270ER/NR000HybridSolar/StorageGroton 345 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-034DISIS-2024-00101 NORTHSargentNDWAPA3/1/20297/1/2029  175175175ER/NR000Battery/StorageForman 115 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-033DISIS-2024-00103 CENTRALVernonMOEvergy11/30/202812/31/2028  225225225ER/NR000SolarNevada-Butler 161 kV Line10/30/2024 DISIS STAGE   
GEN-2024-032DISIS-2024-00103 CENTRALStevensKSSUNC11/1/202812/31/2028  250250250ER/NR000SolarHugoton 115 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-031DISIS-2024-00104 SOUTHEASTMarshallOKOGE11/1/202812/31/2028  220220220ER/NR000SolarRussett-S.Brown 138 kV Line10/30/2024 DISIS STAGE   
GEN-2024-030DISIS-2024-00103 CENTRALGrayKSSUNC11/1/202812/31/2028  150150150ER/NR000SolarSanta Fe 115 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-029DISIS-2024-00104 SOUTHEASTLoganOKOGE11/1/202812/31/2028  150150150ER/NR000Battery/StorageCrescent 138 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-028DISIS-2024-00103 CENTRALNodawayMOWERE6/1/20291/1/2030  450.6425.1450.6ER/NR000ThermalGasMullin Creek 345 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-027DISIS-2024-00103 CENTRALRenoKSWERE6/1/20291/1/2030  717.8690.4717.8ER/NR000ThermalGasReno County 345 kV Substation #144310/30/2024 DISIS STAGE   
GEN-2024-026DISIS-2024-00103 CENTRALSumnerKSWERE1/6/20281/1/2029  721.1693.2721.1ER/NR000ThermalGasViola 345 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-025DISIS-2024-00105 SOUTHWESTBowieTXAEP6/1/203012/31/2030  300300300ER/NR000SolarLydia 345 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-024DISIS-2024-00104 SOUTHEASTWoodwardOKWFEC5/1/20287/1/2028  145145145ER/NR000SolarIodine - Mooreland Switchyard 138 kV10/30/2024 DISIS STAGE   
GEN-2024-023DISIS-2024-00102 NEBRASKAGageNENPPD9/30/203012/31/2030  270270270ER/NR000ThermalGasNew Beatrice Power Station 345 kV10/30/2024 DISIS STAGE   
GEN-2024-022DISIS-2024-00102 NEBRASKAGageNENPPD9/30/203012/31/2030  390390390ER/NR000ThermalGasNew Beatrice Power Station 345 kV10/30/2024 DISIS STAGE   
GEN-2024-021DISIS-2024-00102 NEBRASKALancasterNENPPD9/30/203012/31/2030  540540540ER/NR000ThermalGasOlive Creek 345 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-020DISIS-2024-00102 NEBRASKALancasterNENPPD9/30/203012/31/2030  390390390ER/NR000ThermalGasOlive Creek 345 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-019DISIS-2024-00102 NEBRASKAGageNENPPD9/30/203012/31/2030  626262ER/NR000ThermalGasNew Beatrice Power Station 345 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-018DISIS-2024-00102 NEBRASKAGageNENPPD9/30/203012/31/2030  313131ER/NR000ThermalGasNew Beatrice Power Station 345 kV10/30/2024 DISIS STAGE   
GEN-2024-017DISIS-2024-00102 NEBRASKALancasterNENPPD9/30/203012/31/2030  626262ER/NR000ThermalGasOlive Creek 345 kV Substation10/30/2024 DISIS STAGE   
GEN-2024-016DISIS-2024-00103 CENTRALSmithKSITCGP10/2/202812/29/2028  300300300ER/NR000WindPost Rock - Axtell 345 kV Line10/30/2024 DISIS STAGE   
GEN-2024-015DISIS-2024-00105 SOUTHWESTYoakumTXSPS9/1/202812/1/2028  280280280ER/NR000HybridSolar/StorageSundown-Amaco-Yoakum 230 kV Substation10/4/2024 DISIS STAGE   
GEN-2024-013DISIS-2024-00104 SOUTHEASTMcClainOKOG&E4/1/20291/1/2030  495.6474.4495.6ER/NR000ThermalCTNorman Hills 345 kV8/2/2024 DISIS STAGE   
GEN-2024-012DISIS-2024-00104 SOUTHEASTOklahoma OKOG&E4/1/20281/1/2029  495.6474.4495.6ER/NR000ThermalGasHorseshoe Lake 138 kV8/2/2024 DISIS STAGE   
GEN-2024-011DISIS-2024-00105 SOUTHWESTLeaNMWFEC2/1/202612/29/2026  150150150ER/NR000SolarLea County 115 kV Substation12/29/2023 DISIS STAGE   
GEN-2024-010DISIS-2024-00105 SOUTHWESTLeaNMSPS2/1/202612/28/2026  150150150ER/NR000SolarCunningham 230 kV Substation12/29/2023 DISIS STAGE   
GEN-2024-009DISIS-2024-00105 SOUTHWESTLeaNMSPS2/26/202612/30/2026  150150150ER/NR000SolarHobbs 230 kV Substation1/2/2024 DISIS STAGE   
GEN-2024-008DISIS-2024-00105 SOUTHWESTLeaNMSPS2/1/202612/28/2026  150150150ER/NR000SolarWard 115 kV Substation12/29/2023 DISIS STAGE   
GEN-2024-007DISIS-2024-00103 CENTRALStafford KSMIDW1/30/202812/31/2028  808080ER/NR000HybridSolar/StorageSeward 115 kV Substation4/30/2024 DISIS STAGE   
GEN-2024-006DISIS-2024-00104 SOUTHEASTLawrenceARSWPA10/1/20262/1/2028  100100100ER/NR000SolarJonesboro - Water Valley 161 kV 4/25/2024 DISIS STAGE   
GEN-2024-005DISIS-2024-00103 CENTRALAndrew and NodawayMOEvergy11/1/20263/1/2028  150150150ER/NR000SolarMidway - Avenue City 161 kV 4/25/2024 DISIS STAGE   
GEN-2024-003DISIS-2024-00104 SOUTHEASTFranklinARAECC9/12/202511/7/2025  102.2102.2102.2ER000ThermalCTFitzhugh 161kV4/25/2024 DISIS STAGE   
GEN-2024-002DISIS-2024-00105 SOUTHWESTRooseveltNMSPS5/27/20299/30/2029  909090ER/NR000SolarRoosevelt - Portales 115 kV Line2/2/2024 DISIS STAGE   
GEN-2024-001DISIS-2024-00105 SOUTHWESTCurryNMSPS5/27/20299/30/2029  100100100ER/NR000SolarCurry County 115 kV Substation2/2/2024 DISIS STAGE   
GEN-2023-SR9Surplus05 SOUTHWESTLorenzoTXXcel 6/1/2026  505050ER000Battery/StorageTap Floyd County Interchange and Crosby County Interchange 115kV Line2/13/2023 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-SR8Surplus05 SOUTHWESTGruverTXXcel 6/1/2026  200200200ER000Battery/StorageHitchland 345 kV Substation2/13/2023 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-SR7Surplus02 NEBRASKAWayne CoNENPPD 12/31/2024  135135135ER000Battery/StorageHoskins 345 kV Substation12/16/2022 FACILITY STUDY STAGE   
GEN-2023-SR5Surplus04 SOUTHEASTSeilingOKOGE 6/1/2026  858585ER000Battery/StorageTatonga 345 kV Substation12/15/2022 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-SR4Surplus01 NORTHBurkeNDBEPC 6/1/2026  170170170ER000Battery/StorageTande 345 kV Substation12/15/2022 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-SR28Surplus03 CENTRALFordKSSUNC 12/31/2025  150150150ER 000Solar115 kV Fort Dodge Substation10/6/2023 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-SR27Surplus04 SOUTHEASTMayes CountyOKGRDA12/1/20218/1/2024  101.5101.5101.5ER000Battery/StorageGRDA1 to CLARMR 5 161kV line7/12/2023 IA PENDING   
GEN-2023-SR26Surplus04 SOUTHEASTMayes CountyOKAEP12/1/202112/9/2024  72.572.572.5ER000Battery/StoragePryor Junction 138kV sub7/12/2023 IA PENDING   
GEN-2023-SR25Surplus04 SOUTHEASTMayes CountyOKGRDA12/1/20218/1/2024  72.572.572.5ER000Battery/StorageDry Gulch 161kV sub7/12/2023 IA PENDING   
GEN-2023-SR23Surplus04 SOUTHEASTCaddo ParrishLAAEP 12/1/2025  73.573.573.5ER/NR000Battery/Storage138 kV G16-167-TAP Station (Bus# 588404); Tapping North Benton (Bus# 508811) to Lieberman (bus# 508806) Transmission Line6/20/2023 IA PENDING   
GEN-2023-SR22Surplus04 SOUTHEASTMayes CountyOKAEP 12/6/2024  124.7124.7124.7ER000Battery/StorageExplorer Claremore Tap COOYYAH46/20/2023 IA PENDING   
GEN-2023-SR20Surplus04 SOUTHEASTCuster/WasitaOKAEP 6/1/2025  120120120ER000Battery/StorageWeatherford 138 kV Substation6/21/2023 IA PENDING   
GEN-2023-SR19Surplus02 NEBRASKAJefferson CountyNENPPD 6/1/2025  606060ER000Battery/StorageSteele City 115 kV6/21/2023 FACILITY STUDY STAGE   
GEN-2023-SR18Surplus04 SOUTHEASTGrady CountyOKOGE 5/15/2025  808080ER000Battery/StorageMinco 345 kV6/20/2023 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-SR16Surplus04 SOUTHEASTWoodward and Harper CountiesOKOG&E 6/1/2025  707070ER000Battery/StorageTap Mooreland to Woodward 138 kV Line (FPLSwitch 138 kV Substation)4/26/2023 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-SR15Surplus04 SOUTHEASTChoctaw CountyOKWFEC 6/1/2026  505050ER/NR000Battery/StorageHugo Power Plant 138 kV Substation3/27/2023 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-SR13Surplus04 SOUTHEASTGarfield CountyOKOG&E 6/1/2025  707070ER000Battery/StorageBreckinridge 138 kV Substation1/26/2023 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-SR12Surplus05 SOUTHWESTWhitefaceTXXcel 9/30/2025  120120120ER000Battery/StorageTap Cochran to Lehman 115 kV Line2/13/2023 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-SR1Surplus02 NEBRASKABrownNENPPD10/1/20056/21/2024  21.921.921.9ER/NR000ThermalAinsworth Wind 115 kV12/5/2022 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-GR5Replacement05 SOUTHWESTLamb CountyTXXcel/SPS 4/1/20268/11/2022 150150150ER000SolarPlant X 115 kV Substation7/18/2023 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-GR4Replacement05 SOUTHWESTLea CountyNMXcel/SPS 5/1/20267/13/2022 727272ER000SolarCunningham 115kV7/5/2023 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-GR3Replacement05 SOUTHWESTQuay CountyNMXcel/SPS12/1/200412/27/20249/16/202412/31/2004808080ER/NR000WindNorton 115 kV6/30/2023 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2023-GR2Replacement04 SOUTHEASTOklahoma CityOKOG&E 5/1/20264/1/2026 94.24284.92694.242ER000ThermalGasTinker Air Force Base 138kV2/17/2023 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-GR1Replacement04 SOUTHEASTAnadarkoOKWFEC 12/1/202511/30/2025 97.48897.48895.64ER000ThermalGasAnadarko Power Plant 69 kV1/9/2023 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-241DISIS-2023-00104 SOUTHEASTFranklin & WoodTXAEP8/28/20271/5/2028  939393ER000SolarWinnsboro 138 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-237DISIS-2023-00105 SOUTHWESTHaleTXSPS1/15/203012/31/2030  500500500ER/NR000WindCrawfish Draw 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-236DISIS-2023-00105 SOUTHWESTLeaNMSPS1/15/203012/31/2030  400400400ER/NR000SolarHobbs - Yoakum 345 kV10/2/2023 DISIS STAGE   
GEN-2023-231DISIS-2023-00103 CENTRALCrawfordKSEvergy5/1/202812/1/2028  310310310ER000HybridWind/StorageNeosho - LaCynge 345 kV Line10/2/2023 DISIS STAGE   
GEN-2023-230DISIS-2023-00104 SOUTHEASTBossierLAAEP2/4/202811/19/2028  150150150ER/NR000HybridSolar/StorageRed Pointe 138 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-229DISIS-2023-00104 SOUTHEASTCaddoOKAEP4/1/202810/31/2028  230230230ER/NR000WindSouthwestern Power Station 138 kV Substation (SWS4)10/2/2023 DISIS STAGE   
GEN-2023-228DISIS-2023-00105 SOUTHWESTCottleTXSPS8/15/202612/1/2026  250250250ER/NR000Battery/StorageTuco-Okalunion 345 kV line10/2/2023 DISIS STAGE   
GEN-2023-227DISIS-2023-00104 SOUTHEASTTitusTXAEP5/1/20269/1/2026  200200200ER/NR000Battery/StoragePetty to Chapel 138 kV Line10/2/2023 DISIS STAGE   
GEN-2023-225DISIS-2023-00102 NEBRASKALancasterNENPPD3/1/20276/1/2027  217217217ER000ThermalRICEOlive Creek 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-224DISIS-2023-00102 NEBRASKALancasterNENPPD3/1/20276/1/2027  478478478ER000ThermalCTGOlive Creek 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-223DISIS-2023-00102 NEBRASKAGage NENPPD3/1/20276/1/2027  239239239ER/NR000ThermalCTGNew Beatrice Power Station 345 kV10/2/2023 DISIS STAGE   
GEN-2023-222DISIS-2023-00102 NEBRASKAGageNENPPD3/1/20276/1/2027  478478478ER/NR000ThermalCTGNew Beatrice Power Station 345 kV10/2/2023 DISIS STAGE   
GEN-2023-221DISIS-2023-00103 CENTRALOsageKSEvergy9/1/202912/1/2029  250250250ER/NR000SolarEmporia Energy Center - Swissvale 345 kV Line10/2/2023 DISIS STAGE   
GEN-2023-220DISIS-2023-00103 CENTRALOsageKSEvergy8/1/202912/1/2029  250250250ER/NR000SolarEmporia Energy Center - Swissvale 345 kV Line10/2/2023 DISIS STAGE   
GEN-2023-219DISIS-2023-00103 CENTRALOsageKSEvergy8/1/202912/1/2029  125125125ER/NR000SolarReading - Osage Jct 115 kV Line10/2/2023 DISIS STAGE   
GEN-2023-218DISIS-2023-00102 NEBRASKAKnox and CedarNENPPD9/30/202612/31/2026  200200200ER/NR000WindTurtle Creek 345 kV Substation 10/2/2023 DISIS STAGE   
GEN-2023-217DISIS-2023-00102 NEBRASKAKnox and CedarNENPPD9/30/202612/31/2026  200200200ER/NR000WindTurtle Creek 345 kV Substation 10/2/2023 DISIS STAGE   
GEN-2023-216DISIS-2023-00102 NEBRASKAKnox and CedarNENPPD9/30/202612/31/2026  200200200ER/NR000WindTurtle Creek 345 kV Substation 10/2/2023 DISIS STAGE   
GEN-2023-213DISIS-2023-00104 SOUTHEASTBentonARAEP4/15/20289/1/2028  100100100ER/NR000Battery/StorageChamber Springs 161 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-212DISIS-2023-00104 SOUTHEASTBowieTX/OKAEP3/1/202712/1/2027  400400400ER/NR000HybridSolar/StorageNorthwest Texarkana - Valliant 345 kV Line10/2/2023 DISIS STAGE   
GEN-2023-211DISIS-2023-00104 SOUTHEASTKayOKOGE3/1/202811/1/2028  250250250ER/NR000HybridSolar/Battery/WindRanch Road 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-210DISIS-2023-00104 SOUTHEASTLincolnOKWFEC5/4/20269/1/2026  191191191ER/NR000SolarPrague - Chernicky 138 kV Line10/2/2023 DISIS STAGE   
GEN-2023-209DISIS-2023-00105 SOUTHWESTRandallTXSPS4/1/20276/1/2027  125125125ER/NR000Battery/StorageAmarillo South 115 kV10/2/2023 DISIS STAGE   
GEN-2023-208DISIS-2023-00105 SOUTHWESTPotterTXSPS 12/31/2029  200200200ER000Battery/StorageRolling Hills 115 kV10/2/2023 DISIS STAGE   
GEN-2023-206DISIS-2023-00104 SOUTHEASTSebastianAROGE1/1/202912/31/2029  505050ER/NR000Battery/StorageBattlefield BESS 161 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-205DISIS-2023-00104 SOUTHEASTHughesOKAEP7/1/202612/31/2026  180180180ER/NR000SolarMcAlester City - Weleetka 138 kV line10/2/2023 DISIS STAGE   
GEN-2023-204DISIS-2023-00104 SOUTHEASTMorrisTXAEP4/1/202812/1/2028  953953953ER000ThermalCTGWelsh-Lydia 345kV Line 10/2/2023 DISIS STAGE   
GEN-2023-203DISIS-2023-00105 SOUTHWESTLeaNMSPS7/31/202812/31/2028  300300300ER/NR000HybridSolar/StorageHobbs - Ink Basin 230 kV Transmission Line10/2/2023 DISIS STAGE   
GEN-2023-201DISIS-2023-00105 SOUTHWESTLeaNMNEET7/31/202812/31/2028  300300300ER/NR000HybridSolar/StorageCrossroads - Hobbs 345 kV Line10/2/2023 DISIS STAGE   
GEN-2023-199DISIS-2023-00102 NEBRASKADakota NENPPD3/1/20303/28/2027  250250250ER/NR000HybridSolar/StorageTwin Church 230 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-195DISIS-2023-00105 SOUTHWESTBaileyTXSPS2/1/20286/1/2028  250250250ER/NR000SolarRoosevelt - Tolk 230 kV line tap10/2/2023 DISIS STAGE   
GEN-2023-194DISIS-2023-00103 CENTRALCherokee KSEDE6/1/202812/31/2028  225225225ER/NR000SolarRiverton - Neosho 161 kV Line Tap10/2/2023 DISIS STAGE   
GEN-2023-193DISIS-2023-00104 SOUTHEASTHarrisonTXAEP1/15/20283/31/2028  175175175ER/NR000HybridSolar/StoragePirkey - Whitney 138 kV Line10/2/2023 DISIS STAGE   
GEN-2023-189DISIS-2023-00102 NEBRASKALancasterNELES8/30/203012/31/2030  200200200ER000Battery/StorageNW 68th - Holdrege 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-188DISIS-2023-00105 SOUTHWESTCottonOKAEP2/15/20279/1/2027  160160160ER/NR000HybridSolar/StorageOklaunion - Lawton 345 kV Line10/2/2023 DISIS STAGE   
GEN-2023-184DISIS-2023-00105 SOUTHWESTEddyNMSPS8/30/203012/31/2030  200200200ER000SolarPhantom 115 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-183DISIS-2023-00105 SOUTHWESTHale TXSPS3/31/20272/28/2027  217208217ER000ThermalCTGTuco 345kV10/2/2023 DISIS STAGE   
GEN-2023-182DISIS-2023-00101 NORTHLogan & McIntoshNDBEPC8/15/202612/1/2026  300300300ER000WindGroton - Leland Olds 345 kV Line10/2/2023 DISIS STAGE   
GEN-2023-180DISIS-2023-00104 SOUTHEASTSebastianARAEP2/1/20286/1/2028  150150150ER/NR000SolarHackett - N Huntington 161 kV Line Tap10/2/2023 DISIS STAGE   
GEN-2023-178DISIS-2023-00105 SOUTHWESTRooseveltNMSPS8/15/202612/1/2026  200200200ER/NR000SolarRoosevelt 230kV Substation10/2/2023 DISIS STAGE   
GEN-2023-177DISIS-2023-00104 SOUTHEASTGarvinOKOGE2/1/20286/1/2028  200200200ER/NR000SolarPaoli - Seminole 138 kV line tap10/2/2023 DISIS STAGE   
GEN-2023-176DISIS-2023-00105 SOUTHWESTLambTXSPS8/30/203012/31/2030  300300300ER000WindPlant X 230 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-174DISIS-2023-00104 SOUTHEASTGarvinOKWFEC2/1/20286/1/2028  150150150ER000Battery/StoragePaoli West 138 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-173DISIS-2023-00103 CENTRALKearnyKSSUNC9/1/202712/31/2027  100100100ER/NR000WindHolcomb 345 kV 10/2/2023 DISIS STAGE   
GEN-2023-172DISIS-2023-00103 CENTRALKearnyKSSUNC9/1/202712/31/2027  200200200ER/NR000WindHolcomb 345 kV 10/2/2023 DISIS STAGE   
GEN-2023-171DISIS-2023-00103 CENTRALJacksonMOINDN2/1/20286/1/2028  150150150ER/NR000Battery/StorageSub M 161 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-170DISIS-2023-00103 CENTRALCharitonMOEvergy2/1/20286/1/2028  150150150ER000Battery/StorageSalisbury 161 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-169DISIS-2023-00103 CENTRALClayMOEvergy2/1/20286/1/2028  125125125ER/NR000Battery/StorageMissouri City - Liberty South 161 kV Line10/2/2023 DISIS STAGE   
GEN-2023-168DISIS-2023-00104 SOUTHEASTOklahomaOKOGE2/1/20286/1/2028  175175175ER/NR000Battery/StorageClassen 138 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-167DISIS-2023-00104 SOUTHEASTOklahomaOKOGE2/1/20286/1/2028  250250250ER/NR000Battery/StorageWashington Park 138 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-166DISIS-2023-00104 SOUTHEASTOklahomaOKOGE2/1/20286/1/2028  150150150ER000Battery/Storage84th Street - Tennessee Tap 138 kV Line10/2/2023 DISIS STAGE   
GEN-2023-165DISIS-2023-00104 SOUTHEASTCaddoOKOGE3/1/20285/1/2028  210210210ER/NR000Battery/StorageGracemont 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-164DISIS-2023-00104 SOUTHEASTCaddo OKOGE3/1/20285/1/2028  210210210ER/NR000Battery/StorageGracemont 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-161DISIS-2023-00104 SOUTHEASTBlaineOKOGE9/3/202611/4/2026  74.974.974.9ER/NR000Battery/StorageRoman Nose 138 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-159DISIS-2023-00105 SOUTHWESTBailey and LambTXSPS3/1/20299/15/2029  170170170ER/NR000Battery/StorageNeedmore - Yoakum 230 kV Line10/2/2023 DISIS STAGE   
GEN-2023-158DISIS-2023-00105 SOUTHWESTBailey and LambTXSPS3/1/20299/15/2029  335335335ER/NR000SolarNeedmore - Yoakum 230 kV Line10/2/2023 DISIS STAGE   
GEN-2023-154DISIS-2023-00101 NORTHHandSDWAPA3/1/20299/30/2029  175175175ER000SolarFort Thompson - Huron 230 kV Tap10/2/2023 DISIS STAGE   
GEN-2023-153DISIS-2023-00102 NEBRASKAPerkinsNETri-State6/30/20288/31/2028  120120120ER/NR000HybridSolar/StorageGrant 115 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-151DISIS-2023-00104 SOUTHEASTHempsteadARAEP4/1/20288/1/2028  100100100ER/NR000HybridSolar/StorageSouth Nashville - South Murfreesboro 138kV10/2/2023 DISIS STAGE   
GEN-2023-150DISIS-2023-00104 SOUTHEASTCaddoOKOGE9/1/202712/31/2027  150150150ER/NR000SolarGracemont 138 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-149DISIS-2023-00103 CENTRALLinKSEvergy2/15/20297/1/2029  300300300ER/NR000Battery/StorageLaCygne - Stilwell 345 kV Line10/2/2023 DISIS STAGE   
GEN-2023-143DISIS-2023-00105 SOUTHWESTLambTXSPS3/1/20299/15/2029  200200200ER/NR000Battery/StoragePlant X 230 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-142DISIS-2023-00105 SOUTHWESTLambTXSPS3/1/20299/15/2029  275275275ER/NR000SolarPlant X 230 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-138DISIS-2023-00104 SOUTHEASTDelewareOKGRDA7/15/202811/30/2028  250250250ER000WindGRDA1 - Tonece7 345 kV Line10/2/2023 DISIS STAGE   
GEN-2023-135DISIS-2023-00104 SOUTHEASTBowieTXAEP9/15/202612/31/2026  525252ER/NR000SolarLydia 345kV substation10/2/2023 DISIS STAGE   
GEN-2023-134DISIS-2023-00104 SOUTHEASTHughes/OkfuskeeOKAEP9/15/202612/31/2026  252252252ER/NR000WindFixico Tap to Weleetka 138 kV Line10/2/2023 DISIS STAGE   
GEN-2023-133DISIS-2023-00102 NEBRASKACusterNENPPD5/1/203012/30/2030  250250250ER000WindSweetwater 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-132DISIS-2023-00104 SOUTHEASTCraigheadARSWPA6/30/202612/31/2026  150150150ER/NR000SolarJonesboro - Independence 161 kV 10/2/2023 DISIS STAGE   
GEN-2023-123DISIS-2023-00105 SOUTHWESTOchiltree/HandsfordTXSPS8/30/203012/31/2030  285285285ER000WindPringle Interchange 230 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-120DISIS-2023-00105 SOUTHWESTSwisherTXSPS8/30/203012/31/2030  130130130ER000SolarKress 115 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-117DISIS-2023-00102 NEBRASKAKeith, Deuel, GardenNENPPD8/30/203012/30/2030  300300300ER000WindKeystone 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-116DISIS-2023-00102 NEBRASKAKeith, Deuel, GardenNENPPD8/30/203012/30/2030  500500500ER000WindKeystone 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-110DISIS-2023-00105 SOUTHWESTHallTXSPS8/30/203012/31/2030  250250250ER000SolarTap Border to Tuco 345 kV Line10/2/2023 DISIS STAGE   
GEN-2023-107DISIS-2023-00103 CENTRALFinney/KearnyKSSUNC5/1/203012/31/2030  300300300ER000WindSetab 345 kV 10/2/2023 DISIS STAGE   
GEN-2023-105DISIS-2023-00101 NORTHHydeSDBEPC9/1/202812/1/2028  249249249ER/NR000WindChappelle Creek 345 kV10/2/2023 DISIS STAGE   
GEN-2023-104DISIS-2023-00104 SOUTHEASTWoodsOKWFEC8/30/202712/17/2027  100100100ER/NR000HybridSolar/StorageMooreland - Noel 138 kV Line10/2/2023 DISIS STAGE   
GEN-2023-102DISIS-2023-00104 SOUTHEASTWoodsOKOGE8/30/202712/17/2027  475475475ER/NR000HybridSolar/StorageDegrasse 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-101DISIS-2023-00104 SOUTHEASTWheelerTXSPS10/1/202712/31/2027  150150150ER/NR000HybridSolar/StorageTap Stateline Demarc - Wheeler 230 kV Line10/2/2023 DISIS STAGE   
GEN-2023-100DISIS-2023-00104 SOUTHEASTWoodsOKOGE8/30/202712/17/2027  300300300ER/NR000HybridSolar/StorageDegrasse 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-099DISIS-2023-00103 CENTRALJacksonKSEvergy8/30/203012/31/2030  300300300ER000SolarJeffery Energy Center 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-097DISIS-2023-00101 NORTHWilliamsNDBEPC2/15/20297/1/2029  250250250ER/NR000Battery/StorageJudson 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-092DISIS-2023-00104 SOUTHEASTChoctawOKWFEC8/30/202712/17/2027  125125125ER/NR000HybridSolar/StorageUnger - Frogville 138 kV line10/2/2023 DISIS STAGE   
GEN-2023-088DISIS-2023-00104 SOUTHEASTOkfuskee/OkmulgeeOKWFEC9/15/202812/31/2028  117117117ER/NR000WindPharaoh 138 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-087DISIS-2023-00103 CENTRALCassMOEvergy8/30/203012/31/2030  200200200ER000SolarArchie 161 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-086DISIS-2023-00105 SOUTHWESTRandallTXSPS10/1/20285/1/2029  300300300ER/NR000HybridSolar/StoragePotter - Newhart 230 kV line10/2/2023 DISIS STAGE   
GEN-2023-085DISIS-2023-00103 CENTRALDouglas/WrightMOSWPA9/15/202612/31/2026  150150150ER/NR000WindMansfield - Logan 161 kV Line10/2/2023 DISIS STAGE   
GEN-2023-082DISIS-2023-00101 NORTHBrookings SDWAPA2/15/20297/1/2029  175175175ER/NR000Battery/StorageWhite 115 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-081DISIS-2023-00105 SOUTHWESTLeaNMNEET8/1/202810/1/2028  625625625ER/NR000HybridSolar/StorageCrossroads - Hobbs 345 kV Line10/2/2023 DISIS STAGE   
GEN-2023-079DISIS-2023-00102 NEBRASKACassNEOPPD7/1/20282/1/2029  303303303ER000ThermalGas TurbineSubstation 3740 345 kV10/2/2023 DISIS STAGE   
GEN-2023-078DISIS-2023-00102 NEBRASKACassNEOPPD7/1/20272/1/2028  255235255ER000ThermalGas TurbineSubstation 3740 345 kV10/2/2023 DISIS STAGE   
GEN-2023-077DISIS-2023-00102 NEBRASKACassNEOPPD7/1/20272/1/2028  255235255ER000ThermalGas TurbineSubstation 3740 345 kV10/2/2023 DISIS STAGE   
GEN-2023-076DISIS-2023-00104 SOUTHEASTNowata/CraigOKEvergy9/1/202712/31/2027  100100100ER/NR000WindDelaware - Neosho 345 kV10/2/2023 DISIS STAGE   
GEN-2023-075DISIS-2023-00104 SOUTHEASTNowata/CraigOKEvergy10/1/202712/1/2027  200200200ER/NR000WindDelaware to Neosho 345 kV10/2/2023 DISIS STAGE   
GEN-2023-073DISIS-2023-00103 CENTRALButlerKSEvergy8/30/202712/27/2027  250250250ER/NR000Battery/StorageRose Hill 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-069DISIS-2023-00104 SOUTHEASTAtokaOKWFEC8/30/202712/17/2027  100100100ER/NR000HybridSolar/StorageTupelo - Atoka 138 kV Line10/2/2023 DISIS STAGE   
GEN-2023-065DISIS-2023-00103 CENTRALHarveyKSEvergy5/1/20269/1/2026  140140140ER/NR000Battery/StorageHalstead 69 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-064DISIS-2023-00104 SOUTHEASTLeFloreOKSWPA8/1/202812/1/2028  200200200ER/NR000HybridSolar/StorageRS Kerr-Stigler 161 kV line10/2/2023 DISIS STAGE   
GEN-2023-063DISIS-2023-00104 SOUTHEASTRogersOKAEP8/1/202812/1/2028  135135135ER/NR000HybridSolar/StorageCatoosa - Owasso 88th 138 kV line10/2/2023 DISIS STAGE   
GEN-2023-062DISIS-2023-00101 NORTHWilliamsNDLYREC4/30/20287/31/2028  989898ER000ThermalSteamREN 115 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-061DISIS-2023-00103 CENTRALJasperMOSWPA9/30/202712/31/2027  100100100ER/NR000Battery/StorageCarthage 161 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-060DISIS-2023-00105 SOUTHWESTLambTXSPS9/30/202612/31/2026  256256256ER/NR000SolarPlant X 230kV Substation10/2/2023 DISIS STAGE   
GEN-2023-059DISIS-2023-00104 SOUTHEASTHarrison and PanolaTXAEP9/30/202612/31/2026  200200200ER/NR000HybridSolar\RECIP GasTap Rockhill to South Shreveport 138 kV line9/11/2023 DISIS STAGE   
GEN-2023-057DISIS-2023-00104 SOUTHEASTPawneeOKGRDA12/28/20275/31/2028  150150150ER/NR000Battery/StoragePawnee Switch 138 kV10/2/2023 DISIS STAGE   
GEN-2023-056DISIS-2023-00104 SOUTHEASTVan Buren CountyARSWPA12/28/20275/31/2028  150150150ER/NR000Battery/StorageVan Buren 161 kV10/2/2023 DISIS STAGE   
GEN-2023-055DISIS-2023-00104 SOUTHEASTMayes CountyOKGRDA12/28/20275/31/2028  100100100ER/NR000Battery/StorageKerr Grove 161 kV10/2/2023 DISIS STAGE   
GEN-2023-050DISIS-2023-00103 CENTRALLabetteKSEvergy6/30/202812/31/2028  400400400ER/NR000HybridSolar/StorageNeosho 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-049DISIS-2023-00104 SOUTHEASTMayesOKGRDA6/30/202812/31/2028  150150150ER/NR000HybridSolar/StorageDry Gulch - Pensacola 161 kV Line10/2/2023 DISIS STAGE   
GEN-2023-038DISIS-2023-00104 SOUTHEASTCoalOKOGE5/24/20269/1/2026  200200200ER/NR000SolarLula 138 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-037DISIS-2023-00103 CENTRALWyandotte KSKACY4/15/20287/1/2028  200200200ER/NR000Battery/StorageNearman 161 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-036DISIS-2023-00103 CENTRALJacksonMOINDN8/30/202612/31/2026  165165165ER/NR000Battery/StorageEckles Road 161 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-035DISIS-2023-00104 SOUTHEASTGradyOKWFEC5/4/20269/1/2026  200200200ER/NR000SolarCleveland - Amber Tap 138 kV Line10/2/2023 DISIS STAGE   
GEN-2023-034DISIS-2023-00103 CENTRALSedgwickKSEvergy5/24/20269/1/2026  130130130ER/NR000SolarClear Water - Waco 138 kV line10/2/2023 DISIS STAGE   
GEN-2023-033DISIS-2023-00103 CENTRALClayMOEvergy4/15/20287/1/2028  200200200ER/NR000Battery/StorageLiberty South 161 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-032DISIS-2023-00103 CENTRALLafayetteMOEvergy1/1/20286/1/2028  200200200ER/NR000SolarOdessa and Lexington 161 kV Line10/2/2023 DISIS STAGE   
GEN-2023-030DISIS-2023-00104 SOUTHEASTDeSoto ParishLAAEP9/1/202712/31/2027  252525ER/NR000SolarTap between 345 kV SW Shreveport to Dolet Hills Substations10/2/2023 DISIS STAGE   
GEN-2023-028DISIS-2023-00104 SOUTHEASTMayesOKGRDA4/30/202810/31/2028  230230230ER/NR000HybridSolar/BatteryDry Gulch - Pensacola 161 kV Line10/2/2023 DISIS STAGE   
GEN-2023-027DISIS-2023-00104 SOUTHEASTMayesOKAEP4/30/202811/30/2027  150150150ER/NR000HybridSolar/BatteryBird Hollow (Langley) - Pryor Junction 138 kV Line10/2/2023 DISIS STAGE   
GEN-2023-023DISIS-2023-00103 CENTRALWyandotte KSKACY4/15/20287/1/2028  200200200ER/NR000Battery/StorageCenter City 161 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-022DISIS-2023-00104 SOUTHEASTMcIntosh OKOGE9/1/202712/31/2027  250250250ER/NR000WindCanadian River 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-015DISIS-2023-00103 CENTRALFinney CountyKSSPS5/4/20269/1/2026  330330330ER/NR000SolarFinney-Carpenter 345 KV line10/2/2023 DISIS STAGE   
GEN-2023-012DISIS-2023-00101 NORTHLake PrestonSDEREC6/15/202610/31/2026  98.698.698.6ER/NR000WindKingsbury County 115kV Substation10/2/2023 DISIS STAGE   
GEN-2023-011DISIS-2023-00102 NEBRASKAJeffersonNENPPD8/30/203012/31/2030  190190190ER000WindHarbine 115 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-010DISIS-2023-00105 SOUTHWESTShermanTXSPS8/30/203012/31/2030  280280280ER000WindMoore Co 230 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-009DISIS-2023-00104 SOUTHEASTSawyerOKWFEC6/1/202812/1/2028  250250250ER/NR000Battery/StorageHugo 138 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-008DISIS-2023-00105 SOUTHWESTHaleTXSPS8/8/203012/31/2030  757575ER000SolarTuco - Carlisle 230 kV line10/2/2023 DISIS STAGE   
GEN-2023-006DISIS-2023-00103 CENTRALBarton, VernonMONEET5/1/202912/31/2029  202202202ER000WindWolf Creek- Blackberry 345 kV Line Break10/2/2023 DISIS STAGE   
GEN-2023-005DISIS-2023-00105 SOUTHWESTLambTXSPS9/30/202612/31/2026  256256256ER/NR000SolarPlant X 230kV Substation9/25/2023 DISIS STAGE   
GEN-2023-001DISIS-2023-00105 SOUTHWESTLeaNMSPS7/15/202512/31/2025  230230230ER/NR000SolarT14 Circuit 115 V Line5/26/2023 DISIS STAGE10/3/2023 Updated TO from XCEL to SPS. kr   
GEN-2022-GR1Replacement04 SOUTHEASTHallsvilleTXAEP 3/30/20263/31/2023 580580580ER000SolarPirkey 138 kV3/23/2022 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2022-241DISIS-2022-00104 SOUTHEASTHempsteadARAEP3/1/20289/15/2028  200200200ER/NR000Battery/StorageJohn W Turk Jr Power Plant 345 kV sub2/28/2023 DISIS STAGE   
GEN-2022-240DISIS-2022-00104 SOUTHEASTHempsteadARAEP3/1/20289/15/2028  200200200ER/NR000Battery/StorageJohn W Turk Jr Power Plant 345 kV sub2/28/2023 DISIS STAGE   
GEN-2022-239DISIS-2022-00104 SOUTHEASTHempsteadARAEP3/1/20289/15/2028  350350350ER/NR000SolarJohn W Turk Jr Power Plant 345 kV sub2/28/2023 DISIS STAGE   
GEN-2022-238DISIS-2022-00104 SOUTHEASTPottawatomieOKOGE3/1/20289/15/2028  150150150ER/NR000Battery/StorageMaud 138 kV substation2/28/2023 DISIS STAGE   
GEN-2022-237DISIS-2022-00104 SOUTHEASTPottawatomieOKOGE3/1/20289/15/2028  150150150ER/NR000SolarMaud 138 kV substation2/28/2023 DISIS STAGE   
GEN-2022-235DISIS-2022-00104 SOUTHEASTCanadianOKWFEC3/1/20289/15/2028  150150150ER/NR000Battery/StorageEl Reno SW 138 kV 2/28/2023 DISIS STAGE   
GEN-2022-234DISIS-2022-00104 SOUTHEASTRogersOKAEP3/1/20289/15/2028  200200200ER/NR000SolarAlluwe Tap – Chelsea 138 kV line2/28/2023 DISIS STAGE   
GEN-2022-231DISIS-2022-00104 SOUTHEASTLoganOKOGE3/1/20289/15/2028  166166166ER/NR000SolarCrescent to Cottonwood Creek 138 kV Line2/28/2023 DISIS STAGE   
GEN-2022-219DISIS-2022-00101 NORTHDawsonMTWAPA10/6/202612/31/2026  350350350ER/NR000SolarBelfield 230 kV Substation3/2/2023 DISIS STAGE   
GEN-2022-214DISIS-2022-00103 CENTRALSumnerKSWERE5/1/202712/15/2028  239239239ER000SolarGill - Viola 138 kV Line Break3/2/2023 DISIS STAGE   
GEN-2022-209DISIS-2022-00103 CENTRALAndrew/Gentry/DekalbMOKCPL7/1/202712/1/2027  600600600ER/NR000HybridSolar/StorageTap on the Mullen Creek to Ketchum 345 kV Line3/1/2023 DISIS STAGE   
GEN-2022-208DISIS-2022-00103 CENTRALAndrew/Gentry/DekalbMOKCPL7/1/202712/1/2027  400400400ER/NR000WindTap on the Mullen Creek to Ketchum 345 kV Line3/1/2023 DISIS STAGE   
GEN-2022-206DISIS-2022-00103 CENTRALEdwards/HodgemanKSITCGP7/1/202711/1/2027  250250250ER/NR000WindPost Rock - Spearville 345 kV3/1/2023 DISIS STAGE   
GEN-2022-205DISIS-2022-00103 CENTRALEdwards/HodgemanKSITCGP7/1/202711/1/2027  250250250ER/NR000WindPost Rock - Spearville 345 kV3/1/2023 DISIS STAGE   
GEN-2022-204DISIS-2022-00103 CENTRALEdwards/HodgemanKSITCGP7/1/202711/1/2027  250250250ER/NR000WindPost Rock - Spearville 345 kV3/1/2023 DISIS STAGE   
GEN-2022-196DISIS-2022-00104 SOUTHEASTPittsburgOKAEP5/1/202712/15/2027  215215215ER000WindPittsburg 345kV Substation2/28/2023 DISIS STAGE   
GEN-2022-186DISIS-2022-00103 CENTRALCoffeyKSWERE5/6/20265/30/2026  684684684ER/NR000SolarWolf Creek - Benton 345 kV Substation2/28/2023 DISIS STAGE   
GEN-2022-176DISIS-2022-00104 SOUTHEASTNowataOKAEP4/1/202610/31/2026  215215215ER/NR000WindNortheastern - Delaware 345 kV transmission line2/17/2023 DISIS STAGE   
GEN-2022-171DISIS-2022-00105 SOUTHWESTCurryNMSPS8/1/202612/1/2026  200200200ER000WindPleasant Hill 230 kV Substation2/26/2023 DISIS STAGE   
GEN-2022-168DISIS-2022-00103 CENTRALHenryMOKCPL7/31/202712/31/2027  380380380ER/NR000SolarSilwell - Clinton 161 kV Line2/26/2023 DISIS STAGE   
GEN-2022-167DISIS-2022-00104 SOUTHEASTTulsaOKAEP6/30/202810/1/2028  250250250ER/NR000SolarTulsa North - Northeastern 345 kV Line2/26/2023 DISIS STAGE   
GEN-2022-163DISIS-2022-00104 SOUTHEASTCanadianOKOGE3/15/20266/15/2026  200200200ER/NR000Battery/StorageCimarron 345kV Substation2/26/2023 DISIS STAGE   
GEN-2022-162DISIS-2022-00102 NEBRASKASaline NENPPD5/1/202512/31/2025  118118118ER/NR000WindFriend 115 kV Substation2/24/2023 DISIS STAGE   
GEN-2022-161DISIS-2022-00103 CENTRALButlerKSWERE12/31/20263/1/2027  400400400ER000WindBurns 345kV Substation2/24/2023 DISIS STAGE   
GEN-2022-160DISIS-2022-00105 SOUTHWESTChaves and LeaNMNEET5/1/202812/1/2028  280280280ER/NR000WindCrossroads - Hobbs 345 kV Line2/24/2023 DISIS STAGE   
GEN-2022-159DISIS-2022-00105 SOUTHWESTChaves and LeaNMNEET5/1/202812/1/2027  280280280ER/NR000WindCrossroads - Hobbs 345 kV Line2/24/2023 DISIS STAGE   
GEN-2022-156DISIS-2022-00104 SOUTHEASTCreekOKGRDA9/15/202612/31/2026  100100100ER000Battery/StorageSilver City 138 kV Substation2/24/2023 DISIS STAGE   
GEN-2022-155DISIS-2022-00104 SOUTHEASTOklahomaOKOGE9/15/202612/31/2026  200200200ER000Battery/StorageHorseshoe Lake 138 kV Substation2/24/2023 DISIS STAGE   
GEN-2022-154DISIS-2022-00104 SOUTHEASTClevelandOKWFEC9/15/202612/31/2026  100100100ER000Battery/StorageCanadian Switch 138 kV Substation2/24/2023 DISIS STAGE   
GEN-2022-152DISIS-2022-00102 NEBRASKARichardsonNENPPD5/10/20268/21/2026  808080ER/NR000Battery/StorageHumboldt 161 kV Substation2/23/2023 DISIS STAGE   
GEN-2022-150DISIS-2022-00105 SOUTHWESTRandallTXSPS5/10/20268/21/2026  150171171ER/NR000Battery/StorageRandall 115 kV Substation2/23/2023 DISIS STAGE   
GEN-2022-147DISIS-2022-00105 SOUTHWESTHaleTXSPS2/27/20244/15/2025  203196203ER000ThermalCTGTuco 345kV2/21/2023 DISIS STAGE   
GEN-2022-145DISIS-2022-00104 SOUTHEASTClusterOKAEP9/15/202712/31/2027  195195195ER000Battery/StorageWeatherford Jct. to Hinton 138 kV line2/21/2023 DISIS STAGE   
GEN-2022-144DISIS-2022-00103 CENTRALJacksonMOKCPL9/15/202712/31/2027  200210.4210.4ER000Battery/StorageBlue Mills BESS 161kV Substation2/21/2023 DISIS STAGE   
GEN-2022-143DISIS-2022-00104 SOUTHEASTMarshallOKOGE9/15/202712/31/2027  200210.4210.4ER000Battery/StorageCaney Creek 138 kV Substation2/21/2023 DISIS STAGE   
GEN-2022-142DISIS-2022-00103 CENTRALClayMOKCPL9/15/202712/31/2027  200210.4210.4ER000Battery/StorageShoal Creek 161 kV Substation2/21/2023 DISIS STAGE   
GEN-2022-139DISIS-2022-00104 SOUTHEASTHarrisonTXAEP9/15/202712/31/2027  300315.7315.7ER000Battery/StoragePirkey 345kV Substation2/21/2023 DISIS STAGE   
GEN-2022-138DISIS-2022-00104 SOUTHEASTRogerOKAEP9/15/202712/31/2027  300316.6316.6ER000Battery/StorageTulsa North - Northeast Station 345 kV Substation2/21/2023 DISIS STAGE   
GEN-2022-137DISIS-2022-00104 SOUTHEASTClevelandOKWFEC9/15/202712/31/2027  200210.4210.4ER000Battery/StorageCanadian Switchyard 138kV2/21/2023 DISIS STAGE   
GEN-2022-136DISIS-2022-00104 SOUTHEASTBryanOKWFEC9/15/202712/31/2027  200210.5210.5ER000Battery/StorageColbert 138 kV Substation2/21/2023 DISIS STAGE   
GEN-2022-135DISIS-2022-00105 SOUTHWESTLeaNMSPS9/15/202712/31/2027  150155.1155.1ER000Battery/StorageTaylor Switching Station 115kV2/21/2023 DISIS STAGE   
GEN-2022-132DISIS-2022-00104 SOUTHEASTCaddoOKWFEC9/15/202712/31/2027  300315.8315.8ER000Battery/StorageAnadarko 138kV Substation 2/21/2023 DISIS STAGE   
GEN-2022-131DISIS-2022-00103 CENTRALJohnsonMOKCPL9/15/202712/31/2027  200200200ER000Battery/StorageWarrensburg East - Odessa161kV Substation2/21/2023 DISIS STAGE   
GEN-2022-130DISIS-2022-00104 SOUTHEASTSebastianAROGE9/15/202712/31/2027  200200200ER000Battery/StorageBattlefield BESS 161kV2/21/2023 DISIS STAGE   
GEN-2022-129DISIS-2022-00104 SOUTHEASTOsageOKAEP9/15/202712/31/2027  200200200ER000Battery/StorageWebb City Tap - Shidler 138 kV line2/21/2023 DISIS STAGE   
GEN-2022-128DISIS-2022-00105 SOUTHWESTEddyNMSPS9/15/202712/31/2027  150150150ER000Battery/StoragePecos Interchange 115 kV Substation 2/21/2023 DISIS STAGE   
GEN-2022-114DISIS-2022-00105 SOUTHWESTTillmanOKAEP12/1/202712/31/2027  250250250ER/NR000WindLawton to Oklaunion 345kV Line2/16/2023 DISIS STAGE   
GEN-2022-113DISIS-2022-00103 CENTRALNewtonMOEDE4/1/202612/31/2027  200200200ER/NR000SolarTipton Station 161 kV Substation2/16/2023 DISIS STAGE   
GEN-2022-111DISIS-2022-00104 SOUTHEASTMarionTXAEP6/30/20269/30/2026  150150150ER/NR000HybridSolar/StorageWilkes 345 kV Substation2/10/2023 DISIS STAGE   
GEN-2022-110DISIS-2022-00104 SOUTHEASTCoalOKAEP1/30/20264/30/2026  150150150ER/NR000Battery/StorageLehigh 138kV Station2/10/2023 DISIS STAGE   
GEN-2022-109DISIS-2022-00105 SOUTHWESTLeaNMSPS5/1/202610/1/2026  150150150ER/NR000SolarHobbs - Yoakum 345 kV transmission line1/6/2023 DISIS STAGE   
GEN-2022-108DISIS-2022-00104 SOUTHEASTDeSoto ParishLAAEP9/1/202712/31/2027  100100100ER/NR000SolarTap between 345kV SW Shreveport to Dolet Hills Substations1/8/2023 DISIS STAGE   
GEN-2022-107DISIS-2022-00105 SOUTHWESTTillmanOKAEP3/1/20267/31/2026  400400400ER/NR000SolarTap of Oklaunion to Lawton Eastside 345 kV Transmission Line1/9/2023 DISIS STAGE   
GEN-2022-106DISIS-2022-00105 SOUTHWESTTillmanOKAEP3/1/20267/31/2026  300300300ER/NR000SolarTap of Oklaunion to Lawton Eastside 345 kV Transmission Line1/9/2023 DISIS STAGE   
GEN-2022-105DISIS-2022-00105 SOUTHWESTTillmanOKAEP3/1/20267/31/2026  300300300ER/NR000SolarTap of Oklaunion to Lawton Eastside 345 kV Transmission Line1/9/2023 DISIS STAGE   
GEN-2022-104DISIS-2022-00104 SOUTHEASTBryanOKWFEC11/3/20252/2/2026  113.078113.078113.078ER/NR000SolarBrown - South Coleman Junction 138kV line1/26/2023 DISIS STAGE   
GEN-2022-103DISIS-2022-00103 CENTRALChristianMOEDE10/1/20261/1/2027  74.9974.9974.99ER/NR000Battery/StorageOzark South 161kV 1/30/2023 DISIS STAGE   
GEN-2022-102DISIS-2022-00103 CENTRALClayMOKCPL10/1/20261/1/2027  100100100ER/NR000Battery/StorageLiberty West 161 kV1/6/2023 DISIS STAGE   
GEN-2022-100DISIS-2022-00103 CENTRALCooper MOKCPL8/1/202510/1/2026  808080ER/NR000HybridSolar/StorageOverton - Sedalia East 161 kV Substation3/24/2023 DISIS STAGE   
GEN-2022-098DISIS-2022-00104 SOUTHEASTJohnston OKOGE3/1/202412/1/2024  200200200ER/NR000SolarBison 345kV Substation12/6/2022 DISIS STAGE   
GEN-2022-094DISIS-2022-00103 CENTRALOsborne KSITCGP5/27/202812/31/2028  250250250ER000WindPostrock to Axtell 345 kV line11/15/2022 DISIS STAGE   
GEN-2022-093DISIS-2022-00104 SOUTHEASTHempsteadARAEP10/1/20264/1/2027  838383ER/NR000SolarTurk - Hope 115 kV line11/15/2022 DISIS STAGE   
GEN-2022-092DISIS-2022-00104 SOUTHEASTNowata and CraigOKAEP9/1/202612/15/2026  299.2299.2299.2ER/NR000WindNeosho-Delaware 345 kV11/15/2022 DISIS STAGE   
GEN-2022-091DISIS-2022-00104 SOUTHEASTMcCurtainOKAEP9/30/20269/30/2026  150150150ER/NR000Battery/StorageValiant Substation 138kV11/15/2022 DISIS STAGE   
GEN-2022-090DISIS-2022-00104 SOUTHEASTMcCurtainOKAEP9/30/20269/30/2026  150150150ER/NR000SolarValiant Substation 138kV11/15/2022 DISIS STAGE   
GEN-2022-089DISIS-2022-00104 SOUTHEASTLittle RiverARAEP9/30/20269/30/2026  74.9974.9974.99ER/NR000Battery/StorageSouth Foreman 138 kV Substation 11/15/2022 DISIS STAGE   
GEN-2022-088DISIS-2022-00104 SOUTHEASTLittle RiverARAEP9/30/20269/30/2026  74.9974.9974.99ER/NR000SolarSouth Foreman 138 kV Substation 11/15/2022 DISIS STAGE   
GEN-2022-085DISIS-2022-00104 SOUTHEASTOfuskee and HughesOKOGE9/1/202512/31/2025  241.4241.4241.4ER/NR000WindSeminole to Muskogee 345kV Substation11/5/2022 DISIS STAGE   
GEN-2022-083DISIS-2022-00101 NORTHWilliamsNDBEPC6/1/20252/1/2025  250250265ER000ThermalCTGJudson Substation 345 kV10/21/2022 DISIS STAGE   
GEN-2022-082DISIS-2022-00105 SOUTHWESTHaleTXSPS4/1/202512/31/2028  180180180ER/NR000SolarTuco - Carlisle 230 kV line9/22/2022 DISIS STAGE   
GEN-2022-081DISIS-2022-00103 CENTRALWashington KSSUNC4/1/202511/29/2027  218218218ER/NR000Battery/StorageClifton 115kV Substation 9/22/2022 DISIS STAGE   
GEN-2022-080DISIS-2022-00103 CENTRALCedarMOEDE1/1/202610/31/2027  969696ER000Battery/StorageDadeville East - Bolivar South 161kV 9/22/2022 DISIS STAGE   
GEN-2022-079DISIS-2022-00103 CENTRALCedarMOEDE1/1/202610/31/2027  192192192ER000SolarDadeville East - Bolivar South 161kV9/22/2022 DISIS STAGE   
GEN-2022-077DISIS-2022-00102 NEBRASKAChaseNENPPD1/1/202612/1/2026  255255255ER/NR000SolarEnders 115 kV Substation9/21/2022 DISIS STAGE   
GEN-2022-076DISIS-2022-00103 CENTRALStevensKSSPS3/15/202611/15/2026  500500500ER/NR000SolarCarpenter 345 kV Substation9/7/2022 DISIS STAGE   
GEN-2022-075DISIS-2022-00103 CENTRALEllisKSITCGP9/3/202711/19/2027  175175175ER/NR000SolarTap on the Spearville - Post Rock 345kV line9/2/2022 DISIS STAGE   
GEN-2022-074DISIS-2022-00104 SOUTHEASTEufaula, McIntoshOKWFEC3/1/202510/31/2025  220.86220.86220.86ER/NR000WindHanna 138kV Substation9/6/2022 DISIS STAGE   
GEN-2022-073DISIS-2022-00103 CENTRALKayMOKCPL4/1/202512/31/2027  300300300ER/NR000Battery/StorageNashua 161 kV Substation9/2/2022 DISIS STAGE   
GEN-2022-072DISIS-2022-00104 SOUTHEASTMayesOKGRDA7/1/202512/31/2028  181181181ER/NR000SolarGrand River Dam - Claremore 161 kV Line8/12/2022 DISIS STAGE   
GEN-2022-071DISIS-2022-00104 SOUTHEASTPittsburgOKAEP11/3/20252/2/2026  90.82490.82490.824ER/NR000SolarTalawanda to Canadian River 138 kV Line Tap8/12/2022 DISIS STAGE   
GEN-2022-068DISIS-2022-00101 NORTHHydeSDBEPC7/1/202611/1/2026  250250250ER/NR000WindChappelle Creek 345 kV8/11/2022 DISIS STAGE   
GEN-2022-065DISIS-2022-00103 CENTRALEdwardsKSSUNC9/4/202711/19/2027  145145145ER/NR000Solartap on Arthur Mullergreen-Spearville 230 kV line7/25/2022 DISIS STAGE   
GEN-2022-062DISIS-2022-00103 CENTRALBourbonKSNEET4/1/202512/31/2025  200200200ER/NR000SolarWolf Creek- Blackberry 345 kV7/8/2022 DISIS STAGE   
GEN-2022-058DISIS-2022-00103 CENTRALBentonAREDE7/1/202812/31/2028  180180180ER/NR000SolarNoel Southwest - Decatur 161 kV line tap6/23/2022 DISIS STAGE   
GEN-2022-055DISIS-2022-00104 SOUTHEASTGradyOKWFEC4/1/202512/31/2025  200200200ER000SolarSunshine North to Anadarko 138 kV6/23/2022 DISIS STAGE   
GEN-2022-054DISIS-2022-00103 CENTRALBourbonKSNEET4/1/202512/31/2025  200200200ER000SolarWolf Creek - Blackberry 345 kV Tap6/23/2022 DISIS STAGE   
GEN-2022-048DISIS-2022-00104 SOUTHEASTWoodwardOKWFEC4/1/202512/31/2025  250250250ER000WindMooreland 138 kV6/23/2022 DISIS STAGE   
GEN-2022-042DISIS-2022-00104 SOUTHEASTCarterOKOGE4/1/202512/31/2025  174174174ER/NR000SolarSunnyside to Pooleville 138 kV line6/23/2022 DISIS STAGE   
GEN-2022-041DISIS-2022-00103 CENTRALCowleyKSGHP4/1/202512/31/2025  100100100ER/NR000SolarTie Substation 69 kV6/29/2022 DISIS STAGE   
GEN-2022-038DISIS-2022-00104 SOUTHEASTHarrisonTXAEP4/1/202512/31/2025  200200200ER000SolarLongwood to Scottville 138 kV line6/23/2022 DISIS STAGE   
GEN-2022-026DISIS-2022-00103 CENTRALDecaturKSSUNC6/1/202412/31/2025  200200200ER/NR000SolarTap of Mingo--Red Willow 345kV line6/8/2022 DISIS STAGE   
GEN-2022-025DISIS-2022-00103 CENTRALDecaturKSSUNC6/1/202412/31/2025  200200200ER/NR000SolarTap of Mingo--Red Willow 345kV line6/8/2022 DISIS STAGE   
GEN-2022-024DISIS-2022-00103 CENTRALBourbonKSWERE6/1/202412/31/2025  200200200ER/NR000Battery/StorageTap of Neosho - LaCygne 345 kV Line6/10/2022 DISIS STAGE   
GEN-2022-021DISIS-2022-00105 SOUTHWESTTillmanOKAEP6/1/202412/31/2025  100100100ER/NR000Battery/StorageTap of Oklaunion - Lawton Eastside 345 kV line6/8/2022 DISIS STAGE   
GEN-2022-019DISIS-2022-00105 SOUTHWESTTillman OKAEP6/1/202412/31/2025  100100100ER/NR000Battery/StorageTap of Oklaunion - Lawton Eastside 345 kV line6/8/2022 DISIS STAGE   
GEN-2022-017DISIS-2022-00104 SOUTHEASTWoodwardOKOGE6/6/202412/31/2025  150150150ER/NR000Battery/StorageWoodward 345kV Substation6/8/2022 DISIS STAGE   
GEN-2022-016DISIS-2022-00104 SOUTHEASTWoodwardOKOGE6/1/202412/31/2025  288288288ER/NR000SolarWoodward 345kV Substation6/8/2022 DISIS STAGE   
GEN-2022-015DISIS-2022-00103 CENTRALDecaturKSSUNC6/1/202412/31/2025  270270270ER/NR000SolarTap of Mingo - Red Willow 345 kV Line6/8/2022 DISIS STAGE   
GEN-2022-013DISIS-2022-00103 CENTRALBourbonKSWERE6/1/202412/31/2025  300300300ER/NR000SolarTap of Neosho - LaCygne 345 kV Line6/8/2022 DISIS STAGE   
GEN-2022-012DISIS-2022-00104 SOUTHEASTWoodward OKOGE6/1/202412/31/2025  100100100ER/NR000Battery/StorageWoodward 345 kV Substation6/8/2022 DISIS STAGE   
GEN-2022-011DISIS-2022-00105 SOUTHWESTTillmanOKAEP6/1/202412/31/2025  374374374ER/NR000SolarTap of Oklaunion - Lawton Eastside 345 kV line6/3/2022 DISIS STAGE   
GEN-2022-010DISIS-2022-00101 NORTHWilliamsNDBEPC7/1/20232/1/2025  250250250ER000ThermalJudson Substation 345 kV5/26/2022 DISIS STAGE   
GEN-2022-009DISIS-2022-00101 NORTHWilliamsNDBEPC7/1/20232/1/2025  125125125ER000ThermalJudson Substation 345 kV5/26/2022 DISIS STAGE   
GEN-2022-007DISIS-2022-00103 CENTRALLyonKSWERE5/1/202510/31/2026  135135135ER/NR000SolarLang - Reading 115 kV Transmission Line5/26/2022 DISIS STAGE   
GEN-2022-006DISIS-2022-00103 CENTRALLabetteKSWERE4/1/202510/31/2026  200200200ER/NR000SolarNeosho - N345 161 kV Substation5/25/2022 DISIS STAGE   
GEN-2022-005DISIS-2022-00103 CENTRALLabetteKSWERE4/1/202510/31/2026  200200200ER/NR000SolarNortheast Parsons 138kV Substation5/25/2022 DISIS STAGE   
GEN-2022-004DISIS-2022-00103 CENTRALSedgwickKSWERE8/1/202510/31/2026  333333ER/NR000SolarMurray Gill 138 kV Substation5/26/2022 DISIS STAGE   
GEN-2022-001DISIS-2022-00104 SOUTHEASTRogersOKAEP9/26/20261/7/2027  100100100ER/NR000Battery/StorageCatoosa 138 kV Substation12/30/2021 DISIS STAGE   
GEN-2021-SR9SurplusKansas CityMOKCPL 1/11/2023  101010ER/NR000SolarHawthorn Power Plant8/24/2021 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2021-SR8Surplus03 CENTRALHarperKSWERE11/1/202311/1/2023  424242ER000SolarViola 345kV5/13/2021 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2021-108DISIS-2021-00102 NEBRASKACassNEOPPD5/27/20255/14/2025  182.25182.25182.25ER/NR000SolarOPPD 345KV Cass County Substation5/20/2021 DISIS STAGE   
GEN-2021-107DISIS-2021-00103 CENTRALPottawatomieKSWERE10/1/202612/1/2026  201.6201.6201.6ER000SolarEvergy 345kV Jeffrey Energy Center5/20/2021 DISIS STAGE   
GEN-2021-103DISIS-2021-00103 CENTRALJohnsonKSWERE8/1/20259/1/2026  150150150ER/NR000Battery/StorageEvergy's Atlantic Substation115kV bus5/25/2021 DISIS STAGE   
GEN-2021-101DISIS-2021-00103 CENTRALDouglasKSWERE8/1/20259/1/2025  159159159ER/NR000SolarEvergy's Midland Substation 115kV bus5/25/2021 DISIS STAGE   
GEN-2021-098DISIS-2021-00104 SOUTHEASTDeweyOKOGE7/1/202612/31/2026  160160160ER/NR000HybridWind/StorageDewey District 138 kV Substation5/24/2021 DISIS STAGE   
GEN-2021-096DISIS-2021-00103 CENTRALCoffeyKSWERE5/1/202612/1/2027  500500500ER/NR000SolarWolf Creek - Benton 345 kV4/29/2021 DISIS STAGE   
GEN-2021-090DISIS-2021-00105 SOUTHWESTYoakumTXSPS6/15/20226/30/2028  400400400ER/NR000HybridSolar/StorageYoakum 345kV Substation4/30/2021 DISIS STAGE   
GEN-2021-088DISIS-2021-00104 SOUTHEASTClevelandOKOGE12/21/20251/7/2027  100100100ER/NR000Battery/StorageCedar Lane - Canadian 138 kV Transmission Line4/29/2021 DISIS STAGE   
GEN-2021-077DISIS-2021-00103 CENTRALPettisMOGMO7/1/202512/31/2027  959595ER/NR000HybridSolar/StorageWindsor to AEC Sedalia 161 kV4/30/2021 DISIS STAGE   
GEN-2021-076DISIS-2021-00103 CENTRALEllisKSITCGP7/1/202612/31/2026  113113113ER/NR000SolarITC Post Rock 345 kV Substation5/13/2021 DISIS STAGE   
GEN-2021-075DISIS-2021-00104 SOUTHEASTCampTXAEP7/1/202612/31/2027  300300300ER/NR000HybridSolar/StorageCAMPCOR4 138kV Substation 5/19/2021 DISIS STAGE   
GEN-2021-070DISIS-2021-00103 CENTRALHodgeman and FordKSSUNC8/1/202712/1/2027  504504504ER000WindSUNC Spearville - Holcomb 345kV4/26/2021 DISIS STAGE   
GEN-2021-069DISIS-2021-00103 CENTRALHodgeman and FordKSSUNC8/1/202712/1/2027  249.6249.6249.6ER000WindSUNC Spearville - Holcomb 345kV4/26/2021 DISIS STAGE   
GEN-2021-068DISIS-2021-00103 CENTRALHodgeman and FordKSSUNC9/1/202512/1/2027  249.6249.6249.6ER000WindSUNC Spearville - Holcomb 345kV4/26/2021 DISIS STAGE   
GEN-2021-064DISIS-2021-00104 SOUTHEASTCaddoOKAEP10/25/202512/31/2027  100100100ER/NR000HybridSolar/StorageCarnegie South 138kV4/28/2021 DISIS STAGE   
GEN-2021-063DISIS-2021-00104 SOUTHEASTMcCurtainOKAEP10/25/202512/31/2027  155155155ER/NR000HybridSolar/StorageCraig JCT 138kV4/28/2021 DISIS STAGE   
GEN-2021-057DISIS-2021-00102 NEBRASKAAntelopeNENPPD 12/31/2027  300300300ER000WindAntelope 345kV substation4/29/2021 DISIS STAGE   
GEN-2021-056DISIS-2021-00103 CENTRALHarper and KingmanKSWERE 12/31/2028  300300300ER000WindViola 345kV Substation4/29/2021 DISIS STAGE   
GEN-2021-053DISIS-2021-00104 SOUTHEASTMuskogeeOKOGE 5/30/2026  300300300ER000SolarPecan Creek 345 kV Substation4/29/2021 DISIS STAGE   
GEN-2021-052DISIS-2021-00104 SOUTHEASTMuskogeeOKOGE 5/30/2026  757575ER000Battery/StoragePecan Creek 345kV substation4/29/2021 DISIS STAGE   
GEN-2021-051DISIS-2021-00103 CENTRALHenryMOKCPL7/31/20259/1/2027  757575ER/NR000Battery/Storage161kV Stilwell-Clinton Line4/30/2021 DISIS STAGE   
GEN-2021-050DISIS-2021-00103 CENTRALHenryMOKCPL7/31/20259/1/2028  200200200ER/NR000Solar161kV Stilwell-Clinton Line4/30/2021 DISIS STAGE   
GEN-2021-049DISIS-2021-00102 NEBRASKALancasterNELES7/31/20259/1/2027  225225225ER/NR000SolarWagener 115kV Substation4/30/2021 DISIS STAGE   
GEN-2021-048DISIS-2021-00102 NEBRASKALancasterNELES7/31/20259/1/2027  757575ER/NR000Battery/StorageWagener 115kV Substation4/30/2021 DISIS STAGE   
GEN-2021-047DISIS-2021-00104 SOUTHEASTMayesOKGRDA3/1/20269/30/2029  250250250ER000SolarTulsa (Bus #509852) - Igloo (Bus #513596) 345kV line4/29/2021 DISIS STAGE   
GEN-2021-043DISIS-2021-00102 NEBRASKALancasterNELES2/1/20265/31/2028  250250250ER000Battery/Storage8000 SW 12th (Rokeby) Station, 115kV Bus4/30/2021 DISIS STAGE   
GEN-2021-042DISIS-2021-00103 CENTRALJackson MOINDN2/1/20256/1/2028  50100100ER/NR000Battery/StorageIndependence Power & Light, Blue Valley Substation, 161kV Bus4/30/2021 DISIS STAGE   
GEN-2021-041DISIS-2021-00104 SOUTHEASTCanadianOKOGE2/1/20256/1/2026  100100.657100.657ER/NR000Battery/StorageMustang 138kV Substation4/30/2021 DISIS STAGE   
GEN-2021-040DISIS-2021-00102 NEBRASKACassNEOPPD2/1/202511/30/2029  200200200ER000Battery/StorageOPPD District, Cass County Power Plant Substation, 345kV Bus4/30/2021 DISIS STAGE   
GEN-2021-039DISIS-2021-00102 NEBRASKADouglasNEOPPD2/1/20255/31/2030  100100100ER000Battery/StorageNew 161kV substation looping in OPPD 161kV lines S1211 to S1220 and S1211 to S12994/30/2021 DISIS STAGE   
GEN-2021-038DISIS-2021-00104 SOUTHEASTTitusTXAEP2/1/20265/31/2028  200201.32201.32ER/NR000Battery/StorageWelsh 345kV Substation4/30/2021 DISIS STAGE   
GEN-2021-036DISIS-2021-00104 SOUTHEASTLittle RiverARAEP10/29/202512/31/2027  204.12204.12204.12ER/NR000SolarCraig to Patterson 138 kV Transmission Line5/14/2021 DISIS STAGE   
GEN-2021-035DISIS-2021-00103 CENTRALGrantKSSUNC10/29/202512/31/2026  113113113ER000SolarTap Sunflower Santana 115kV Transmission Line5/14/2021 DISIS STAGE   
GEN-2021-034DISIS-2021-00102 NEBRASKALancasterNELES10/31/202712/31/2027  113113113ER000SolarRokeby 115 kV Substation5/13/2021 DISIS STAGE   
GEN-2021-033DISIS-2021-00104 SOUTHEASTFranklinAROGE7/1/202712/31/2027  204.12204.12204.12ER000SolarBranch 161kV Substation 5/14/2021 DISIS STAGE   
GEN-2021-030DISIS-2021-00103 CENTRALLinn KS and Bates MOKSKCPL9/28/202612/31/2026  510.3510.3510.3ER000SolarEvergy Tap the La Cygne to Stillwel 345 kV Line5/14/2021 DISIS STAGE   
GEN-2021-029DISIS-2021-00103 CENTRALLinn KS and Bates MOKSKCPL7/1/202612/31/2026  253.8253.8253.8ER000Battery/StorageEvergy Tap the La Cygne to Stillwel 345 kV Line5/14/2021 DISIS STAGE   
GEN-2021-027DISIS-2021-00102 NEBRASKALancasterNENPPD7/1/202612/31/2026  102.06102.06102.06ER000SolarOlive Creek 115 kV Substation5/14/2021 DISIS STAGE   
GEN-2021-025DISIS-2021-00104 SOUTHEASTWoodwardOKWFEC10/31/202512/1/2026  203.04203.04203.04ER000WindWestern Farmers 138kV Mooreland Substation5/14/2021 DISIS STAGE   
GEN-2021-023DISIS-2021-00103 CENTRALGrantKSWERE9/30/202611/30/2026  306.18306.18306.18ER000SolarWild Plains 345kV Substation5/14/2021 DISIS STAGE   
GEN-2021-021DISIS-2021-00103 CENTRALStevensKSSPS9/1/202612/31/2027  150150150ER000WindCarpenter 345 kV Substation4/20/2021 DISIS STAGE   
GEN-2021-019DISIS-2021-00104 SOUTHEASTNobleOKOGE4/1/202712/31/2028  74.975.8975.89ER/NR000Battery/StorageSooner 345 kV4/30/2021 DISIS STAGE   
GEN-2021-018DISIS-2021-00104 SOUTHEASTNobleOKOGE4/1/202712/31/2028  231235.35235.35ER000SolarSooner 345 kV4/30/2021 DISIS STAGE   
GEN-2021-017DISIS-2021-00103 CENTRALCloud and MitchellKSITCGP4/1/202512/31/2027  37.537.537.5ER000WindElm Creek 345 kV interconnection substation4/30/2021 DISIS STAGE   
GEN-2021-016DISIS-2021-00104 SOUTHEASTJohnston and MurrayOKAEP4/1/202512/31/2029  250250250ER000WindSunnyside-Johnston 345 kV4/30/2021 DISIS STAGE   
GEN-2021-015DISIS-2021-00104 SOUTHEASTEllisOKOGE4/1/202712/1/2028  74.975.9175.91ER000SolarBobcat 345 kV interconnection substation4/30/2021 DISIS STAGE   
GEN-2021-014DISIS-2021-00104 SOUTHEASTBeckhamOKOGE4/1/202712/31/2029  208233.98233.98ER000SolarBorder 345 kV interconnection substation4/30/2021 DISIS STAGE   
GEN-2021-012DISIS-2021-00104 SOUTHEASTBeckhamOKOGE11/15/202312/31/2029  203227227ER000Battery/StorageBorder 345 kV interconnection substation4/30/2021 DISIS STAGE   
GEN-2021-010DISIS-2021-00104 SOUTHEASTBeckhamOKOGE4/1/202712/31/2029  208233.98233.98ER000SolarBorder 345 kV interconnection substation4/30/2021 DISIS STAGE   
GEN-2021-008DISIS-2021-00101 NORTHMcKenzieNDBEPC5/9/202610/19/2030  200200200ER/NR000Solar345kV Bus at BEPC Patent Gate Substation, McKenzie County, ND5/10/2021 DISIS STAGE   
GEN-2021-006DISIS-2021-00103 CENTRALLabetteKSWERE10/1/20252/1/2026  300300300ER/NR000Battery/StorageNeosho 345kV substation in Labette County, KS5/7/2021 DISIS STAGE   
GEN-2021-005DISIS-2021-00103 CENTRALSalineKSWERE11/1/20243/1/2025  350350350ER/NR000Battery/StorageSummit 345 kV substation in Saline County, KS5/7/2021 DISIS STAGE   
GEN-2021-001DISIS-2021-00104 SOUTHEASTBryanOKOGE9/25/202412/24/2027  100100100ER/NR000Battery/Storage138kV Brown Substation12/29/2020 DISIS STAGE   
GEN-2020-SR2Surplus04 SOUTHEASTJohnstonOKOGE12/1/20213/31/2026  100100100ER/NR000Battery/StorageBrown 138kV8/4/2020 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2020-094DISIS-2020-00102 NEBRASKASyracuseNEOPPD4/2/202312/24/2026  250250250ER/NR000SolarNeb. City - 103rd & Rokeby 345 kV4/30/2020 DISIS STAGE   
GEN-2020-092DISIS-2020-00104 SOUTHEASTMayes CountyOKAEP11/2/202511/19/2026  100100100ER/NR000SolarPryor Junction - Midwest Carbide 138kV line 4/30/2020 DISIS STAGE   
GEN-2020-091DISIS-2020-00101 NORTHMcKenzieNDBEPC11/2/202511/19/2026  150150150ER/NR000SolarPatent Gate Substation 345 kV4/30/2020 DISIS STAGE   
GEN-2020-090DISIS-2020-00103 CENTRALBourbonKSWERE4/1/202612/1/2026  204.3204.3204.3ER/NR000Battery/StorageWolf Creek - Blackberry 345 kV Substation4/27/2020 DISIS STAGE   
GEN-2020-088DISIS-2020-00103 CENTRALJasperMOEDE11/30/202212/31/2025  150150150ER/NR000SolarLa Russell 161 kV Substation4/30/2020 DISIS STAGE   
GEN-2020-087DISIS-2020-00104 SOUTHEASTComancheOKAEP5/1/202310/1/2026  500500500ER/NR000SolarCimmarron to Lawton 345 kV Line4/23/2020 DISIS STAGE   
GEN-2020-085DISIS-2020-00104 SOUTHEASTCarterOKAEP4/2/202310/1/2026  500500500ER/NR000SolarLawton to Sunnyside 345 kV Line4/23/2020 DISIS STAGE   
GEN-2020-084DISIS-2020-00102 NEBRASKABurtNEOPPD4/1/202210/31/2026  350350350ER/NR000SolarRaun - Fort Calhoun 345 kV4/30/2020 DISIS STAGE   
GEN-2020-083DISIS-2020-00101 NORTHFairviewMTWAPA10/1/202412/1/2026  74.574.574.5ER/NR000HybridSolar/StorageFairview 115kV Substation4/30/2020 DISIS STAGE   
GEN-2020-081DISIS-2020-00104 SOUTHEASTRuskTXAEP5/1/20226/1/2028  200200200ER/NR000Battery/StorageTenaska Switching Substation 345kV4/30/2020 DISIS STAGE   
GEN-2020-079DISIS-2020-00103 CENTRALCherokee KSEDE7/1/202512/31/2025  225225225ER/NR000HybridSolar/StorageRiverton-Neosho 161kV line4/30/2020 DISIS STAGE   
GEN-2020-078DISIS-2020-00102 NEBRASKAWashingtonNEOPPD11/30/202212/31/2025  100100100ER/NR000SolarSubstation 1226 to Substation 1237, 161kV Tap4/30/2020 DISIS STAGE   
GEN-2020-075DISIS-2020-00104 SOUTHEASTComancheOKAEP5/1/202310/1/2026  200200200ER/NR000Battery/StorageCimmarron to Lawton 345 kV Line4/28/2020 DISIS STAGE   
GEN-2020-074DISIS-2020-00104 SOUTHEASTCarterOKAEP3/31/202310/1/2026  200200200ER/NR000Battery/StorageLawton to Sunnyside 345 kV Substation4/28/2020 DISIS STAGE   
GEN-2020-073DISIS-2020-00103 CENTRALFranklinKSKCPL7/1/202512/1/2027  150150150ER/NR000HybridSolar/StorageSE Ottawa to Pleasant Valley 161kV4/30/2020 DISIS STAGE   
GEN-2020-072DISIS-2020-00103 CENTRALWindsorMOGMO7/1/202512/1/2027  150150150ER/NR000HybridSolar/StorageWindsor to AEC Sedalia 161 kV line4/30/2020 DISIS STAGE   
GEN-2020-069DISIS-2020-00102 NEBRASKACherryNENPPD11/30/202311/30/2025  52.8552.8552.85ER/NR000WindCody to Valentine 115kV line4/24/2020 DISIS STAGE   
GEN-2020-068DISIS-2020-00105 SOUTHWESTTerry & HockleyTXSPS11/1/202412/1/2026  400400400ER000SolarTuco to Yoakum 345kV line4/29/2020 DISIS STAGE   
GEN-2020-067DISIS-2020-00105 SOUTHWESTTerry & HockleyTXSPS11/1/202412/1/2026  352.5352.5352.5ER000WindTuco to Yoakum 345kV line4/24/2020 DISIS STAGE   
GEN-2020-065DISIS-2020-00105 SOUTHWESTGainesNMSPS12/1/20255/15/2028  1003912.31003ER000ThermalCombined CycleHobbs-Andrews 345 kV Line4/30/2020 DISIS STAGE   
GEN-2020-064DISIS-2020-00103 CENTRALJoplinMOEDE10/1/20205/17/2021  643664ER/NR000ThermalCT4544 Stateline CC 161kV Substation4/22/2020 DISIS STAGE   
GEN-2020-062DISIS-2020-00105 SOUTHWESTCurryNMSPS11/1/20234/1/2028  256256256ER000SolarOASIS 230kV Substation4/29/2020 DISIS STAGE   
GEN-2020-061DISIS-2020-00103 CENTRALPleasant HillMOGMO5/1/20215/1/2022  292921ER/NR000ThermalGasPleasant Hill 345/161/69 kV Substation4/28/2020 DISIS STAGE   
GEN-2020-060DISIS-2020-00105 SOUTHWESTLubbockTXSPS5/1/20266/1/2027  200200200ER000Battery/StorageLubbock East Substation 230 kV4/30/2020 DISIS STAGE   
GEN-2020-059DISIS-2020-00105 SOUTHWESTLovingtonNMSPS3/2/20256/1/2027  250250250ER000HybridSolar/StorageTuco-Yoakum-Hobbs 345 kV4/29/2020 DISIS STAGE   
GEN-2020-058DISIS-2020-00103 CENTRALGarnerKSWERE11/1/20266/1/2028  424.5424.5424.5ER/NR000SolarAtlantic 345 kV Substation4/30/2020 DISIS STAGE   
GEN-2020-057DISIS-2020-00103 CENTRALGarnerKSWERE11/1/20266/1/2028  424.5424.5424.5ER/NR000Battery/StorageAtlantic 345 kV Substation4/30/2020 DISIS STAGE   
GEN-2020-056DISIS-2020-00103 CENTRALRussell CountyKSSUNC3/30/20231/3/2025  202020ER/NR000SolarRussell 115 kV Substation4/30/2020 DISIS STAGE   
GEN-2020-054DISIS-2020-00104 SOUTHEASTBowie CountyTXAEP8/1/20239/1/2026  298298298ER/NR000SolarLydia 345 kV Station4/27/2020 DISIS STAGE   
GEN-2020-045DISIS-2020-00102 NEBRASKADouglas CountyNEOPPD4/30/20238/1/2024  56.5256.5256.52ER000ThermalReciprocating EngineBetween Substation 1209 and 1252; 161kV4/29/2020 DISIS STAGE ViewView
GEN-2020-044DISIS-2020-00102 NEBRASKADouglas CountyNEOPPD4/30/20238/1/2024  56.5256.5256.52ER000ThermalReciprocating EngineBetween Substation 1209 and 1252; 161kV4/29/2020 DISIS STAGE ViewView
GEN-2020-043DISIS-2020-00102 NEBRASKADouglas CountyNEOPPD4/30/20238/1/2024  56.5256.5256.52ER000ThermalReciprocating EngineBetween Substation 1209 and 1252; 161kV4/29/2020 DISIS STAGE ViewView
GEN-2020-038DISIS-2020-00102 NEBRASKAPlattsmouthNEOPPD4/30/20234/21/2028  272.7258303ER000ThermalCTSubstation 3740; 345kV4/29/2020 DISIS STAGE   
GEN-2020-031DISIS-2020-00102 NEBRASKASarpy CountyNEOPPD4/30/20234/21/2028  272.7258303ER000ThermalCTSubstation 1363; 161kV Substation4/29/2020 DISIS STAGE   
GEN-2020-028DISIS-2020-00102 NEBRASKASarpy CountyNEOPPD4/30/20238/1/2024  255235255ER000ThermalCTSubstation 1363; 161kV Substation4/29/2020 DISIS STAGE ViewView
GEN-2020-025DISIS-2020-00102 NEBRASKASarpy CountyNEOPPD4/30/20238/1/2024  255235255ER000ThermalCTSubstation 1363; 161kV Substation4/29/2020 DISIS STAGE ViewView
GEN-2020-021DISIS-2020-00101 NORTHSioux CountyNDBEPC11/30/202312/31/2026  235235235ER/NR000WindLeLand Olds-Chapelle Creek 345kV line 4/24/2020 DISIS STAGE   
GEN-2020-020DISIS-2020-00104 SOUTHEASTMcCurtainOKAEP5/15/202512/15/2025  201.6201.6201.6ER/NR000HybridSolar/StorageTap the 345 kV Northwest Texarkana - Valliant line4/28/2020 DISIS STAGE   
GEN-2020-017DISIS-2020-00105 SOUTHWESTLamb CountyTXSPS10/1/202512/31/2025  74.8874.8874.88ER/NR000Solar230kV Lamb County Interchange4/24/2020 DISIS STAGE   
GEN-2020-014DISIS-2020-00101 NORTHAlexanderNDBEPC6/17/202110/18/2021  454545ER/NR000ThermalGasLonesome Creek 115kV4/20/2020 DISIS STAGE   
GEN-2020-013DISIS-2020-00102 NEBRASKAOrleansNENPPD10/15/20266/1/2027  215215215ER/NR000HybridSolar/StorageOrleans-Holdrege Substation 115kV4/10/2020 DISIS STAGE   
GEN-2020-012DISIS-2020-00104 SOUTHEASTHeadrickOKAEP10/15/20266/1/2027  113113113ER/NR000HybridSolar/StorageSnyder – Altus Jct. 138kV4/10/2020 DISIS STAGE   
GEN-2020-011DISIS-2020-00102 NEBRASKAFunkNENPPD10/15/20266/1/2027  320320320ER/NR000HybridSolar/StorageAxtell-Sweetwater Substation 345kV4/8/2020 DISIS STAGE   
GEN-2020-010DISIS-2020-00104 SOUTHEASTMutualOKWFEC10/15/20266/1/2027  140140140ER/NR000HybridSolar/StorageSeiling-Taloga Substations 138kV4/8/2020 DISIS STAGE   
GEN-2020-009DISIS-2020-00105 SOUTHWESTCottonOKAEP10/15/202612/31/2025  300300300ER/NR000HybridSolar/StorageLawton East Side to Oklaunion 345kV4/8/2020 DISIS STAGE   
GEN-2020-008DISIS-2020-00103 CENTRALStevens CountyKSSPS9/1/202312/31/2026  250250250ER000HybridSolar/StorageCorporation Carpenter 345kV Substation4/22/2020 DISIS STAGE   
GEN-2020-007DISIS-2020-00103 CENTRALLinn & BatesKSKCPL7/1/202312/31/2025  650650650ER/NR000HybridSolar/StorageEvergy La Cygne to Wolf Creek 345kV Substation4/22/2020 DISIS STAGE   
GEN-2020-003DISIS-2020-00103 CENTRALWinfieldKSKPP3/1/20236/1/2025  585858ER/NR000ThermalDiesel/GasEast Substation 69 kV4/1/2020 DISIS STAGE   
GEN-2020-002DISIS-2020-00102 NEBRASKAYutanNEOPPD11/15/20225/1/2024  818181ER000Solar6846 Substation 69 kV4/6/2020 DISIS STAGE ViewView
GEN-2019-073DISIS-2019-00102 NEBRASKAMadisonNENPPD12/31/202312/31/2027  100100100ER000SolarShell Creek-Hoskins 345kv Line5/24/2019 IA PENDING   
GEN-2019-070DISIS-2019-00102 NEBRASKAMadisonNENPPD12/31/202312/31/2027  505050ER000SolarShell Creek-Hoskins 345kv Line5/24/2019 IA PENDING   
GEN-2019-069DISIS-2019-00102 NEBRASKAMadisonNENPPD12/31/202312/31/2027  100100100ER000SolarShell Creek-Hoskins 345kV Line5/24/2019 IA PENDING   
GEN-2019-068DISIS-2019-00103 CENTRALBartonKSSUNC6/1/20235/1/2026  505050ER/NR000Battery/StorageGreat Bend - Circle 230kV line5/24/2019 FACILITY STUDY STAGE   
GEN-2019-065DISIS-2019-00104 SOUTHEASTSmithTXAEP6/1/202412/1/2026  180180180ER000Battery/StorageOverton-Northwest Henderson 138kV5/23/2019 IA PENDING   
GEN-2019-063DISIS-2019-00103 CENTRALFord, ClarkKSITCGP6/1/20235/1/2026  505050ER/NR000Battery/StorageClark County 345kV substation5/24/2019 IA PENDING   
GEN-2019-058DISIS-2019-00103 CENTRALFord, ClarkKSITCGP6/1/20235/1/2026  150150150ER/NR000SolarClark County 345kV substation5/24/2019 IA PENDING   
GEN-2019-055DISIS-2019-00103 CENTRALEdwards, PawneeKSSUNC6/1/20235/1/2026  150150150ER/NR000SolarGreat Bend-Spearville 230kV line5/24/2019 IA PENDING   
GEN-2019-054DISIS-2019-00103 CENTRALBartonKSSUNC6/1/20235/1/2026  150150150ER/NR000SolarGreat Bend- Circle 230kV line5/24/2019 FACILITY STUDY STAGE   
GEN-2019-053DISIS-2019-00103 CENTRALEdwards/PawneeKSSUNC6/1/20235/1/2026  505050ER/NR000Battery/StorageGreat Bend-Spearville 230kV line5/24/2019 IA PENDING   
GEN-2019-045DISIS-2019-00104 SOUTHEASTWoodsOKOGE12/31/202212/31/2027  155155155ER000SolarDeGrasse 138kV Substation5/24/2019 IA PENDING   
GEN-2019-044DISIS-2019-00103 CENTRALFordKSSUNC12/31/202312/15/2027  100100100ER000SolarNorth Fort Dodge 115kV Substation5/24/2019 IA PENDING   
GEN-2019-041DISIS-2019-00102 NEBRASKALancasterNENPPD12/1/202012/31/2026  787878ER/NR000Solar115kV Monolith Substation5/23/2019 IA PENDING   
GEN-2019-039DISIS-2019-00102 NEBRASKAButlerNENPPD5/16/20225/1/2025  174.5174.5174.5ER/NR000SolarColumbus Southeast-Rising City 115kV5/21/2019 IA PENDING   
GEN-2019-037DISIS-2019-00101 NORTHMercerNDBEPC12/1/202312/1/2027  150150150ER/NR000SolarLeland Olds 345kV substation5/17/2019 IA PENDING   
GEN-2019-030DISIS-2019-00103 CENTRALFordKSITCGP12/1/20213/31/2027  252252252ER/NR000WindSpearville to Clark County 345 kV line4/25/2019 IA PENDING   
GEN-2019-023DISIS-2019-00101 NORTHWibauxMTWAPA12/31/20236/1/2025  110110110ER/NR000HybridWind/StorageWAPA-UGP Mingusville 230kV5/8/2019 FACILITY STUDY STAGE   
GEN-2019-021DISIS-2019-00105 SOUTHWESTRooseveltNMSPS12/1/20226/1/2025  505050ER/NR000SolarRoosevelt 230kV Substation4/29/2019 IA PENDING   
GEN-2019-019DISIS-2019-00101 NORTHSiouxIANIPCO2/1/20202/16/2023  15.1515.1515.15ER/NR000ThermalGas TurbineSiouxland 69kV4/24/2019 FACILITY STUDY STAGE    
GEN-2019-018DISIS-2019-00103 CENTRALRiceKSMIDW3/1/20206/1/2021  15.5611.9715.56ER/NR000ThermalGas TurbineSaxman 115kV substation4/24/2019 IA PENDING   
GEN-2019-016DISIS-2019-00103 CENTRALPolk and DadeMOEDE11/30/202212/31/2026  200200200ER000SolarDadeville 161kV Substation 4/30/2019 IA PENDING   
GEN-2019-012DISIS-2019-00104 SOUTHEASTWoodwardOKOGE5/1/20235/1/2027  200200200ER/NR000Battery/StorageWoodward 345kV substation5/22/2019 IA PENDING   
GEN-2019-011DISIS-2019-00105 SOUTHWESTYoakumTXSPS5/1/20235/1/2025  207207207ER/NR000Battery/StorageYoakum 345kV Substation4/22/2019 IA PENDING   
GEN-2019-009DISIS-2019-00102 NEBRASKANemahaNEOPPD10/31/202211/30/2026  100100100ER000SolarS1263 Brock 161kV substation4/24/2019 IA PENDING   
GEN-2019-003DISIS-2019-00105 SOUTHWESTRooseveltNMSPS12/1/20226/1/2025  150150150ER/NR000SolarRoosevelt 230kV Substation4/19/2019 IA PENDING   
GEN-2019-002DISIS-2019-00104 SOUTHEASTMayesOKGRDA12/1/20206/1/2025  100100100ER000Battery/StorageMaid 161kV substation11/26/2018 IA PENDING   
GEN-2019-001DISIS-2019-00103 CENTRALPrattKSWERE12/31/201812/31/2026  252525ER000WindThistle-Wichita Dbl Ckt (Buffalo Flats) 345kV11/27/2018 IA PENDING   
GEN-2018-132DISIS-2018-00202 NEBRASKAPierceNENPPD12/31/202012/31/2026  201.6201.6201.6ER/NR000SolarAntelope - Hoskins 345 kV11/21/2018 IA PENDING   
GEN-2018-131DISIS-2018-00202 NEBRASKAPierceNENPPD12/31/202012/31/2026  221.4221.4221.4ER/NR000SolarAntelope - Hoskins 345 kV11/21/2018 IA PENDING   
GEN-2018-128DISIS-2018-00203 CENTRALSumnerKSWERE9/1/202110/1/2027  200.22200.22200.22ER/NR000WindRenfrow-Viola 345 kV11/19/2018 IA PENDING   
GEN-2018-125DISIS-2018-00202 NEBRASKALincolnNENPPD12/15/202212/1/2027  231231231ER/NR000WindNew switching station on Gentleman to Sweetwater 345kV line11/19/2018 IA PENDING   
GEN-2018-115DISIS-2018-00204 SOUTHEASTLawtonOKAEP12/1/202112/1/2027  250250250ER/NR000HybridSolar/StorageLawton East Side 345kV/138kv Substation11/21/2018 IA PENDING   
GEN-2018-108DISIS-2018-00203 CENTRALBarberKSITCGP12/31/202712/31/2027  959595ER000Battery/StorageThistle 345kV substation11/21/2018 IA PENDING   
GEN-2018-106DISIS-2018-00204 SOUTHEASTCaddoLAAEP12/31/202312/31/2027  165165165ER000SolarLongwood 345kV substation11/2/2018 IA PENDING   
GEN-2018-099DISIS-2018-00205 SOUTHWESTParmerTXSPS12/31/202312/31/2027  300300300ER000WindTolk 230kV Substation11/21/2018 IA PENDING   
GEN-2018-089DISIS-2018-00205 SOUTHWESTCastroTXSPS12/31/202312/31/2027  196196196ER000WindNewhart 230kV Substation11/21/2018 IA PENDING   
GEN-2018-083DISIS-2018-00202 NEBRASKAMadisonNENPPD12/31/202312/31/2027  250250250ER000WindShell Creek-Hoskins 345kv Line Break11/16/2018 IA PENDING   
GEN-2018-082DISIS-2018-00204 SOUTHEASTPittsburgOKAEP12/31/202312/31/2027  215215215ER000WindPittsburg 345kV Substation11/18/2018 IA PENDING   
GEN-2018-079DISIS-2018-00204 SOUTHEASTCraig/NovataOKAEP12/31/202312/31/2027  148148148ER000SolarFarmland-Delaware 138kV line11/18/2018 IA PENDING   
GEN-2018-074DISIS-2018-00201 NORTHCrawford and Carrol IAWAPA5/10/202210/31/2026  727272ER000WindDenison 230kV Substation10/31/2018 FACILITY STUDY STAGE   
GEN-2018-072DISIS-2018-00204 SOUTHEASTKayOKOGE11/30/202111/30/2025  151151151ER/NR000Battery/StorageInterconnecting into OG&E's Ranch Road 345kV substation by tapping a 0.1 gen tie line into the existing Frontier II gen-tie line10/26/2018 IA PENDING   
GEN-2018-071DISIS-2018-00204 SOUTHEASTKayOKOGE11/30/202111/30/2025  151151151ER/NR000Battery/StorageInterconnecting into OG&E's Ranch Road 345kV substation by tapping a 0.1 gen tie line into the existing Frontier II gen-tie line10/25/2018 IA PENDING   
GEN-2018-069DISIS-2018-00201 NORTHWibauxMTWAPA12/31/20206/1/2025  125125125ER/NR000WindWAPA-UGP Mingusville 230kV10/26/2018 FACILITY STUDY STAGE   
GEN-2018-068DISIS-2018-00202 NEBRASKAMadisonNENPPD9/1/202212/1/2027  302.4302.4302.4ER/NR000WindAntelope - Hoskins 345 kV Substation10/26/2018 IA PENDING   
GEN-2018-067DISIS-2018-00201 NORTHWilliamsNDMWEC10/30/202010/30/2026  255255255ER000Wind115kV Strandahl sub 10/25/2018 IA PENDING   
GEN-2018-065DISIS-2018-00202 NEBRASKAMadisonNENPPD7/1/202012/1/2027  19.819.819.8ER/NR000WindAntelope - Hoskins 345 kV Substation10/24/2018 IA PENDING   
GEN-2018-064DISIS-2018-00204 SOUTHEASTBenton CountyARGRDA6/30/202112/31/2025  808080ER/NR000SolarTonnece Substation 69kV10/24/2018 IA PENDING   
GEN-2018-060DISIS-2018-00102 NEBRASKAWebsterNENPPD12/1/202012/31/2026  505050ER/NR000WindAxtell-Post Rock 345 kV5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-057DISIS-2018-00103 CENTRALSedgwickKSWERE5/15/20295/15/2029  203.4203.4203.4ER/NR000SolarGordon Evans 138kV5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-055DISIS-2018-00104 SOUTHEASTGradyOKAEP12/31/202012/31/2026  252252252ER/NR000SolarTerry Road 345kV station (shared with Rush Springs Windfarm on a common gentie) 5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-052DISIS-2018-00105 SOUTHWESTLeaNMSPS12/31/202112/31/2026  707070ER000Battery/StorageRoadrunner 115kV Substation5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-050DISIS-2018-00104 SOUTHEASTCaddoLAAEP12/31/20214/15/2027  200200200ER000SolarLongwood 345kV Substation5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-049DISIS-2018-00103 CENTRALSumnerKSITCGP12/31/20214/1/2027  120120120ER000SolarThistle 345kV Substation5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-048DISIS-2018-00104 SOUTHEASTCaddoOKOGE12/31/202112/15/2027  300300300ER000SolarPecan Creek 345kV Substation5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-043DISIS-2018-00102 NEBRASKABurtNEOPPD12/31/202112/15/2028  500500500ER000SolarFt. Calhoun - Raun 345 kV Line Break5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-037DISIS-2018-00102 NEBRASKADouglasNEOPPD12/31/20245/31/2030  100100100ER000Battery/StorageLooping in OPPD (S1211) (S1220) (S1211) (S1299) 161kV5/29/2018 IA FULLY EXECUTED/ON SUSPENSION   
GEN-2018-033DISIS-2018-00102 NEBRASKACassNEOPPD12/31/202311/30/2029  200200200ER000Battery/StorageCass County 345kV Substation5/29/2018 IA FULLY EXECUTED/ON SUSPENSION   
GEN-2018-032DISIS-2018-00103 CENTRALMcPhearsonKSWERE12/1/20215/1/2029  310310310ER000WindNeosho 345kV Substation5/29/2018 IA FULLY EXECUTED/ON SUSPENSION   
GEN-2018-031DISIS-2018-00103 CENTRALJacksonMOINDN12/31/20245/31/2028  505050ER000Battery/StorageBlue Valley 161kV Substation5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-029DISIS-2018-00104 SOUTHEASTOklahomaOKOGE10/15/20235/31/2028  100100100ER000Battery/StorageHorseshoe Lake 138kV Substation5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-028DISIS-2018-00104 SOUTHEASTTulsaOKAEP10/15/20235/31/2028  200200200ER000Battery/StorageTulsa North 138kV Substation5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-027DISIS-2018-00104 SOUTHEASTTulsaOKAEP12/31/20245/31/2028  100100100ER000Battery/StorageTulsa Power Station 138kV Substation5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-026DISIS-2018-00104 SOUTHEASTCanadianOKOGE10/15/20235/31/2026  100100100ER000Battery/StorageMustang 138kV Substation5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-025DISIS-2018-00102 NEBRASKAWashington NEOPPD10/15/202311/30/2028  200200200ER000Battery/StorageFort Calhoun 345kV Substation5/29/2018 IA FULLY EXECUTED/ON SUSPENSION   
GEN-2018-024DISIS-2018-00104 SOUTHEASTMuskogeeOKOGE10/15/202312/31/2028  100100100ER000Battery/StorageCanadian River-Muskogee and Muskogee-Seminole 345kV5/28/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-021DISIS-2018-00104 SOUTHEASTWashitaOKAEP12/1/202312/31/2024  74.174.174.1ER/NR000SolarChisholm-Gracemont 345kV Line5/24/2018 IA PENDING   
GEN-2018-015DISIS-2018-00105 SOUTHWESTPaducahTXSPS10/31/202111/1/2027  252252252ER/NR000SolarTuco-Oklaunion 345kV Line4/27/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-013DISIS-2018-00103 CENTRALDickinsonKSWERE12/30/202412/31/2026  74.174.174.1ER000WindAbilene Energy Center-Northview 115kV Line4/27/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-011DISIS-2018-00104 SOUTHEASTKingfisherOKWFEC12/1/202012/31/2027  74.174.174.1ER/NR000Battery/StorageDover 138 kV Switching Station4/27/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-010DISIS-2018-00101 NORTHMontrailNDBEPC12/1/202112/31/2026  74.174.174.1ER/NR000Battery/StorageNeset 230kV Substation4/27/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-009DISIS-2018-00103 CENTRALSeward/MeadeKSSUNC7/15/202512/31/2028  150150150ER000WindCimarron 115kV Substation4/27/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-004DISIS-2018-00105 SOUTHWESTLeaNMSPS12/31/20193/1/2027  74.9974.9974.99ER000SolarT14 Circuit 115kV line4/26/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-003DISIS-2018-00104 SOUTHEASTBowieTXAEP12/31/20216/1/2027  150150150ER/NR000SolarNorth Boston-Bann 138kV Line4/25/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-239IFS-2017-002-76DISIS-2017-00205 SOUTHWESTYoakumTXSPS6/1/20235/1/2026  300300300ER000SolarMahoney 230kV Substation11/30/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-234IFS-2017-002-73DISIS-2017-00202 NEBRASKAGreeleyNENPPD12/31/201912/31/2024  115115115ER000WindSpalding to North Loup 115kV11/6/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-233IFS-2017-002-72DISIS-2017-00204 SOUTHEASTGradyOKOGE12/1/202012/31/2027  215215215ER/NR000WindMinco 345kV11/28/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-232IFS-2017-002-71DISIS-2017-00204 SOUTHEASTBryan CountyOKOGE6/1/20203/31/2026  52.252.252.2ER/NR000SolarBrown 138kV Substation11/28/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-231IFS-2017-002-70DISIS-2017-00204 SOUTHEASTFranklin CountyAROGE6/1/20203/1/2027  72.572.572.5ER/NR000SolarBranch 161kV Substation11/28/2017 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-230IFS-2017-002-69DISIS-2017-00204 SOUTHEASTLincoln CountyOKOGE6/1/202011/1/2026  72.572.572.5ER/NR000SolarTryon 138kV Substation11/28/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-227IFS-2017-002-67DISIS-2017-00203 CENTRALSedwick CountyKSWERE12/31/20205/15/2029  201.6201.6201.6ER/NR000Battery/StorageGordon Evans 138kV Substation11/30/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-226IFS-2017-002-66DISIS-2017-00203 CENTRALSedgwick CountyKSWERE12/1/20205/15/2029  201.6201.6201.6ER/NR000SolarGordon Evans 138kV Substation11/30/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-222IFS-2017-002-64DISIS-2017-00201 NORTHDenisonIAWAPA10/6/202010/15/2027  180180180ER000WindDenison 230kV Substation11/30/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-221IFS-2017-002-63DISIS-2017-00203 CENTRALSedgwickKSWERE12/31/20203/30/2029  152152152ER/NR000Battery/StorageBuffalo Flats 345kV Substation11/30/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-220IFS-2017-002-62DISIS-2017-00203 CENTRALSedgwickKSWERE12/1/202012/31/2029  201.6201.6201.6ER/NR000SolarBuffalo Flats 345kV Substation11/30/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-215IFS-2017-002-60DISIS-2017-00201 NORTHWardNDBEPC12/1/202012/31/2030  100100100ER/NR000WindLogan 230kV Substation11/30/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-214IFS-2017-002-59DISIS-2017-00201 NORTHWardNDBEPC12/1/202012/31/2030  100100100ER/NR000WindLogan 230kV Substation11/30/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-210IFS-2017-002-57DISIS-2017-00202 NEBRASKACedarNENPPD12/1/202112/1/2026  310310310ER000HybridSolarMcCool 345kV Substation11/30/2017 IA FULLY EXECUTED/ON SUSPENSION  View
GEN-2017-203IFS-2017-002-55DISIS-2017-00204 SOUTHEASTGrant/KayOKOGE7/1/202312/31/2026  210210210ER000HybridSolarRenfrow 345kV Substation11/30/2017 IA FULLY EXECUTED/ON SUSPENSION  View
GEN-2017-201IFS-2017-002-53DISIS-2017-00202 NEBRASKAWayne CountyNENPPD12/1/202212/31/2028  250250250ER/NR000WindHoskins 345kV Substation11/30/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-198IFS-2017-002-50DISIS-2017-00202 NEBRASKAOmahaNEOPPD12/1/20222/28/2027  11.6411.6411.64ER000Battery/StorageJones St. No 1201 69kV substation11/30/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-196IFS-2017-002-49DISIS-2017-00203 CENTRALJohnsonKSKCPL12/1/202012/1/2030  128128128ER/NR000Battery/StorageWest Gardner 345kV11/30/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-195IFS-2017-002-48DISIS-2017-00203 CENTRALJohnsonKSKCPL12/1/202012/1/2030  500.4500.4500.4ER/NR000SolarWest Gardner 345kV11/30/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-188IFS-2017-002-44DISIS-2017-00203 CENTRALBarryMOEDE12/31/20206/15/2026  130130130ER000SolarAsbury 161 kV11/30/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-187IFS-2017-002-43DISIS-2017-00205 SOUTHWESTTerryTXSPS12/31/20206/1/2026  150150150ER000SolarFlatland 115 kV Substation11/30/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-184IFS-2017-002-42DISIS-2017-00203 CENTRALHodgeman/FordKSKCPL12/1/20216/1/2029  400400400ER/NR000SolarNashua-St. Joe 345kV11/29/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-183IFS-2017-002-41DISIS-2017-00203 CENTRALHodgeman/FordKSKCPL12/1/20216/1/2029  400400400ER/NR000WindNashua-St. Joe 345kV11/29/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-182IFS-2017-002-40DISIS-2017-00202 NEBRASKALancasterNENPPD12/1/20202/4/2025  128128128ER/NR000WindTobias 345kV Substation11/29/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-181IFS-2017-002-39DISIS-2017-00202 NEBRASKALancasterNENPPD12/1/202012/8/2024  300300300ER/NR000WindTobias 345kV Substation11/29/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-178IFS-2017-002-37DISIS-2017-00204 SOUTHEASTGarfieldOKOGE12/31/202012/1/2025  525252ER/NR000Battery/StorageWoodring 345kV Substation11/29/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-175IFS-2017-002-36DISIS-2017-00201 NORTHTurnerSDWAPA9/30/202312/1/2026  300300300ER000WindVfodnes-Utica Jct. 230kV11/29/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-173IFS-2017-002-35DISIS-2017-00204 SOUTHEASTStephenOKAEP12/1/202012/31/2027  505050ER/NR000SolarLawton Eastside - Terry Road 345kV11/29/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-172IFS-2017-002-34DISIS-2017-00204 SOUTHEASTStephenOKAEP12/1/202012/31/2027  505050ER/NR000SolarLawton Eastside - Terry Road 345kV11/29/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-171IFS-2017-002-33DISIS-2017-00204 SOUTHEASTStephenOKAEP12/1/202012/31/2027  150150150ER/NR000SolarLawton Eastside - Terry Road 345kV11/29/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-164IFS-2017-002-28DISIS-2017-00204 SOUTHEASTGarfieldOKOGE12/1/202012/31/2025  250250250ER/NR000SolarWoodring 345kV Substation11/29/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-158IFS-2017-002-27DISIS-2017-00205 SOUTHWESTParmer/CastroTXSPS12/31/20208/30/2026  265265265ER000WindTolk 230kV Substation11/29/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-151IFS-2017-002-23DISIS-2017-00205 SOUTHWESTCrosbyTXSPS10/31/202010/15/2026  300300300ER000WindTUCO-Oklaunion 345kV11/28/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-150IFS-2017-002-22DISIS-2017-00204 SOUTHEASTGradyOKOGE12/1/202012/31/2026  250250250ER/NR000SolarMinco 345kV11/28/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-149IFS-2017-002-21DISIS-2017-00204 SOUTHEASTJohnstonOKOGE12/1/202012/31/2027  258258258ER/NR000WindJohnson County 345kV Substation11/27/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-146IFS-2017-002-19DISIS-2017-00205 SOUTHWESTCastroTXSPS10/31/202010/15/2026  151.8151.8151.8ER000WindDeaf Smith-Plant X 230kV11/27/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-144IFS-2017-002-18DISIS-2017-00202 NEBRASKAHolt, Antelope, WheelerNENPPD12/31/202112/31/2025  200200200ER000WindHolt County 345kV11/27/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-141IFS-2017-002-17DISIS-2017-00204 SOUTHEASTWagonerOKAEP12/1/202012/31/2027  241.7241.7241.7ER/NR000SolarClarksville 345kV Switching Station11/22/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-140IFS-2017-002-16DISIS-2017-00204 SOUTHEASTWagonerOKAEP12/1/202012/31/2027  160160160ER/NR000SolarClarksville 345kV Switching Station11/22/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-137IFS-2017-002-15DISIS-2017-00204 SOUTHEASTOklahomaOKOGE12/1/202012/31/2028  295295295ER/NR000WindArcadia 345kV11/22/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-134IFS-2017-002-14DISIS-2017-00204 SOUTHEASTOklahomaOKOGE12/1/202012/31/2028  250250250ER/NR000WindArcadia 345kV11/22/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-133IFS-2017-002-13DISIS-2017-00204 SOUTHEASTOklahomaOKOGE12/1/202012/31/2028  200200200ER/NR000WindArcadia 345kV11/22/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-131IFS-2017-002-11DISIS-2017-00203 CENTRALWilsonKSWERE12/1/20202/1/2026  29.629.629.6ER/NR000Battery/StorageAltoona- NE Parson 138kV11/22/2017 IA FULLY EXECUTED/ON SUSPENSION  View
GEN-2017-121IFS-2017-002-08DISIS-2017-00203 CENTRALSumnerKSWERE12/1/202112/1/2026  200200200ER/NR000WindSumner 138kV11/17/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-120IFS-2017-002-07DISIS-2017-00203 CENTRALDickinson/MarionKSWERE5/1/202712/31/2027  260260260ER000WindAbilene Energy Center-Northview 115kV11/17/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-119IFS-2017-002-06DISIS-2017-00203 CENTRALCloud/MitchellKSSUNC5/1/202412/31/2027  180180180ER000WindElm Creek 345kV substation11/17/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-117IFS-2017-002-05DISIS-2017-00204 SOUTHEASTCanadianOKWFEC12/1/202012/1/2026  19.819.819.8ER/NR000Battery/StorageEl Reno SW 138kV11/17/2017 IA FULLY EXECUTED/ON SUSPENSION  View
GEN-2017-115IFS-2017-002-04DISIS-2017-00203 CENTRALAtchinson/NodawayMOKCPL5/1/202712/31/2026  244244244ER000WindHolt County 345 kV11/10/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-108IFS-2017-002-02DISIS-2017-00203 CENTRALHenry CountyMOKCPL12/1/20223/1/2027  400400400ER/NR000SolarStillwell - Clinton 161kV Line8/26/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-105IFS-2017-002-01DISIS-2017-00202 NEBRASKABurt CountyNEOPPD12/15/201812/20/2026  757575ER/NR000WindTekamah - Raun 161 kV Line7/12/2017 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-100IFS-2017-001-20DISIS-2017-00105 SOUTHWESTTexas CountyOKSPS12/31/201912/1/2025  102.6102.6102.6ER/NR000SolarTexas County 115kV5/31/2017 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2017-097IFS-2017-001-24DISIS-2017-00101 NORTHPennington CountySDWAPA1/9/20226/29/2024  128128128ER000SolarUnderwood 115 kV Sub5/31/2017 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2017-094IFS-2017-001-31DISIS-2017-00101 NORTHWessington/Hand CountiesSDWAPA10/6/202011/1/2023  200200200ER000WindFort Thompson-Huron 230 kV5/24/2017 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2017-092IFS-2017-001-04DISIS-2017-00104 SOUTHEASTMuskogee CountyOKOGE6/1/202312/31/2025  200200200ER000SolarCanadian River-Muskogee and Muskogee-Seminole 345kV5/30/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-086IFS-2017-001-10DISIS-2017-00103 CENTRALHarper CountyKSWERE12/1/20213/1/2025  150150150ER000WindViola 345kV5/25/2017 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2017-082IFS-2017-001-02DISIS-2017-00103 CENTRALBarton/Jasper CountiesMOEDE7/1/202012/31/2020  149.4149.4149.4ER000WindAsbury Plant 161 kV5/31/2017 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2017-077IFS-2017-001-18DISIS-2017-00104 SOUTHEASTMayes CountyOKAEP12/1/20218/8/2025  124.7124.7124.7ER000SolarExplorer Claremore Tap COOYYAH45/28/2017 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2017-076IFS-2017-001-17DISIS-2017-00104 SOUTHEASTBenton CountyARAEP12/1/202112/1/2024  52.252.252.2ER000SolarChamber Springs 161kV sub5/28/2017 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2017-075IFS-2017-001-16DISIS-2017-00104 SOUTHEASTJohnston CountyOKOGE12/1/202112/1/2026  200200200ER000SolarHugo-Sunnyside 345 kV5/28/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-074IFS-2017-001-15DISIS-2017-00104 SOUTHEASTMayes CountyOKAEP12/1/20218/8/2025  72.572.572.5ER000SolarPryor Junction 138kV sub5/28/2017 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2017-073IFS-2017-001-14DISIS-2017-00104 SOUTHEASTMayes CountyOKGRDA12/1/20219/1/2025  72.572.572.5ER000SolarDry Gulch 161kV sub5/28/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-072IFS-2017-001-37DISIS-2017-00104 SOUTHEASTPayne CountyOKOGE12/1/202112/1/2025  52.252.252.2ER000SolarGreenwood 138kV sub5/28/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-071IFS-2017-001-36DISIS-2017-00104 SOUTHEASTPayne CountyOKOGE12/1/202112/1/2025  124.7124.7124.7ER000SolarGreenwood 138kV sub5/28/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-068IFS-2017-001-26DISIS-2017-00103 CENTRALSumner CountyKSWERE12/31/202012/15/2028  103.5103.5103.5ER/NR000SolarGordon Evans 138kV Substation5/30/2017 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2017-061IFS-2017-001-25DISIS-2017-00104 SOUTHEASTMayes CountyOKGRDA12/1/20219/1/2025  101.5101.5101.5ER000SolarGRDA1 to CLARMR 5 161kV line5/28/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-060IFS-2017-001-01DISIS-2017-00103 CENTRALBarton CountyMOEDE9/1/20204/21/2021  149.4149.4149.4ER000WindLaRussell Energy Center 161kV5/30/2017 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2017-057IFS-2017-001-13DISIS-2017-00104 SOUTHEASTCaddo ParishLAAEP12/1/20212/28/2025  72.572.572.5ER000SolarHosston 69kV5/30/2017 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2017-048IFS-2017-001-34DISIS-2017-00101 NORTHWilliams CountyNDBEPC8/30/202412/31/2026  300300300ER000WindNeset 230 kV Substation5/31/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-047IFS-2017-001-19DISIS-2017-00105 SOUTHWESTBeaver CountyOKSPS12/31/201912/27/2024  102102102ER/NR000WindBull Creek 115 kV substation5/18/2017 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2017-040IFS-2017-001-03DISIS-2017-00104 SOUTHEASTOchiltree CountyTXOGE6/1/202012/31/2025  200.1200.1200.1ER000SolarCanadian River-Muskogee and Muskogee-Seminole 345kV5/31/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-036IFS-2017-001-23DISIS-2017-00104 SOUTHEASTKiowa CountyOKAEP12/1/20222/22/2025  100100100ER000SolarSnyder - Cache 138 kV5/31/2017 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2017-033IFS-2017-001-28DISIS-2017-00105 SOUTHWESTBaylor CountyTXAEP12/31/202012/23/2024  200200200ER000WindOklaunion 345 kV sub5/31/2017 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2017-027IFS-2017-001-33DISIS-2017-00104 SOUTHEASTCarter CountyOKOGE11/1/202112/21/2021  140140140ER000WindPooleville-Ratliff (Carter County) 138kV5/31/2017 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2017-023IFS-2017-001-22DISIS-2017-00104 SOUTHEASTChoctaw CountyOKWFEC 6/1/2026  858585ER/NR000SolarHugo Power Plant 138 kV Sub5/31/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-022IFS-2017-001-21DISIS-2017-00103 CENTRALWilson CountyKSWERE12/1/20196/1/2025  656565ER/NR000SolarAltoona- NE Parson 138kV5/31/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-018IFS-2017-001-27DISIS-2017-00103 CENTRALBarber CountyKSITCGP12/31/20204/30/2025  189189189ER/NR000SolarThistle 345 kV sub5/30/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-014IFS-2017-001-29DISIS-2017-00101 NORTHHaakon CountySDWAPA12/1/202012/1/2027  300300300ER000WindPhilip Tap 230 kV5/22/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-011IFS-2017-001-06DISIS-2017-00104 SOUTHEASTEllis CountyOKOGE12/31/201912/31/2026  151.8151.8151.8ER000SolarBadger-Woodward EHV Dbl Ckt 345kV5/17/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-010IFS-2017-001-12DISIS-2017-00101 NORTHBowman CountyNDBEPC10/31/202212/12/2025  200.1200.1200.1ER000WindRhame 230 kV Sub4/14/2017 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2017-009IFS-2017-001-39DISIS-2017-00103 CENTRALNeoshoe CountyKSWERE10/31/20205/1/2021  302302302ER000WindNeosho - Caney River 345 kV4/14/2017 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2017-005IFS-2017-001-11DISIS-2017-00103 CENTRALBourbon and Crawford CountiesOKWERE12/31/202012/13/2021  190190190ER000WindMarmaton - Litchfield 161 kV4/14/2017 IA FULLY EXECUTED/COMMERCIAL OPERATIONInterim IGIA effective 3/3/2021 - AB  View
GEN-2017-004IFS-2017-001-05DISIS-2017-00103 CENTRALCloud CountyKSITCGP12/31/202111/30/2027  201.6201.6201.6ER000WindElm Creek - Summit 345 kV4/14/2017 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2016-177IFS-2016-002-60DISIS-2016-002-105 SOUTHWESTGainesTXSPS 7/28/2021  1714.417ER000ThermalGas TurbineXTO-Cornell 115 kV station1/23/2017 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-176IFS-2016-002-67DISIS-2016-002-103 CENTRALNemaha CountyKSWERE12/31/201912/6/2021  302302302ER000WindStranger Creek 345kV12/15/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-174IFS-2016-002-19DISIS-2016-002-103 CENTRALNemahaKSWERE9/15/201911/18/2020  302302302ER000WindStranger Creek 345kV11/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-167IFS-2016-002-02DISIS-2016-002-104 SOUTHEASTCaddo ParishLAAEP9/1/202312/1/2024  73.573.573.5ER/NR000SolarLieberman - North Benton 138 kV Line11/29/2016 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2016-160IFS-2016-002-04DISIS-2016-002-103 CENTRALEllisKSMIDW10/2/202312/31/2026  202020ER/NR000Battery/StoragePost Rock 230kV11/21/2016 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2016-153IFS-2016-002-11DISIS-2016-002-103 CENTRALHarper CountyKSWERE10/30/201912/31/2024  134134134ER000WindViola 345kV11/30/2016 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2016-151IFS-2016-002-62DISIS-2016-002-101 NORTHBurkeNDBEPC9/15/201912/22/2020  202202202ER000WindTande 345kV11/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-150IFS-2016-002-15DISIS-2016-002-103 CENTRALNemahaKSWERE9/22/202212/7/2023  302302302ER000WindStranger Creek 345kV11/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-149IFS-2016-002-14DISIS-2016-002-103 CENTRALWashingtonKSWERE9/15/201912/7/2023  302302302ER000WindStranger Creek 345kV11/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-147IFS-2016-002-33DISIS-2016-002-102 NEBRASKACheyenneNETri-State9/15/20196/28/2024  404040ER000SolarSidney 115 kV Sub11/30/2016 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2016-146IFS-2016-002-56DISIS-2016-002-104 SOUTHEASTTexasOKAEP9/1/202012/31/2025  175175175ER000WindRiverside 345kV Substation11/29/2016 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2016-145IFS-2016-002-55DISIS-2016-002-104 SOUTHEASTTexasOKAEP9/1/202012/31/2025  175175175ER000WindRiverside 345kV Substation11/29/2016 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2016-142IFS-2016-002-52DISIS-2016-002-104 SOUTHEASTTexasOKAEP9/1/202012/31/2025  350350350ER000WindRiverside 345kV Substation11/29/2016 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2016-141IFS-2016-002-51DISIS-2016-002-104 SOUTHEASTTexasOKAEP9/1/202012/31/2025  350350350ER000WindRiverside 345kV Substation11/29/2016 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2016-139IFS-2016-002-49DISIS-2016-002-104 SOUTHEASTTexasOKAEP9/1/202012/31/2025  100100100ER000WindRiverside 345kV Substation11/29/2016 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2016-138IFS-2016-002-48DISIS-2016-002-104 SOUTHEASTTexasOKAEP9/1/202012/31/2025  187.5187.5187.5ER000WindRiverside 345kV Substation11/29/2016 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2016-137IFS-2016-002-47DISIS-2016-002-104 SOUTHEASTTexasOKAEP9/1/202012/31/2025  187.5187.5187.5ER000WindRiverside 345kV Substation11/29/2016 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2016-134IFS-2016-002-44DISIS-2016-002-104 SOUTHEAST TexasOKAEP9/1/202012/31/2025  187.5187.5187.5ER000WindRiverside 345kV Substation11/29/2016 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2016-133IFS-2016-002-43DISIS-2016-002-104 SOUTHEASTTexasOKAEP9/1/202012/31/2025  187.5187.1187.5ER000WindRiverside 345kV Substation11/29/2016 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2016-132IFS-2016-002-61DISIS-2016-002-104 SOUTHEASTRoger MillsOKAEP12/31/20176/5/2020  6.16.16.1ER000WindSweetwater 230kV11/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-131IFS-2016-002-37DISIS-2016-002-104 SOUTHEASTGradyOKOGE12/31/201710/25/2021  2.52.52.5ER000WindMinco 345kV11/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-130IFS-2016-002-21DISIS-2016-002-101 NORTHMercerNDBEPC9/15/201912/27/2024  202202202ER000WindLeland Olds 345 kV11/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-128IFS-2016-002-36DISIS-2016-002-104 SOUTHEASTAlfalfaOKOGE9/15/201912/31/2026  176176176ER000WindWoodring 345kV11/30/2016 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2016-126IFS-2016-002-06DISIS-2016-002-104 SOUTHEASTMurrayOKOGE12/31/201911/24/2021  172.5172.5172.5ER/NR000WindArbuckle 138kV substation11/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-125IFS-2016-002-29DISIS-2016-002-105 SOUTHWESTRooseveltNMSPS12/31/201912/31/2020  747474ER000WindEddy County-Tolk (Crossroads) 345kV11/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-124IFS-2016-002-28DISIS-2016-002-105 SOUTHWESTRooseveltNMSPS12/31/201912/31/2020  150150150ER000WindEddy County-Tolk (Crossroads) 345kV11/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-123IFS-2016-002-27DISIS-2016-002-105 SOUTHWESTRooseveltNMSPS12/31/201912/31/2020  298298298ER000WindEddy County-Tolk (Crossroads) 345kV11/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-121IFS-2016-002-26DISIS-2016-002-105 SOUTHWESTLeaNMSPS10/1/202212/31/2026  110110110ER000SolarRoadrunner 115kV11/22/2016 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2016-119IFS-2016-002-10DISIS-2016-002-104 SOUTHEASTKingfisherOKOGE5/15/202012/31/2025  600600600ER000WindSpring Creek-Sooner 345kV11/30/2016 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2016-118IFS-2016-002-05DISIS-2016-002-104 SOUTHEASTKingfisherOKWFEC5/15/20219/10/2021  288288288ER000WindDover Switchyard 138 kV Line11/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-115IFS-2016-002-24DISIS-2016-002-103 CENTRALAtchisonMOGMO11/16/20203/2/2021  300300300ER000WindNebraska City-Mullen Creek (Holt County MO) 345kV11/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION   View
GEN-2016-111IFS-2016-002-18DISIS-2016-002-103 CENTRALMcPhersonKSEvergy9/15/20191/15/2027  302302302ER000WindReno - Summit 345kV11/30/2016 IA FULLY EXECUTED/ON SCHEDULESuspension Start Date of 3/24/2021  View
GEN-2016-102IFS-2016-002-01DISIS-2016-002-104 SOUTHEASTPontotocOKOGE11/1/202312/1/2024  150.9150.9150.9ER/NR000WindBlue River 138kV11/7/2016 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2016-097IFS-2016-002-31DISIS-2016-002-104 SOUTHEASTCaddoOKAEP9/1/20201/1/2024  100100100ER/NR000WindTap Southwestern-Fletcher Tap 138kV10/19/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-095IFS-2016-002-32DISIS-2016-002-104 SOUTHEASTCaddoOKAEP9/1/20204/22/2024  200200200ER/NR000WindGracemont-Lawton East Side 345kV12/1/2020 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-094IFS-2016-002-25DISIS-2016-002-101 NORTHHydeSDWAPA10/1/20201/24/2024  200200200ER000WindTap Ft Thompson - Oahe 230kV Line (Single Circuit)10/31/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-091IFS-2016-002-22DISIS-2016-002-104 SOUTHEASTCaddoOKAEP5/6/20201/8/2022  303.6303.6303.6ER000WindGracemont-Lawton East Side 345kV10/3/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-087IFS-2016-002-59DISIS-2016-002-101 NORTHCampbellSDWAPA11/15/201912/31/2026  98.698.698.6ER000WindCampbell County 230 kV line7/25/2016 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2016-075IFS-2016-001-21DISIS-2016-001-302 NEBRASKAHoltNEWAPA12/31/201712/31/2027  505050ER000WindFort Thompson-Grand Island (Grand Prairie) 345kV3/31/2016 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2016-074IFS-2016-002-57DISIS-2016-002-102 NEBRASKACusterNENPPD10/30/20207/1/2027  200200200ER000WindSweetwater 345kV4/14/2016 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2016-071IFS-2016-001-19DISIS-2016-001-304 SOUTHEASTKayOKOGE9/30/20182/27/2027  169.2169.2169.2ER000WindMiddleton Tap 138kV Substation3/30/2016 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2016-070IFS-2016-001-18DISIS-2016-001-305 SOUTHWESTCarsonTXSPS11/1/201612/11/2020  5.35.35.3ER000WindMartin 115 kV Substation3/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-068IFS-2016-001-40DISIS-2016-001-304 SOUTHEASTGarfieldOKOGE9/18/202012/15/2020  250250250ER000WindWoodring 345kV3/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-067IFS-2016-001-33DISIS-2016-001-303 CENTRALThomasKSSUNC11/1/20177/24/2019  73.673.673.6ER000WindMingo 345kV3/31/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-061IFS-2016-001-15DISIS-2016-001-304 SOUTHEASTGarfield/NobleOKOGE12/1/201711/21/2020  250.7250.7250.7ER000WindSooner-Woodring 345 kV line3/29/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-057IFS-2016-001-35DISIS-2016-001-304 SOUTHEASTCimarron, Texas CountyOKOGE8/31/20183/18/2022  499.1499.1499.1ER000WindMathewson 345kV3/31/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-051IFS-2016-001-13DISIS-2016-001-304 SOUTHEASTCusterOKAEP 12/18/2020  9.89.89.8ER000WindClinton Junction-Weatherford Southeast 138kV3/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-050IFS-2016-001-42DISIS-2016-001-302 NEBRASKAWebster CoNENPPD12/1/201712/9/2021  250.7250.7250.7ER000WindAxtell – Post Rock 345 kV3/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-047IFS-2016-001-22DISIS-2016-001-304 SOUTHEASTCanadianOKOGE12/31/20173/24/2018  24824ER000ThermalCTMustang 69kV3/31/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-046IFS-2016-001-12DISIS-2016-001-303 CENTRALFord CountyKSSUNC12/1/201812/23/2021  299299299ER000WindClark County-Ironwood 345kV3/31/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-045IFS-2016-001-34DISIS-2016-001-304 SOUTHEASTCimarron, Texas CountyOKOGE8/31/20183/18/2022  499.1499.1499.1ER000WindMathewson 345kV3/31/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-043IFS-2016-001-36DISIS-2016-001-302 NEBRASKAWayne CountyNENPPD9/1/20186/27/2020  230230230ER000WindHoskins 345kV3/31/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-037IFS-2017-001-32DISIS-2017-00104 SOUTHEASTWashita CountyOKAEP6/1/20213/21/2023  300300300ER000WindChisholm-Gracemont 345kV3/31/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-036IFS-2016-002-42DISIS-2016-002-101 NORTHChippewa CountyMNWAPA11/17/201812/30/2018  44.644.644.6ER000WindGranite Falls 115kV substation3/28/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-032IFS-2016-001-11DISIS-2016-001-304 SOUTHEASTKingfisher CoOKOGE2/1/20234/11/2024  200200200ER/NR000WindCrescent Substation 138 kV3/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-031IFS-2016-001-10DISIS-2016-001-304 SOUTHEASTKay CountyOKOGE11/30/201612/17/2016  1.51.51.5ER000WindRose Hill (Open Sky)-Sooner (Ranch Road) 345kV3/25/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-030IFS-2016-001-26DISIS-2016-001-304 SOUTHEASTJohnston CoOKOGE8/28/20213/31/2026  100100100ER/NR000SolarBrown 138kV3/30/2016 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2016-028IFS-2016-001-38DISIS-2016-001-304 SOUTHEASTLe Flore CoOKAEP12/31/201812/27/2019  100100100ER000WindClayton 138 kV Sub3/29/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-022IFS-2016-001-29DISIS-2016-001-304 SOUTHEASTNewkirk, Kay CountyOKOGE12/31/201712/10/2020  151.8151.8151.8ER000WindRose Hill (Open Sky)-Sooner (Ranch Road) 345kV3/31/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-021IFS-2016-001-31DISIS-2016-001-302 NEBRASKADixon CountyNENPPD12/1/20183/9/2022  298.47298.47298.47ER000WindHoskins 345kV3/31/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-020IFS-2016-001-27DISIS-2016-001-304 SOUTHEASTWoodward CountyOKWFEC12/31/201812/18/2020  148.4148.4148.4ER000WindMoreland 138kV Substation4/1/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-017IFS-2016-001-08DISIS-2016-001-301 NORTHHyde CountySDBEPC12/1/201711/23/2020  250.24250.24250.24ER000WindChappelle Creek 345kV3/29/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-014IFS-2016-001-04DISIS-2016-001-303 CENTRALJoplinMOEDE4/25/20034/30/2020  101010ER000ThermalCTLaRussell Energy Center 161kV3/29/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-013IFS-2016-001-03DISIS-2016-001-303 CENTRALJoplinMOEDE4/25/20034/30/2020  101010ER000ThermalCTLaRussell Energy Center 161kV3/29/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-009IFS-2016-001-02DISIS-2016-001-303 CENTRALPonca CityOKOGE9/30/201811/18/2020  292929ER000ThermalSteam TurbineOsage 69 kV Sub3/24/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2016-004IFS-2016-001-25DISIS-2016-001-301 NORTHOliverNDBEPC10/5/202212/31/2027  202202202ER/NR000WindBasin Electric 230 kV3/10/2016 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2016-003IFS-2016-001-45DISIS-2016-001-304 SOUTHEASTEllisOKOGE12/31/201712/21/2022  250.4250.4250.4ER000WindBadger-Woodward EHV Dbl Ckt 345kV3/15/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-096IFS-2015-002-43DISIS-2015-002-701 NORTHHettinger CountyNDBEPC12/31/201712/29/2016  150150150ER000WindBrady 230kV substation10/19/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-090IFS-2015-002-21DISIS-2015-002-703 CENTRALPrattKSWERE12/1/201712/14/2018  220220220ER000WindThistle-Wichita Dbl Ckt (Buffalo Flats) 345kV9/29/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-089IFS-2016-001-05DISIS-2016-001-301 NORTHBon HommeSDWAPA6/30/20174/22/2020  200200200ER000WindUtica 230 kV Substation10/13/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-088IFS-2015-002-32DISIS-2015-002-702 NEBRASKASalineNENPPD1/1/201912/29/2020  300300300ER/NR000WindTobias 345kV Substation9/30/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2015-082IFS-2016-001-28DISIS-2016-001-305 SOUTHWESTBeaverOKOGE12/1/201711/25/2020  200200200ER000WindBeaver County - Woodward EHV Dbl Ckt (Badger) 345kV9/28/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-073IFS-2015-002-20DISIS-2015-002-703 CENTRALLyon CountyKSWERE12/31/201812/19/2019  200.1200.1200.1ER/NR000WindEmporia 345kV9/28/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-069IFS-2015-002-06DISIS-2015-002-703 CENTRALDickenson / Marion CountiesKSWERE12/1/201712/17/2018  300300300ER000WindUnion Ridge 230kV9/21/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-066IFS-2015-002-38DISIS-2015-002-704 SOUTHEASTPawneeOKOGE12/1/201712/31/2025  248.4248.4248.4ER000WindSooner - Cleveland 345kV10/7/2015 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2015-065IFS-2015-002-19DISIS-2015-002-703 CENTRALThomas CountyKSSUNC11/1/20177/1/2019  202.4202.4202.4ER000WindMingo 345kV10/7/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-064IFS-2015-002-18DISIS-2015-002-703 CENTRALThomas CountyKSSUNC11/1/20173/26/2020  197.8197.8197.8ER000WindMingo 115kV10/7/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-063IFS-2015-002-16DISIS-2015-002-704 SOUTHEASTKingfisher CountyOKOGE12/1/20171/1/2018  300300300ER000WindWoodring-Matthewson 345kV10/6/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-062IFS-2015-002-15DISIS-2015-002-704 SOUTHEASTGarfield CountyOKOGE3/1/20168/27/2024  4.54.54.5ER000WindBreckinridge 138kV10/6/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-057IFS-2015-002-33DISIS-2015-002-704 SOUTHEASTGrady CountyOKOGE12/1/201612/22/2018  100100100ER000WindMinco 345kV10/6/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-052IFS-2015-002-03DISIS-2015-002-703 CENTRALSumnerKSWERE12/1/20172/7/2025  300300300ER000WindOpen Sky-Rose Hill 345kV10/5/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-048IFS-2015-002-11DISIS-2015-002-704 SOUTHEASTMajor County, OKOKOGE12/1/20174/14/2021  200200200ER000WindCleo Corner 138kV10/5/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-047IFS-2015-002-02DISIS-2015-002-704 SOUTHEASTNoble CountyOKOGE12/1/20171/1/2018  300300300ER000WindSooner 345kV10/5/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-046IFS-2015-002-46DISIS-2015-002-701 NORTHWilliams CountyNDBEPC12/1/20175/27/2021  300300300ER000WindTande 345kV10/5/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-045IFS-2015-002-10DISIS-2015-002-704 SOUTHEASTGrady CountyOKAEP12/1/20172/2/2020  10.310.310.3ER000Battery/StorageLawton East Side-Sunnyside (Terry Road) 345kV10/5/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-041IFS-2015-002-41DISIS-2016-00105 SOUTHWESTHale CountyTXSPS7/1/201510/19/2019  550ER000ThermalCTTUCO 345kV9/30/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-036IFS-2016-001-44DISIS-2016-001-304 SOUTHEASTJohnston CountyOKOGE12/31/201712/13/2020  303.6303.6303.6ER000WindJohnston County 345kV9/10/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-034IFS-2015-002-08DISIS-2015-002-704 SOUTHEASTKay CountyOKOGE10/31/201712/10/2020  200200200ER000WindRose Hill (Open Sky)-Sooner (Ranch Road) 345kV8/28/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-025IFS-2015-001-03DISIS-2015-001-403 CENTRALPrattKSWERE12/31/201612/19/2016  220220220ER000WindTap Thistle – Wichita 345kV Dbl CKT3/26/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-024IFS-2015-001-02DISIS-2015-001-403 CENTRALPratt CountyKSWERE12/31/201612/9/2016  220220220ER000WindThistle-Wichita Dbl Ckt (Buffalo Flats) 345kV3/26/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-023IFS-2015-001-08DISIS-2015-001-402 NEBRASKAAntelope & Wheeler CountyNENPPD12/31/201911/16/2022  300.7300.7300.7ER/NR000WindGrand Prairie-Grand Island (Holt County NE) 345kV3/31/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2015-021IFS-2015-001-16DISIS-2015-001-403 CENTRALStantonKSSUNC12/31/20164/7/2020  202020ER/NR000SolarJohnson Corner 115kV4/1/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-016IFS-2015-001-05DISIS-2015-001-403 CENTRALAllen CountyKSKCPL12/31/20179/11/2019  200200200ER/NR000WindTap Marmaton - Centerville 161kV3/20/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-015IFS-2015-001-14DISIS-2015-001-404 SOUTHEASTGrant CountyOKOGE7/31/201612/8/2017  154.56154.56154.56ER/NR000WindTap Medford Tap – Coyote 138kV3/27/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-014IFS-2015-001-20DISIS-2015-001-405 SOUTHWESTCochran CountyTXSPS12/1/201612/15/2018  150150150ER000WindTap Cochran - Lehman 115kV substation3/31/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-013IFS-2015-001-18DISIS-2015-001-404 SOUTHEASTKiowa CountyOKWFEC12/1/20165/23/2024  120120120ER/NR000SolarSnyder 138kV3/31/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-007IFS-2015-001-01DISIS-2015-001-402 NEBRASKAWayne CountyNENPPD11/8/201912/31/2019  160160160ER000WindHoskins 345kV3/25/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2015-005IFS-2015-001-04DISIS-2015-001-403 CENTRALDeKalb CountyMOGMO12/31/201712/16/2016  200.1200.1200.1ER000WindMullen Creek-Sibley (Ketchum) 345kV3/25/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2015-001IFS-2015-001-15DISIS-2015-001-404 SOUTHEASTKayOKOGE12/31/201612/17/2016  200200200ER000WindRose Hill (Open Sky)-Sooner (Ranch Road) 345kV3/4/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2014-064IFS-2014-002-24 DISIS-2014-002-604 SOUTHEASTGarfieldOKOGE12/1/201612/21/2018  248.4248.4248.4ER000WindOtter 138kV9/30/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-057IFS-2014-002-22DISIS-2014-002-604 SOUTHEASTGradyOKAEP12/31/201612/1/2016  249.9249.9249.9ER000WindLawton East Side-Sunnyside (Terry Road) 345kV9/29/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-056IFS-2014-002-21DISIS-2014-002-604 SOUTHEASTCanadianOKOGE12/31/201612/22/2018  250250250ER000WindMinco 345kV9/29/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-040IFS-2014-002-14DISIS-2014-002-605 SOUTHWESTCastroTXSPS9/1/201612/30/2016  320320320ER000WindCastro 115kV9/26/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-035IFS-2014-002-12 DISIS-2014-002-605 SOUTHWESTChavesNMSPS12/31/20164/24/2023  303030ER000SolarChaves County 115kV9/29/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-034IFS-2014-002-11DISIS-2014-002-605 SOUTHWESTChavesNMSPS12/31/201610/21/2016  707070ER000SolarChaves County 115kV9/29/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-033IFS-2014-002-10DISIS-2014-002-605 SOUTHWESTChavesNMSPS12/31/20168/25/2016  707070ER000SolarChaves County 115kV9/29/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-032IFS-2014-002-09DISIS-2014-002-602 NEBRASKAAntelope NENPPD10/1/20155/1/2014  10.210.210.2ER/NR000WindMeadow Grove 230kV9/29/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2014-031IFS-2014-002-08 DISIS-2014-002-602 NEBRASKAAntelope CountyNENPPD10/1/20153/30/2016  35.835.835.8ER/NR000WindMeadow Grove 230kV9/26/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2014-028IFS-2014-002-07 DISIS-2014-002-603 CENTRALCherokee CountyKSEDE1/1/20164/1/2016  50050ER000ThermalCCRiverton 161kV9/25/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-025IFS-2014-002-05 DISIS-2014-002-603 CENTRALRush KSMIDW10/15/201512/1/2015  2.422.422.42ER000WindTap Nekoma - Bazine (Walnut Creek) 69kV9/25/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-021IFS-2014-002-04DISIS-2014-002-603 CENTRALAtchison MOGMO12/1/201611/7/2017  300300300ER/NR000WindNebraska City-Mullen Creek (Holt County MO) 345kV9/2/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-020IFS-2014-002-03 DISIS-2014-002-604 SOUTHEASTGrady OKAEP12/31/201410/10/2017  100100100ER/NR000WindTuttle 138kV7/14/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-013IFS-2014-001-07 DISIS-2014-001-102 NEBRASKAAntelope / BooneNENPPD12/31/201412/18/2015  73.573.573.5ER/NR000WindMeadow Grove 230kV3/31/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-005IFS-2014-001-05 DISIS-2014-001-104 SOUTHEASTCaddoOKOGE 6/1/2015  5.75.75.7ER000WindMinco 345kV2/19/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-004IFS-2014-001-04 DISIS-2014-001-102 NEBRASKAJeffersonNENPPD 10/29/2013  3.963.963.96ER000WindSteele City 115kV2/19/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-002IFS-2014-001-02DISIS-2014-001-104 SOUTHEASTDeweyOKOGE12/31/20144/8/2015  10.510.510.5ER000WindTatonga 345kV2/18/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-001ISIFS-2015-001-21DISIS-2015-002 Prior Queued01 NORTHButteSDWAPA12/15/20159/24/2020  103.24103.24103.24ER000WindSulphur 115kV11/24/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-001IFS-2014-001-08DISIS-2014-001-103 CENTRALMarionKSWERE7/15/20148/11/2023  200.6200.6200.6ER000WindTap Wichita - Emporia Energy Center 345kV1/15/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2013-033IFS-2013-002-07DISIS-2013-002-203 CENTRALEllisKSMIDW12/31/20152/27/2016  282828ER/NR000ThermalGasGoodman Energy Center 115kV9/30/2013 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2013-032IFS-2013-002-06DISIS-2013-002-202 NEBRASKAAntelopeNENPPD12/31/201612/20/2018  202.5202.5202.5ER000WindAntelope 115kV9/30/2013 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2013-029IFS-2013-002-04 DISIS-2013-002-204 SOUTHEASTGrantOKOGE12/15/20154/8/2016  299299299ER000WindRenfrow 345kV9/30/2013 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2013-028IFS-2013-002-03DISIS-2013-002-204 SOUTHEASTMayesOKGRDA4/16/201612/23/2017  538495538ER000ThermalGasTap N Tulsa - GRDA 1 345kV9/30/2013 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2013-027IFS-2014-002-02DISIS-2014-002-605 SOUTHWESTBaileyTXSPS3/31/201612/10/2018  148.4148.4148.4ER/NR000WindTolk - Yoakum 230kV9/30/2013 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2013-022IFS-2013-002-02DISIS-2013-002-205 SOUTHWESTQuayNMSPS5/1/201512/7/2016  252525ER/NR000SolarNorton 115kV Switching Station9/5/2013 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2013-019IFS-2013-002-01DISIS-2013-002-202 NEBRASKALancasterNENPPD6/30/201412/1/2026  73.673.673.6ER/NR000HybridWind/SolarMonolith 115kV4/17/2013 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2013-016IFS-2013-001-03DISIS-2013-001-405 SOUTHWESTHaleTXSPS12/1/201610/19/2019  203191203ER000ThermalCTTUCO 345kV3/29/2013 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2013-012DISIS-2013-001-404 SOUTHEASTLogan CountyOKOGE11/30/20148/11/2014  14768147ER000ThermalGasRedbud 345kV3/28/2013 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2013-011IFS-2013-001-02DISIS-2013-001-404 SOUTHEASTHempsteadARAEP 12/18/2012  304030ER000ThermalCoalTurk 138kV3/28/2013 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2013-008DISIS-2013-001-402 NEBRASKAJeffersonNENPPD12/31/201312/31/2013  1.21.21.2ER000WindSteele City 115kV3/27/2013 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2013-007DISIS-2013-001-404 SOUTHEASTMurrayOKOGE12/31/201411/23/2015  100100100ER/NR000WindTap Prices Falls - Carter 138kV3/25/2013 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2013-002IFS-2013-001-01DISIS-2013-001-402 NEBRASKALancasterNENPPD12/31/201312/1/2026  50.650.650.6ER/NR000HybridWind/SolarMonolith 115kV3/1/2013 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2012-044CrawfordKSWERE11/30/201311/1/2013  222ER000ThermalGasSheffield 69kV12/5/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-041DISIS-2012-002-604 SOUTHEASTKayOKOGE4/15/20154/15/2015  121.585.3121.5ER000ThermalCTRose Hill (Open Sky)-Sooner (Ranch Road) 345kV9/30/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-037DISIS-2012-002-605 SOUTHWESTHaleTXSPS3/1/20153/1/2015  203196203ER000ThermalCTTUCO 345kV9/30/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-036DISIS-2012-002-605 SOUTHWESTYoakumTXSPS6/1/20133/1/2013  777ER000ThermalCTMustang 230kV9/30/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-035DISIS-2012-002-605 SOUTHWESTYoakumTXSPS6/1/20134/1/2015  777ER000ThermalCTMustang 230kV9/30/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-034DISIS-2012-002-605 SOUTHWESTYoakumTXSPS6/1/20134/1/2015  777ER000ThermalCTMustang 230kV9/30/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-033DISIS-2012-002-604 SOUTHEASTGarfieldOKOGE12/1/20149/1/2015  98.8298.8298.82ER000WindBreckinridge 138kV9/28/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2012-032DISIS-2012-002-604 SOUTHEASTKayOKOGE11/30/20146/30/2015  299299299ER000WindRose Hill-(Ranch Road) Sooner (Open Sky) 345kV9/28/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-028DISIS-2012-002-604 SOUTHEASTWashitaOKWFEC12/1/201412/22/2015  747474ER000WindGotebo 69kV9/28/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-024IFS-2012-002-01DISIS-2012-002-603 CENTRALFordKSSUNC12/31/20156/1/2017  180180180ER000WindClark County 345kV9/28/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-021DISIS-2012-002-602 NEBRASKALincolnNELES8/1/201312/1/2013  4.84.84.8ER000ThermalGasTerry Bundy Generating Station 115kV9/26/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-020DISIS-2012-002-605 SOUTHWESTAbernathy CountyTXSPS9/30/20156/28/2019  478478478ER000WindTUCO 230kV9/26/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-007DISIS-2012-001-403 CENTRALGrant CountyKSSUNC4/1/20144/15/2014  120120120ER/NR000ThermalGasRubart 115kV3/29/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-004DISIS-2012-001-404 SOUTHEASTCarter CountyOKOGE12/31/201311/21/2014  40.840.840.8ER/NR000WindPooleville-Ratliff (Carter County) 138kV3/27/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-001DISIS-2012-001-405 SOUTHWESTLynn County TexasTXSPS11/30/201212/21/2012  61.261.261.2ER000WindTap Grassland - Borden County 230 kv3/8/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-057DISIS-2011-002-603 CENTRALSumner CountyKSWERE12/31/201312/30/2015  150150150ER000WindCreswell 138kV9/30/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-056BDISIS-2011-002-602 NEBRASKANorth Platte - LexingtonNENPPD6/30/201210/31/2012  4.54.54.5ER000HydroJohn 2 115kV3/8/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-056ADISIS-2011-002-602 NEBRASKANorth Platte - LexingtonNENPPD6/30/201210/31/2012  3.63.63.6ER000HydroJohn 1 115kV3/8/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-056DISIS-2011-002-602 NEBRASKANorth Platte - LexingtonNENPPD6/30/201210/31/2012  3.63.63.6ER000HydroJeffrey 115kV9/30/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-054DISIS-2011-002-604 SOUTHEASTCanadian CountyOKOGE11/30/201312/31/2014  300300300ER000WindCimarron 345kV9/30/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2011-050DISIS-2011-002-604 SOUTHEASTGrady CountyOKAEP12/31/201312/13/2016  108108108ER000WindTap Rush Springs - Marlow 138kV9/30/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-048DISIS-2011-002-605 SOUTHWESTDenver CityTXSPS3/1/20133/1/2013  175165175ER/NR000ThermalCTMustang 230kV9/30/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-046DISIS-2011-002-605 SOUTHWESTQuay CountyNMSPS6/1/20139/5/2013  232323ER000ThermalCTTucumcari 115kV9/29/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-045DISIS-2011-002-605 SOUTHWESTLubbockTXSPS6/1/20135/1/2013  205180205ER000ThermalNG/CTJones 230kV9/29/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-040DISIS-2011-002-604 SOUTHEASTMurray CountyOKOGE12/31/201211/21/2014  111111111ER/NR000WindPooleville-Ratliff (Carter County) 138kV9/16/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-037DISIS-2011-002-604 SOUTHEASTApacheOKWFEC1/1/20122/5/2013  6.66.66.6ER000WindBlue Canyon 5 138kV7/1/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-027DISIS-2011-001-802 NEBRASKAWinsideNENPPD12/31/201212/17/2018  120120120ER/NR000WindWakefield 230kV3/31/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2011-025DISIS-2011-001-805 SOUTHWESTLorenzoTXSPS6/30/201212/15/2018  79.9679.9679.96ER000WindTap Floyd County - Crosby County 115kV3/31/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-022DISIS-2011-001-805 SOUTHWESTHansfordTXSPS12/31/20129/8/2022  299299299ER000WindHitchland 345kV3/31/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-020DISIS-2011-001-804 SOUTHEASTEllisOKOGE12/31/201210/31/2027  165.6165.6165.6ER/NR000WindWoodward EHV 345kV3/31/2011 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2011-019DISIS-2011-001-804 SOUTHEASTWoodward CountyOKOGE12/31/201212/31/2027  175175175ER/NR000WindWoodward EHV 345kV3/31/2011 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2011-018DISIS-2011-001-802 NEBRASKAJefferson CountyNENPPD12/1/201312/31/2013  73.673.673.6ER/NR000WindSteele City 115kV3/31/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-014DISIS-2011-001-805 SOUTHWESTBeaver CountyOKOGE12/31/201312/20/2016  198198198ER000WindBeaver County-Woodward EHV Dbl Ckt (Badger) 345kV3/31/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-011DISIS-2011-001-803 CENTRALWestonMOKCPL12/31/20106/5/2012  505050ER000ThermalCoalIatan 345kV3/31/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-010DISIS-2011-001-804 SOUTHEASTCaddo CountyOKOGE12/1/201210/1/2012  100.8100.8100.8ER000WindMinco 345kV3/30/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-008DISIS-2011-001-803 CENTRALClark CountyKSSUNC12/1/201512/21/2016  600600600ER000WindClark County 345kV3/29/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-057DISIS-2011-001-803 CENTRALLincoln CountyKSMIDW8/1/20129/28/2012  201201201ER/NR000WindRice County 230kV10/27/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-055DISIS-2011-001-804 SOUTHEASTSand SpringsOKAEP12/31/20112/27/2013  4.54.54.5ER000ThermalGasWekiwa 138kV9/30/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-051DISIS-2010-002-602 NEBRASKADixon CountyNENPPD12/15/201212/17/2018  200200200ER000WindWakefield 230kV9/30/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-040DISIS-2010-002-604 SOUTHEASTCanadian CountyOKOGE11/30/201111/23/2012  300300300ER000WindCimarron 345kV8/19/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-036DISIS-2010-002-603 CENTRALDouglas CountyKSWERE8/1/20128/1/2012  4.64.64.6ER000Hydro6th Street 115kV6/30/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-014DISIS-2010-001-805 SOUTHWESTHansford CountyTXSPS12/31/201312/31/2022  358.8358.8358.8ER000WindHitchland 345kV3/31/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-011DISIS-2010-001-804 SOUTHEASTDewey CountyOKOGE12/31/20112/28/2012  29.729.729.7ER000WindTatonga 345kV3/31/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-009DISIS-2010-001-803 CENTRALGray CountyKSSUNC12/1/201112/31/2012  165.6165.6165.6ER000WindBuckner 345kV3/29/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-006DISIS-2010-001-805 SOUTHWESTLubbockTXSPS6/1/20126/30/2011  205180205ER000ThermalGasJones 230kV3/24/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-005DISIS-2010-001-803 CENTRALHarper CountyKSWERE12/1/201212/31/2021  299.2299.2299.2ER000WindViola 345kV3/15/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-003DISIS-2010-001-803 CENTRALCoffey CountyKSWERE12/31/20117/31/2014  99.599.599.5ER000WindWaverly 345kV3/8/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-001DISIS-2010-002-605 SOUTHWESTBeaver CountyOKOGE1/1/20125/15/2015  300300300ER000WindHitchland-Woodward EHV Dbl Ckt (Beaver County) 345kV3/3/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2009-040DISIS-2010-001-803 CENTRALMarshall CountyKSWERE12/31/20129/3/2016  727272ER000WindTap Smittyville - Knob Hill 115KV8/31/2009 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2009-025DISIS-2009-001-604 SOUTHEASTKay CountyOKOGE12/31/201111/1/2012  59.859.859.8ER000WindTAP Deer Creek – Sinclair 69kV6/19/2009 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2009-020DISIS-2010-001-803 CENTRALRush CountyKSMIDW12/31/201110/15/2015  48.348.348.3ER000WindTap Nekoma - Bazine (Walnut Creek) 69kV4/15/2009 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2009-008DISIS-2010-001-803 CENTRALNess CountyKSMIDW9/1/201112/1/2015  198.69198.69198.69ER000WindSouth Hays 230kV3/10/2009 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-129DISIS-2009-001-603 CENTRALCass CountyMOMIPU5/1/20092/15/2002  72643675ER000ThermalCTPleasant Hill 161kV12/12/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-124DISIS-2009-001-603 CENTRALFord CountyKSSUNC1/1/20162/28/2017  200.1200.1200.1ER000WindClark County-Spearville Ckt 1 (Ironwood) 345kV11/14/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-123NDISIS-2010-001-802 NEBRASKAWebster CountyNENPPD12/31/201611/16/2017  89.6689.6689.66ER000WindTap Pauline - Hildreth (Rosemont) 115kV11/12/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-119OICS-2008-001 Prior Queued02 NEBRASKARichardson CountyNEOPPD12/31/2009   606060ER000WindS1399 161kV10/8/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-098DISIS-2010-001-803 CENTRALCoffey CountyKSWERE12/31/201111/30/2015  99.599.599.5ER000WindWaverly 345kV8/22/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2008-092DISIS-2009-001-603 CENTRALEllis CountyKSMIDW12/1/201111/30/2015  200.5200.5200.5ER000WindPost Rock 230kV8/18/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-086N02DISIS-2009-001-602 NEBRASKAAntelope CountyNENPPD 12/31/2014  201201201ER000WindMeadow Grove 230kV8/8/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-079DISIS-2009-001-603 CENTRALGray CountyKSMKEC12/1/201011/2/2011  98.998.998.9ER000WindCrooked Creek 115kV7/29/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-051DISIS-2009-001-605 SOUTHWESTOldham CountyTXSPS12/31/201012/31/2014  161161161ER000WindPotter County 345kV5/30/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-047DISIS-2010-001-805 SOUTHWESTBeaver CountyOKOGE12/31/201212/31/2014  263.13263.13263.13ER000WindHitchland-Woodward EHV Dbl Ckt (Beaver County) 345kV5/16/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-044DISIS-2010-001-804 SOUTHEASTDewey CountyOKOGE12/1/20112/28/2012  197.8197.8197.8ER000WindTatonga 345kV5/15/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-037DISIS-2010-001-804 SOUTHEASTCommanche CountyOKWFEC11/30/201112/17/2011  999999ER000WindTap Washita - Blue Canyon Wind 138kV5/12/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-023DISIS-2009-001-604 SOUTHEASTWashita CountyOKAEP12/1/201011/30/2012  150150150ER000WindHobart Junction 138kV3/28/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-022DISIS-2010-001-805 SOUTHWESTChaves CountyNMSPS9/1/201111/15/2015  299.65299.65299.65ER000WindEddy County-Tolk (Crossroads) 345kV3/28/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-021Coffey CountyKSWERE5/16/20115/16/2011  424242ER000ThermalNuclearWolf Creek 345kV3/24/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-018ICS-2008-001-603 CENTRALFinney CountyKSSPS12/31/201212/13/2013  250250250ER000WindFinney 345kV3/17/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-013ICS-2008-001-604 SOUTHEASTGarfield CountyOKOGE10/1/201012/7/2012  300300300ER000WindHunter 345kV2/19/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-006Caddo ParishLAAEP6/1/20106/16/2010  302030ER000ThermalGasArsenal Hill 138kV1/31/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-005Mayes CountyOKGRDA1/9/20099/2/2009  161616ER000Hydro1/28/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-003ICS-2008-001-604 SOUTHEASTWoodwardOKOGE8/31/200912/14/2009  101.2101.2101.2ER000WindWoodward EHV 138kV1/25/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-002Platte CountyMOKACP1/1/20094/12/2009  656565ER000ThermalCoal1/22/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-062ICS-2008-001-604 SOUTHEASTHarper CountyOKOGE12/31/201112/21/2016  424424424ER000WindWoodward EHV 345kV12/27/2007 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-052ICS-2008-001-604 SOUTHEASTCaddo CountyOKWFEC5/1/20097/1/2009  150150150ER000ThermalGasAnadarko 138kV11/9/2007 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-050ICS-2008-001-604 SOUTHEASTWoodward CountyOKOGE10/1/200912/23/2010  151.8151.8151.8ER000WindWoodward EHV 138kV10/22/2007 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-046ICS-2008-001-605 SOUTHWESTTexas CountyOKSPS12/31/201112/15/2015  200200200ER000WindHitchland 115kV10/15/2007 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-044ICS-2008-001-604 SOUTHEASTBlaine CountyOKOGE12/1/200912/31/2014  299.2299.2299.2ER000WindTatonga 345kV10/2/2007 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-043ICS-2008-001-604 SOUTHEASTGrady CountyOKOGE12/1/200911/1/2010  200200200ER000WindMinco 345kV10/2/2007 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-040DISIS-2009-001-603 CENTRALGray CountyKSSUNC12/15/20106/9/2012  131.1131.1131.1ER000WindBuckner 345kV9/25/2007 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2007-025ICS-2008-001-603 CENTRALBarber CountyKSWERE12/31/200910/1/2012  299.2299.2299.2ER000WindViola 345kV5/24/2007 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-021ICS-2008-001-604 SOUTHEASTDewey CountyOKOGE8/1/200912/31/2014  198.9198.9198.9ER000WindTatonga 345kV5/9/2007 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-011N08ICS-2008-001 Prior Queued02 NEBRASKAKnox CountyNENPPD1/1/2009   818181ER000WindBloomfield 115kV3/19/2007 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-046ICS-2008-001 Prior Queued04 SOUTHEASTDeweyOKOGE12/31/20096/6/2011  129.6129.6129.6ER000WindDewey 138kV12/5/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-044NDISIS-2009-001-602 NEBRASKAPetersburgNENPPD1/1/201012/31/2011  40.540.540.5ER000WindNorth Petersburg 115kV12/4/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-044ICS-2008-001 Prior Queued05 SOUTHWESTHansfordTXSPS10/1/201012/31/2022  370370370ER000WindHitchland 345kV12/4/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-043ICS-2008-001 Prior Queued04 SOUTHEASTBeckham CountyOKAEP8/1/200812/15/2009  999999ER000WindSweetwater 230kV11/17/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-038N019ICS-2008-001 Prior Queued02 NEBRASKABoone CountyNENPPD5/1/201110/31/2011  808080ER000WindPetersburg North 115kV10/26/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-038N005ICS-2008-001 Prior Queued02 NEBRASKACuster CountyNENPPD12/1/201012/31/2012  808080ER000WindBroken Bow 115kV10/17/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-037N1DISIS-2009-001-602 NEBRASKACuster CountyNENPPD1/1/201012/31/2014  757575ER000WindBroken Bow 115kV10/3/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-035ICS-2008-001 Prior Queued04 SOUTHEASTBeckham CountyOKAEP12/1/20084/27/2012  132132132ER000WindSweetwater 230kV8/29/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-03103 CENTRALEllis CountyKSMIDW6/1/20086/1/2008  75.675.675.6ER000ThermalGasKnoll 115kV8/16/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-028LyonKSWERE5/1/20096/1/2009  360300360ER000ThermalGasEmporia 345kV8/11/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-027LyonKSWERE5/1/20086/1/2008  380310380ER000ThermalGasEmporia 345kV8/11/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-026ICS-2008-001 Prior Queued05 SOUTHWESTLeaNMSPS6/1/20086/1/2008  604604604ER000ThermalGasHobbs 230kV & Hobbs 115kV7/26/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-024SICS-2008-001 Prior Queued04 SOUTHEASTHarperOKWFEC12/31/200712/31/2008  18.918.918.9ER000WindBuffalo Bear Tap 69kV7/7/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-021ICS-2008-001 Prior Queued03 CENTRALBarber CountyKSITCGP5/31/200812/1/2008  949494ER000WindFlat Ridge Tap 138kV6/21/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-020SICS-2008-001 Prior Queued05 SOUTHWESTHansfordTXSPS9/1/20073/1/2012  202020ER000WindDWS Frisco 115kV12/31/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-020NICS-2008-001 Prior Queued02 NEBRASKABloomfieldNENPPD1/1/2009   424242ER000WindBloomfield 115kV6/20/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-019GreeneMOSPRM6/1/20101/1/2011  275275275ER000ThermalCoal6/19/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-018ICS-2008-001 Prior Queued05 SOUTHWESTHaleTXSPS6/1/20073/22/2011  168.1168.1168.1ER000ThermalCTTUCO 230kV6/1/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-01505 SOUTHWESTDenver CityTXSPS4/1/20076/1/2007  150150150ER000ThermalGasMustang 230kV4/24/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-01004 SOUTHEASTHempstead Co.ARAEP6/1/201112/20/2012  620610620ER000ThermalCoalTurk 138kV2/27/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-008Caddo Prsh.LAAEP6/1/20086/26/2010  550490550ER000ThermalGasArsenal Hill 138kV2/27/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-002ICS-2008-001 Prior Queued04 SOUTHEASTBeckham OKAEP12/31/200612/28/2010  100.8100.8100.8ER000WindSweetwater 230kV1/9/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2005-024Tulsa CountyOKAEP6/1/20073/22/2007  181172181ER000ThermalGas12/13/2005 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2005-022Caddo CountyOKAEP6/1/200712/27/2007  177168177ER000ThermalGas12/13/2005 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2005-013ICS-2008-001 Prior Queued03 CENTRALElk CountyKSWERE11/1/20077/5/2011  199.8199.8199.8ER000WindCaney River 345kV8/22/2005 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2005-012ICS-2008-001 Prior Queued03 CENTRALFord CountyKSSUNC12/31/20159/1/2012  248.4248.4248.4ER000WindClark County-Spearville Ckt 1 (Ironwood) 345kV8/8/2005 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2005-008ICS-2008-001 Prior Queued04 SOUTHEASTHarper CountyOKOGE7/31/20076/30/2007  120120120ER000WindWoodward 138kV4/1/2005 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2005-003ICS-2008-001 Prior Queued04 SOUTHEASTCaddo & Kiowa CountiesOKWFEC12/1/200512/15/2005  30.630.630.6ER000WindWashita 138kV1/21/2005 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-023NICS-2008-001 Prior Queued02 NEBRASKAColumbusNENPPD1/1/2009   757575ER000ThermalCoalColumbus Co 115kV11/29/2004 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-023ICS-2008-001 Prior Queued04 SOUTHEASTApacheOKWFEC12/1/200512/15/2005  20.620.620.6ER000WindWashita 138kV10/26/2004 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-022NHastingsNENPPD1/1/2005   111111ER000Thermal10/20/2004 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-020ICS-2008-001 Prior Queued04 SOUTHEASTCuster CountyOKAEP12/31/20051/1/2006  272727ER000WindClinton Junction-Weatherford Southeast 138kV10/8/2004 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-019NColfax CountyNENPPD1/1/2005   0.10.10.1ER000ThermalGas10/4/2004 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-018N1BrownsvilleNENPPD1/1/2005   222222ER000ThermalNuclear9/20/2004 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-017NColumbusNENPPD1/1/2007   555ER000Hydro9/13/2004 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-01703 CENTRALRiverton SE Cherokee CntyKSEDE1/1/2007   250250250ER/NR000ThermalCT/STRiverton 161kV8/23/2004 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-01505 SOUTHWESTDenver City/YoakumTXSPS4/1/20064/1/2006  150150150ER000ThermalCT7/12/2004 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-014ICS-2008-001 Prior Queued03 CENTRALEdwardsKSMKEC11/15/200512/31/2012  152152152ER000WindSpearville 230kV4/22/2004 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-00803 CENTRALPlatte CountyMOKCPL6/1/20096/5/2012  850850850ER000ThermalCoal3/26/2004 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-002OWashington CountyNEOPPD1/1/2007   484848ER000ThermalNuclear1/21/2004 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2003-022ICS-2008-001 Prior Queued04 SOUTHEASTCuster/WasitaOKAEP12/31/20041/1/2006  120120120ER000WindClinton Junction-Weatherford Southeast 138kV12/31/2003 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2003-021NICS-2008-001 Prior Queued02 NEBRASKAAinsworthNENPPD10/1/2005   757575ER000WindAinsworth Wind Tap 115kV12/29/2003 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2003-020ICS-2008-001 Prior Queued05 SOUTHWESTCarson CountyTXSPS6/1/20078/1/2012  159.1159.1159.1ER000WindMartin 115kV12/29/2003 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2003-019ICS-2008-001 Prior Queued03 CENTRALSalina NC Ellsworth CntyKSMIDW11/1/200611/1/2006  249.3249.3249.3ER000WindSmoky Hills Tap 230kV11/24/2003 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2003-017NBrownsvilleNENPPD1/1/2007   505050ER000ThermalNuclear10/15/2003 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2003-008OOtoe CountyNEOPPD5/1/2009   700700700ER000ThermalCoal7/15/2003 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2003-006AICS-2008-001 Prior Queued03 CENTRALCloud CountyKSMKEC    201201201ER000WindElm Creek 230kV7/9/2003 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2003-005ICS-2008-001 Prior Queued04 SOUTHEASTApacheOKWFEC12/1/2006   999999ER000WindAnadarko - Paradise (Blue Canyon) 138kV6/5/2003 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2003-004ICS-2008-001 Prior Queued04 SOUTHEASTApacheOKWFEC12/1/200512/15/2005  100100100ER000WindWashita 138kV6/5/2003 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2002-025AICS-2008-001 Prior Queued03 CENTRALSpearvilleKSMKEC6/1/2006   100.5100.5100.5ER000WindSpearville 230kV10/31/2002 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2002-023NHarmonyNENPPD    0.80.80.8ER000WindHarmony 115kV9/28/2002 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2002-022ICS-2008-001 Prior Queued05 SOUTHWESTOldham County (Wildorado)TXSPS12/15/2006   239.2239.2239.2ER000WindBushland 230kV9/12/2002 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2002-009ICS-2008-001 Prior Queued05 SOUTHWESTHansford CountyTXSPS9/30/20069/30/2006  67.267.267.2ER000WindHansford 115kV7/19/2002 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2002-008ICS-2008-001 Prior Queued05 SOUTHWESTHansford CountyTXSPS11/1/200712/30/2008  240240240ER000WindHitchland 345kV7/19/2002 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2002-005ICS-2008-001 Prior Queued04 SOUTHEASTHammonOKWFEC12/31/200612/31/2008  123123123ER000WindRed Hills Tap 138kV4/28/2002 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2002-004NGrand IslandNENPPD12/1/2003   808080ER000ThermalGas4/16/2002 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2002-004ICS-2008-001 Prior Queued03 CENTRALBeaumont SE Butler CntyKSWERE9/30/200312/15/2005  153153153ER000WindLatham 345kV4/12/2002 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-04003 CENTRALLaRussell Energy Ctr.MOEDE6/1/20034/24/2003  505050ER000ThermalCTLaRussell Energy Center 161kV11/27/2001 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-039MICS-2008-001 Prior Queued03 CENTRALWichita CountyKSSUNC12/1/2008   100100100ER000WindCentral Plains Tap 115kV11/1/2001 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-039AICS-2008-001 Prior Queued03 CENTRALKiowa CountyKSMKEC    104104104ER000WindShooting Star Tap 115kV10/30/2001 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-037ICS-2008-001 Prior Queued04 SOUTHEASTWoodwardOKOGE10/1/200211/12/2003  102102102ER000WindFPL Moreland Tap 138kV10/18/2001 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-033ICS-2008-001 Prior Queued05 SOUTHWESTChaves County (Melrose)NMSPS10/1/200212/22/2005  120120120ER000WindSan Juan Tap 230kV9/17/2001 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-03003 CENTRALLaRussell Energy CenterMOEDE6/1/20034/25/2003  505050ER000ThermalCTLaRussell Energy Center 161kV9/4/2001 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-029NBeatriceNENPPD1/1/20051/1/2005  250250250ER000ThermalGas8/15/2001 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-026ICS-2008-001 Prior Queued04 SOUTHEASTMeersOKWFEC10/1/200310/1/2003  74.2574.2574.25ER000WindWashita 138kV7/24/2001 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-024Washington CountyARAEP5/1/20077/1/2007  630580630ER000ThermalCTSWEPCO Tontitown 161kV Substation7/9/2001 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-018Neosho CountyKSWERE1/1/20021/1/2002  474747ER000ThermalGasChanute NW Neosho Cnty By Tioga Sub5/15/2001 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-014ICS-2008-001 Prior Queued04 SOUTHEASTSleeping BearOKWFEC6/30/20074/15/2007  94.594.594.5ER000WindFt Supply 138kV4/24/2001 IA FULLY EXECUTED/COMMERCIAL OPERATION   

Download data as CSV