OASIS Apps

- Curtailment Viewer
- DC Tie Viewer
- Price Discounts
- Price Matrix
- Transmission Load Relief

- SPP OASIS Archive Map
    > SPP OASIS Archive Page
    > Market System Status
    > Member Related Postings
    > FERC890 Items

- Studies Postings
 

GI Active Requests

Last Updated: 8/11/2022    Download data as CSV

Generation Interconnection NumberIFS Queue NumberCurrent ClusterCluster GroupNearest Town or CountyStateTO at POIIn-Service Date (proposed) Commercial Operation DateCessation DateReplacement Generator Commercial Op. DateCapacity (MW)MAX Summer MWMAX Winter MWService TypeGeneration TypeFuel Type Substation or LineRequest ReceivedStatusCause of DelayAssociated StudiesImpact ReportFacility Report
GEN-2001-014ICS-2008-001 Prior Queued04 SOUTHEASTSleeping BearOKWFEC6/30/20074/15/2007  94.594.594.5ERWindFt Supply 138kV4/24/2001IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-018Neosho CountyKSWERE1/1/20021/1/2002  474747ERThermalGasChanute NW Neosho Cnty By Tioga Sub5/15/2001IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-024Washington CountyARAEP5/1/20077/1/2007  630580630ERThermalCTSWEPCO Tontitown 161kV Substation7/9/2001IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-026ICS-2008-001 Prior Queued04 SOUTHEASTMeersOKWFEC10/1/200310/1/2003  74.2574.2574.25ERWindWashita 138kV7/24/2001IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-029NBeatriceNENPPD1/1/20051/1/2005  250250250ERThermalGas8/15/2001IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-03003 CENTRALLaRussell Energy CenterMOEDE6/1/20034/25/2003  505050ERThermalCTLaRussell Energy Center 161kV9/4/2001IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-033ICS-2008-001 Prior Queued05 SOUTHWESTChaves County (Melrose)NMSPS10/1/200212/22/2005  180180180ERWindSan Juan Tap 230kV9/17/2001IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-036ICS-2008-001 Prior Queued05 SOUTHWESTTucumcariNMSPS10/1/200212/31/2004  808080ERWindNorton 115kV Switching Station10/15/2001IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-037ICS-2008-001 Prior Queued04 SOUTHEASTWoodwardOKOGE10/1/200211/12/2003  102102102ERWindFPL Moreland Tap 138kV10/18/2001IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-039AICS-2008-001 Prior Queued03 CENTRALKiowa CountyKSMKEC    104104104ERWindShooting Star Tap 115kV10/30/2001IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-039MICS-2008-001 Prior Queued03 CENTRALWichita CountyKSSUNC12/1/2008   100100100ERWindCentral Plains Tap 115kV11/1/2001IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-04003 CENTRALLaRussell Energy Ctr.MOEDE6/1/20034/24/2003  505050ERThermalCTLaRussell Energy Center 161kV11/27/2001IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2002-004ICS-2008-001 Prior Queued03 CENTRALBeaumont SE Butler CntyKSWERE9/30/200312/15/2005  153153153ERWindLatham 345kV4/12/2002IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2002-004NGrand IslandNENPPD12/1/2003   808080ERThermalGas4/16/2002IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2002-005ICS-2008-001 Prior Queued04 SOUTHEASTHammonOKWFEC12/31/200612/31/2008  123123123ERWindRed Hills Tap 138kV4/28/2002IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2002-008ICS-2008-001 Prior Queued05 SOUTHWESTHansford CountyTXSPS11/1/200712/30/2008  240240240ERWindHitchland 345kV7/19/2002IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2002-009ICS-2008-001 Prior Queued05 SOUTHWESTHansford CountyTXSPS9/30/20069/30/2006  67.267.267.2ERWindHansford 115kV7/19/2002IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2002-022ICS-2008-001 Prior Queued05 SOUTHWESTOldham County (Wildorado)TXSPS12/15/2006   239.2239.2239.2ERWindBushland 230kV9/12/2002IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2002-023NHarmonyNENPPD    0.80.80.8ERWindHarmony 115kV9/28/2002IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2002-025AICS-2008-001 Prior Queued03 CENTRALSpearvilleKSMKEC6/1/2006   100.5100.5100.5ERWindSpearville 230kV10/31/2002IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2003-004ICS-2008-001 Prior Queued04 SOUTHEASTApacheOKWFEC12/1/200512/15/2005  100100100ERWindWashita 138kV6/5/2003IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2003-005ICS-2008-001 Prior Queued04 SOUTHEASTApacheOKWFEC12/1/2006   999999ERWindAnadarko - Paradise (Blue Canyon) 138kV6/5/2003IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2003-006AICS-2008-001 Prior Queued03 CENTRALCloud CountyKSMKEC    201201201ERWindElm Creek 230kV7/9/2003IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2003-008OOtoe CountyNEOPPD5/1/2009   700700700ERThermalCoal7/15/2003IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2003-017NBrownsvilleNENPPD1/1/2007   505050ERNuclear10/15/2003IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2003-019ICS-2008-001 Prior Queued03 CENTRALSalina NC Ellsworth CntyKSMIDW11/1/200611/1/2006  249.3249.3249.3ERWindSmoky Hills Tap 230kV11/24/2003IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2003-020ICS-2008-001 Prior Queued05 SOUTHWESTCarson CountyTXSPS6/1/20078/1/2012  159.1159.1159.1ERWindMartin 115kV12/29/2003IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2003-021NICS-2008-001 Prior Queued02 NEBRASKAAinsworthNENPPD10/1/2005   757575ERWindAinsworth Wind Tap 115kV12/29/2003IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2003-022ICS-2008-001 Prior Queued04 SOUTHEASTCuster/WasitaOKAEP12/31/20041/1/2006  120120120ERWindClinton Junction-Weatherford Southeast 138kV12/31/2003IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-002OWashington CountyNEOPPD1/1/2007   484848ERNuclear1/21/2004IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-00803 CENTRALPlatte CountyMOKCPL6/1/20096/5/2012  850850850ERThermalCoal3/26/2004IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-014ICS-2008-001 Prior Queued03 CENTRALEdwardsKSMKEC11/15/200512/31/2012  152152152ERWindSpearville 230kV4/22/2004IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-01505 SOUTHWESTDenver City/YoakumTXSPS4/1/20064/1/2006  150150150ERThermalCT7/12/2004IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-01703 CENTRALRiverton SE Cherokee CntyKSEDE1/1/2007   250250250ER/NRThermalCT/STRiverton 161kV8/23/2004IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-017NColumbusNENPPD1/1/2007   555ERHydro9/13/2004IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-018N1BrownsvilleNENPPD1/1/2005   222222ERNuclear9/20/2004IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-019NColfax CountyNENPPD1/1/2005   0.10.10.1ERThermalGas10/4/2004IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-020ICS-2008-001 Prior Queued04 SOUTHEASTCuster CountyOKAEP12/31/20051/1/2006  272727ERWindClinton Junction-Weatherford Southeast 138kV10/8/2004IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-022NHastingsNENPPD1/1/2005   111111ERThermal10/20/2004IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-023ICS-2008-001 Prior Queued04 SOUTHEASTApacheOKWFEC12/1/200512/15/2005  20.620.620.6ERWindWashita 138kV10/26/2004IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-023NICS-2008-001 Prior Queued02 NEBRASKAColumbusNENPPD1/1/2009   757575ERThermalCoalColumbus Co 115kV11/29/2004IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2005-003ICS-2008-001 Prior Queued04 SOUTHEASTCaddo & Kiowa CountiesOKWFEC12/1/200512/15/2005  30.630.630.6ERWindWashita 138kV1/21/2005IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2005-008ICS-2008-001 Prior Queued04 SOUTHEASTHarper CountyOKOGE7/31/20076/30/2007  120120120ERWindWoodward 138kV4/1/2005IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2005-012ICS-2008-001 Prior Queued03 CENTRALFord CountyKSSUNC12/31/20159/1/2012  248.4248.4248.4ERWindClark County-Spearville Ckt 1 (Ironwood) 345kV8/8/2005IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2005-013ICS-2008-001 Prior Queued03 CENTRALElk CountyKSWERE11/1/20077/5/2011  199.8199.8199.8ERWindCaney River 345kV8/22/2005IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2005-022Caddo CountyOKAEP6/1/200712/27/2007  177168177ERThermalGas12/13/2005IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2005-024Tulsa CountyOKAEP6/1/200711/30/2007  181172181ERThermalGas12/13/2005IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-002ICS-2008-001 Prior Queued04 SOUTHEASTBeckham OKAEP12/31/200612/28/2010  100.8100.8100.8ERWindSweetwater 230kV1/9/2006IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-008Caddo Prsh.LAAEP6/1/20086/26/2010  550490550ERThermalGasArsenal Hill 138kV2/27/2006IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-01004 SOUTHEASTHempstead Co.ARAEP6/1/201112/20/2012  620610620ERThermalCoalTurk 138kV2/27/2006IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-01505 SOUTHWESTDenver CityTXSPS4/1/20076/1/2007  150150150ERThermalGasMustang 230kV4/24/2006IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-018ICS-2008-001 Prior Queued05 SOUTHWESTHaleTXSPS6/1/20073/22/2011  168.1168.1168.1ERThermalCTTUCO 230kV6/1/2010IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-019GreeneMOSPRM6/1/20101/1/2011  275275275ERThermalCoal6/19/2006IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-020NICS-2008-001 Prior Queued02 NEBRASKABloomfieldNENPPD1/1/2009   424242ERWindBloomfield 115kV6/20/2006IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-020SICS-2008-001 Prior Queued05 SOUTHWESTHansfordTXSPS9/1/20073/1/2012  202020ERWindDWS Frisco 115kV12/31/2010IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-021ICS-2008-001 Prior Queued03 CENTRALBarber CountyKSITCGP5/31/200812/1/2008  949494ERWindFlat Ridge Tap 138kV6/21/2006IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-024SICS-2008-001 Prior Queued04 SOUTHEASTHarperOKWFEC12/31/200712/31/2008  18.918.918.9ERWindBuffalo Bear Tap 69kV7/7/2006IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-026ICS-2008-001 Prior Queued05 SOUTHWESTLeaNMSPS6/1/20086/1/2008  604604604ERThermalGasHobbs 230kV & Hobbs 115kV7/26/2006IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-027LyonKSWERE5/1/20086/1/2008  380310380ERThermalGasEmporia 345kV8/11/2006IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-028LyonKSWERE5/1/20096/1/2009  360300360ERThermalGasEmporia 345kV8/11/2006IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-03103 CENTRALEllis CountyKSMIDW6/1/20086/1/2008  75.675.675.6ERThermalGasKnoll 115kV8/16/2006IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-035ICS-2008-001 Prior Queued04 SOUTHEASTBeckham CountyOKAEP12/1/20084/27/2012  132132132ERWindSweetwater 230kV8/29/2006IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-037N1DISIS-2009-001-602 NEBRASKACuster CountyNENPPD1/1/201012/31/2014  757575ERWindBroken Bow 115kV10/3/2006IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-038N005ICS-2008-001 Prior Queued02 NEBRASKACuster CountyNENPPD12/1/201012/31/2012  808080ERWindBroken Bow 115kV10/17/2006IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-038N019ICS-2008-001 Prior Queued02 NEBRASKABoone CountyNENPPD5/1/201110/31/2011  808080ERWindPetersburg North 115kV10/26/2006IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-043ICS-2008-001 Prior Queued04 SOUTHEASTBeckham CountyOKAEP8/1/200812/15/2009  999999ERWindSweetwater 230kV11/17/2006IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-044ICS-2008-001 Prior Queued05 SOUTHWESTHansfordTXSPS10/1/201012/31/2022  370370370ERWindHitchland 345kV12/4/2006IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-044NDISIS-2009-001-602 NEBRASKAPetersburgNENPPD1/1/201012/31/2011  40.540.540.5ERWindNorth Petersburg 115kV12/4/2006IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-046ICS-2008-001 Prior Queued04 SOUTHEASTDeweyOKOGE12/31/20096/6/2011  129.6129.6129.6ERWindDewey 138kV12/5/2006IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-011N08ICS-2008-001 Prior Queued02 NEBRASKAKnox CountyNENPPD1/1/2009   818181ERWindBloomfield 115kV3/19/2007IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-021ICS-2008-001-604 SOUTHEASTDewey CountyOKOGE8/1/200912/31/2014  198.9198.9198.9ERWindTatonga 345kV5/9/2007IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-025ICS-2008-001-603 CENTRALBarber CountyKSWERE12/31/200910/1/2012  299.2299.2299.2ERWindViola 345kV5/24/2007IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-040DISIS-2009-001-603 CENTRALGray CountyKSSUNC12/15/20106/9/2012  131.1131.1131.1ERWindBuckner 345kV9/25/2007IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-043ICS-2008-001-604 SOUTHEASTGrady CountyOKOGE12/1/200911/1/2010  200200200ERWindMinco 345kV10/2/2007IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-044ICS-2008-001-604 SOUTHEASTBlaine CountyOKOGE12/1/200912/31/2014  299.2299.2299.2ERWindTatonga 345kV10/2/2007IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-046ICS-2008-001-605 SOUTHWESTTexas CountyOKSPS12/31/201112/15/2015  200200200ERWindHitchland 115kV10/15/2007IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-050ICS-2008-001-604 SOUTHEASTWoodward CountyOKOGE10/1/200912/23/2010  151.8151.8151.8ERWindWoodward EHV 138kV10/22/2007IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-052ICS-2008-001-604 SOUTHEASTCaddo CountyOKWFEC5/1/20097/1/2009  150150150ERThermalGasAnadarko 138kV11/9/2007IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-062ICS-2008-001-604 SOUTHEASTHarper CountyOKOGE12/31/201112/21/2016  424424424ERWindWoodward EHV 345kV12/27/2007IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-002Platte CountyMOKACP1/1/20094/12/2009  656565ERThermalCoal1/22/2008IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-003ICS-2008-001-604 SOUTHEASTWoodwardOKOGE8/31/200912/14/2009  101.2101.2101.2ERWindWoodward EHV 138kV1/25/2008IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-005Mayes CountyOKGRDA1/9/20099/2/2009  161616ERHydro1/28/2008IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-006Caddo ParishLAAEP6/1/20106/16/2010  303030ERThermalGasArsenal Hill 138kV1/31/2008IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-013ICS-2008-001-604 SOUTHEASTGarfield CountyOKOGE10/1/201012/7/2012  300300300ERWindHunter 345kV2/19/2008IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-018ICS-2008-001-603 CENTRALFinney CountyKSSPS12/31/201212/13/2013  250250250ERWindFinney 345kV3/17/2008IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-021Coffey CountyKSWERE5/16/20115/16/2011  424242ERNuclearWolf Creek 345kV3/24/2008IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-022DISIS-2010-001-805 SOUTHWESTChaves CountyNMSPS9/1/201111/15/2015  299.65299.65299.65ERWindEddy County-Tolk (Crossroads) 345kV3/28/2008IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-023DISIS-2009-001-604 SOUTHEASTWashita CountyOKAEP12/1/201011/30/2012  150150150ERWindHobart Junction 138kV3/28/2008IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-037DISIS-2010-001-804 SOUTHEASTCommanche CountyOKWFEC11/30/201112/17/2011  999999ERWindTap Washita - Blue Canyon Wind 138kV5/12/2008IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-044DISIS-2010-001-804 SOUTHEASTDewey CountyOKOGE12/1/20112/28/2012  197.8197.8197.8ERWindTatonga 345kV5/15/2008IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-047DISIS-2010-001-805 SOUTHWESTBeaver CountyOKOGE12/31/201212/31/2014  263.13263.13263.13ERWindHitchland-Woodward EHV Dbl Ckt (Beaver County) 345kV5/16/2008IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-051DISIS-2009-001-605 SOUTHWESTOldham CountyTXSPS12/31/201012/31/2014  161161161ERWindPotter County 345kV5/30/2008IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-079DISIS-2009-001-603 CENTRALGray CountyKSMKEC12/1/201011/2/2011  98.998.998.9ERWindCrooked Creek 115kV7/29/2008IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-086N02DISIS-2009-001-602 NEBRASKAAntelope CountyNENPPD 12/31/2014  201201201ERWindMeadow Grove 230kV8/8/2008IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-092DISIS-2009-001-603 CENTRALEllis CountyKSMIDW12/1/201111/30/2015  200.5200.5200.5ERWindPost Rock 230kV8/18/2008IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-098DISIS-2010-001-803 CENTRALCoffey CountyKSWERE12/31/201111/30/2015  99.599.599.5ERWindWaverly 345kV8/22/2008IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-119OICS-2008-001 Prior Queued02 NEBRASKARichardson CountyNEOPPD12/31/2009   606060ERWindS1399 161kV10/8/2008IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-123NDISIS-2010-001-802 NEBRASKAWebster CountyNENPPD12/31/201611/16/2017  89.6689.6689.66ERWindTap Pauline - Hildreth (Rosemont) 115kV11/12/2008IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-124DISIS-2009-001-603 CENTRALFord CountyKSSUNC1/1/20162/28/2017  200.1200.1200.1ERWindClark County-Spearville Ckt 1 (Ironwood) 345kV11/14/2008IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-129DISIS-2009-001-603 CENTRALCass CountyMOMIPU5/1/20092/15/2002  72643675ERThermalCTPleasant Hill 161kV12/12/2008IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2009-008DISIS-2010-001-803 CENTRALNess CountyKSMIDW9/1/201112/1/2015  198.69198.69198.69ERWindSouth Hays 230kV3/10/2009IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2009-020DISIS-2010-001-803 CENTRALRush CountyKSMIDW12/31/201110/15/2015  48.348.348.3ERWindTap Nekoma - Bazine (Walnut Creek) 69kV4/15/2009IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2009-025DISIS-2009-001-604 SOUTHEASTKay CountyOKOGE12/31/201111/1/2012  59.859.859.8ERWindTAP Deer Creek – Sinclair 69kV6/19/2009IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2009-040DISIS-2010-001-803 CENTRALMarshall CountyKSWERE12/31/20129/3/2016  727272ERWindTap Smittyville - Knob Hill 115KV8/31/2009IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-001DISIS-2010-002-605 SOUTHWESTBeaver CountyOKOGE1/1/20125/15/2015  300300300ERWindHitchland-Woodward EHV Dbl Ckt (Beaver County) 345kV3/3/2010IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-003DISIS-2010-001-803 CENTRALCoffey CountyKSWERE12/31/20117/31/2014  99.599.599.5ERWindWaverly 345kV3/8/2010IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-005DISIS-2010-001-803 CENTRALHarper CountyKSWERE12/1/201212/31/2021  299.2299.2299.2ERWindViola 345kV3/15/2010IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-006DISIS-2010-001-805 SOUTHWESTLubbockTXSPS6/1/20126/30/2011  205180205ERThermalGasJones 230kV3/24/2010IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-009DISIS-2010-001-803 CENTRALGray CountyKSSUNC12/1/201112/31/2012  165.6165.6165.6ERWindBuckner 345kV3/29/2010IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-011DISIS-2010-001-804 SOUTHEASTDewey CountyOKOGE12/31/20112/28/2012  29.729.729.7ERWindTatonga 345kV3/31/2010IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-014DISIS-2010-001-805 SOUTHWESTHansford CountyTXSPS12/31/201312/31/2022  358.8358.8358.8ERWindHitchland 345kV3/31/2010IA FULLY EXECUTED/ON SCHEDULE   
GEN-2010-036DISIS-2010-002-603 CENTRALDouglas CountyKSWERE8/1/20128/1/2012  4.64.64.6ERHydro6th Street 115kV6/30/2010IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-040DISIS-2010-002-604 SOUTHEASTCanadian CountyOKOGE11/30/201111/23/2012  300300300ERWindCimarron 345kV8/19/2010IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-051DISIS-2010-002-602 NEBRASKADixon CountyNENPPD12/15/201212/17/2018  200200200ERWindWakefield 230kV9/30/2010IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-055DISIS-2011-001-804 SOUTHEASTSand SpringsOKAEP12/31/20112/27/2013  4.54.54.5ERThermalGasWekiwa 138kV9/30/2010IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-057DISIS-2011-001-803 CENTRALLincoln CountyKSMIDW8/1/20129/28/2012  201201201ER/NRWindRice County 230kV10/27/2010IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-008DISIS-2011-001-803 CENTRALClark CountyKSSUNC12/1/201512/21/2016  600600600ERWindClark County 345kV3/29/2011IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-010DISIS-2011-001-804 SOUTHEASTCaddo CountyOKOGE12/1/201210/1/2012  100.8100.8100.8ERWindMinco 345kV3/30/2011IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-011DISIS-2011-001-803 CENTRALWestonMOKCPL12/31/20106/5/2012  505050ERThermalCoalIatan 345kV3/31/2011IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-014DISIS-2011-001-805 SOUTHWESTBeaver CountyOKOGE12/31/201312/20/2016  198198198ERWindBeaver County-Woodward EHV Dbl Ckt (Badger) 345kV3/31/2011IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-018DISIS-2011-001-802 NEBRASKAJefferson CountyNENPPD12/1/201312/31/2013  73.673.673.6ER/NRWindSteele City 115kV3/31/2011IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-019DISIS-2011-001-804 SOUTHEASTWoodward CountyOKOGE12/31/201212/31/2020  175175175ER/NRWindWoodward EHV 345kV3/31/2011IA FULLY EXECUTED/ON SCHEDULE   
GEN-2011-020DISIS-2011-001-804 SOUTHEASTEllisOKOGE12/31/201212/31/2020  165.6165.6165.6ER/NRWindWoodward EHV 345kV3/31/2011IA FULLY EXECUTED/ON SCHEDULE   
GEN-2011-022DISIS-2011-001-805 SOUTHWESTHansfordTXSPS12/31/201212/31/2022  299299299ERWindHitchland 345kV3/31/2011IA FULLY EXECUTED/ON SCHEDULE   
GEN-2011-025DISIS-2011-001-805 SOUTHWESTLorenzoTXSPS6/30/201212/15/2018  79.9679.9679.96ERWindTap Floyd County - Crosby County 115kV3/31/2011IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-027DISIS-2011-001-802 NEBRASKAWinsideNENPPD12/31/201212/17/2018  120120120ER/NRWindWakefield 230kV3/31/2011IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-037DISIS-2011-002-604 SOUTHEASTApacheOKWFEC1/1/20122/5/2013  6.66.66.6ERWindBlue Canyon 5 138kV7/1/2011IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-040DISIS-2011-002-604 SOUTHEASTMurray CountyOKOGE12/31/201211/21/2014  111111111ER/NRWindPooleville-Ratliff (Carter County) 138kV9/16/2011IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-045DISIS-2011-002-605 SOUTHWESTLubbockTXSPS6/1/20135/1/2013  205180205ERThermalNG/CTJones 230kV9/29/2011IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-046DISIS-2011-002-605 SOUTHWESTQuay CountyNMSPS6/1/20139/5/2013  232323ERThermalCTTucumcari 115kV9/29/2011IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-048DISIS-2011-002-605 SOUTHWESTDenver CityTXSPS3/1/20133/1/2013  175165175ER/NRThermalCTMustang 230kV9/30/2011IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-050DISIS-2011-002-604 SOUTHEASTGrady CountyOKAEP12/31/201312/13/2016  108108108ERWindTap Rush Springs - Marlow 138kV9/30/2011IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-054DISIS-2011-002-604 SOUTHEASTCanadian CountyOKOGE11/30/201312/31/2014  300300300ERWindCimarron 345kV9/30/2011IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2011-056DISIS-2011-002-602 NEBRASKANorth Platte - LexingtonNENPPD6/30/201210/31/2012  3.63.63.6ERHydroJeffrey 115kV9/30/2011IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-056ADISIS-2011-002-602 NEBRASKANorth Platte - LexingtonNENPPD6/30/201210/31/2012  3.63.63.6ERHydroJohn 1 115kV3/8/2012IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-056BDISIS-2011-002-602 NEBRASKANorth Platte - LexingtonNENPPD6/30/201210/31/2012  4.54.54.5ERHydroJohn 2 115kV3/8/2012IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-057DISIS-2011-002-603 CENTRALSumner CountyKSWERE12/31/201312/30/2015  150150150ERWindCreswell 138kV9/30/2011IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-001DISIS-2012-001-405 SOUTHWESTLynn County TexasTXSPS11/30/201212/21/2012  61.261.261.2ERWindTap Grassland - Borden County 230 kv3/8/2012IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-004DISIS-2012-001-404 SOUTHEASTCarter CountyOKOGE12/31/201311/21/2014  40.840.840.8ER/NRWindPooleville-Ratliff (Carter County) 138kV3/27/2012IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-007DISIS-2012-001-403 CENTRALGrant CountyKSSUNC4/1/20144/15/2014  120120120ER/NRThermalGasRubart 115kV3/29/2012IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-020DISIS-2012-002-605 SOUTHWESTAbernathy CountyTXSPS9/30/20156/28/2019  478478478ERWindTUCO 230kV9/26/2012IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-021DISIS-2012-002-602 NEBRASKALincolnNELES8/1/201312/1/2013  4.84.84.8ERThermalGasTerry Bundy Generating Station 115kV9/26/2012IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-024IFS-2012-002-01DISIS-2012-002-603 CENTRALFordKSSUNC12/31/20156/1/2017  180180180ERWindClark County 345kV9/28/2012IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-028DISIS-2012-002-604 SOUTHEASTWashitaOKWFEC12/1/201412/22/2015  747474ERWindGotebo 69kV9/28/2012IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-032DISIS-2012-002-604 SOUTHEASTKayOKOGE11/30/20146/30/2015  299299299ERWindRose Hill-(Ranch Road) Sooner (Open Sky) 345kV9/28/2012IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-033DISIS-2012-002-604 SOUTHEASTGarfieldOKOGE12/1/20149/1/2015  98.8298.8298.82ERWindBreckinridge 138kV9/28/2012IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2012-034DISIS-2012-002-605 SOUTHWESTYoakumTXSPS6/1/20134/1/2015  777ERThermalCTMustang 230kV9/30/2012IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-035DISIS-2012-002-605 SOUTHWESTYoakumTXSPS6/1/20134/1/2015  777ERThermalCTMustang 230kV9/30/2012IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-036DISIS-2012-002-605 SOUTHWESTYoakumTXSPS6/1/20133/1/2013  777ERThermalCTMustang 230kV9/30/2012IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-037DISIS-2012-002-605 SOUTHWESTHaleTXSPS3/1/20153/1/2015  203196203ERThermalCTTUCO 345kV9/30/2012IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-041DISIS-2012-002-604 SOUTHEASTKayOKOGE4/15/20154/15/2015  121.585.3121.5ERThermalCTRose Hill (Open Sky)-Sooner (Ranch Road) 345kV9/30/2012IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-044CrawfordKSWERE11/30/201311/1/2013  222ERThermalGasSheffield 69kV12/5/2012IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2013-002IFS-2013-001-01DISIS-2013-001-402 NEBRASKALancasterNENPPD12/31/201312/1/2023  50.650.650.6ER/NRWindMonolith 115kV3/1/2013IA FULLY EXECUTED/ON SCHEDULE   
GEN-2013-007DISIS-2013-001-404 SOUTHEASTMurrayOKOGE12/31/201411/23/2015  100100100ER/NRWindTap Prices Falls - Carter 138kV3/25/2013IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2013-008DISIS-2013-001-402 NEBRASKAJeffersonNENPPD12/31/201312/31/2013  1.21.21.2ERWindSteele City 115kV3/27/2013IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2013-011IFS-2013-001-02DISIS-2013-001-404 SOUTHEASTHempsteadARAEP 12/18/2012  304030ERThermalCoalTurk 138kV3/28/2013IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2013-012DISIS-2013-001-404 SOUTHEASTLogan CountyOKOGE11/30/20148/11/2014  14768147ERThermalGasRedbud 345kV3/28/2013IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2013-016IFS-2013-001-03DISIS-2013-001-405 SOUTHWESTHaleTXSPS12/1/201610/19/2019  203191203ERThermalCTTUCO 345kV3/29/2013IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2013-019IFS-2013-002-01DISIS-2013-002-202 NEBRASKALancasterNENPPD6/30/201412/1/2023  73.673.673.6ER/NRWindMonolith 115kV4/17/2013IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2013-022IFS-2013-002-02DISIS-2013-002-205 SOUTHWESTQuayNMSPS5/1/201512/7/2016  252525ER/NRSolarNorton 115kV Switching Station9/5/2013IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2013-027IFS-2014-002-02DISIS-2014-002-605 SOUTHWESTBaileyTXSPS3/31/201612/10/2018  148.4148.4148.4ER/NRWindTolk - Yoakum 230kV9/30/2013IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2013-028IFS-2013-002-03DISIS-2013-002-204 SOUTHEASTMayesOKGRDA4/16/201612/23/2017  538495538ERThermalGasTap N Tulsa - GRDA 1 345kV9/30/2013IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2013-029IFS-2013-002-04 DISIS-2013-002-204 SOUTHEASTGrantOKOGE12/15/20154/8/2016  299299299ERWindRenfrow 345kV9/30/2013IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2013-032IFS-2013-002-06DISIS-2013-002-202 NEBRASKAAntelopeNENPPD12/31/201612/20/2018  202.5202.5202.5ERWindAntelope 115kV9/30/2013IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2013-033IFS-2013-002-07DISIS-2013-002-203 CENTRALEllisKSMIDW12/31/20152/27/2016  282828ER/NRThermalGasGoodman Energy Center 115kV9/30/2013IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2014-001IFS-2014-001-08DISIS-2014-001-103 CENTRALMarionKSWERE7/15/201410/1/2021  200.6200.6200.6ERWindTap Wichita - Emporia Energy Center 345kV1/15/2014IA FULLY EXECUTED/ON SCHEDULE   
GEN-2014-001ISIFS-2015-001-21DISIS-2015-002 Prior Queued01 NORTHButteSDWAPA12/15/20159/24/2020  103.24103.24103.24ERWindSulphur 115kV11/24/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-002IFS-2014-001-02DISIS-2014-001-104 SOUTHEASTDeweyOKOGE12/31/20144/8/2015  10.510.510.5ERWindTatonga 345kV2/18/2014IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-004IFS-2014-001-04 DISIS-2014-001-102 NEBRASKAJeffersonNENPPD 10/29/2013  444ERWindSteele City 115kV2/19/2014IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-005IFS-2014-001-05 DISIS-2014-001-104 SOUTHEASTCaddoOKOGE 6/1/2015  5.75.75.7ERWindMinco 345kV2/19/2014IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-013IFS-2014-001-07 DISIS-2014-001-102 NEBRASKAAntelope / BooneNENPPD12/31/201412/18/2015  73.573.573.5ER/NRWindMeadow Grove 230kV3/31/2014IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-020IFS-2014-002-03 DISIS-2014-002-604 SOUTHEASTGrady OKAEP12/31/201410/10/2017  100100100ER/NRWindTuttle 138kV7/14/2014IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-021IFS-2014-002-04DISIS-2014-002-603 CENTRALAtchison MOGMO12/1/201611/7/2017  300300300ER/NRWindNebraska City-Mullen Creek (Holt County MO) 345kV9/2/2014IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-025IFS-2014-002-05 DISIS-2014-002-603 CENTRALRush KSMIDW10/15/201512/1/2015  2.422.422.42ERWindTap Nekoma - Bazine (Walnut Creek) 69kV9/25/2014IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-028IFS-2014-002-07 DISIS-2014-002-603 CENTRALCherokee CountyKSEDE1/1/20164/1/2016  50050ERThermalCCRiverton 161kV9/25/2014IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-031IFS-2014-002-08 DISIS-2014-002-602 NEBRASKAAntelope CountyNENPPD10/1/20153/30/2016  35.835.835.8ER/NRWindMeadow Grove 230kV9/26/2014IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-032IFS-2014-002-09DISIS-2014-002-602 NEBRASKAAntelope NENPPD10/1/20155/1/2014  10.210.210.2ER/NRWindMeadow Grove 230kV9/29/2014IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-033IFS-2014-002-10DISIS-2014-002-605 SOUTHWESTChavesNMSPS12/31/20168/25/2016  707070ERSolarChaves County 115kV9/29/2014IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-034IFS-2014-002-11DISIS-2014-002-605 SOUTHWESTChavesNMSPS12/31/201610/21/2016  707070ERSolarChaves County 115kV9/29/2014IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-035IFS-2014-002-12 DISIS-2014-002-605 SOUTHWESTChavesNMSPS12/31/201612/15/2022  303030ERSolarChaves County 115kV9/29/2014IA FULLY EXECUTED/ON SCHEDULE   
GEN-2014-040IFS-2014-002-14DISIS-2014-002-605 SOUTHWESTCastroTXSPS9/1/201612/30/2016  320320320ERWindCastro 115kV9/26/2014IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-056IFS-2014-002-21DISIS-2014-002-604 SOUTHEASTCanadianOKOGE12/31/201612/22/2018  250250250ERWindMinco 345kV9/29/2014IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-057IFS-2014-002-22DISIS-2014-002-604 SOUTHEASTGradyOKAEP12/31/201612/1/2016  249.9249.9249.9ERWindLawton East Side-Sunnyside (Terry Road) 345kV9/29/2014IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-064IFS-2014-002-24 DISIS-2014-002-604 SOUTHEASTGarfieldOKOGE12/1/201612/21/2018  248.4248.4248.4ERWindOtter 138kV9/30/2014IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-001IFS-2015-001-15DISIS-2015-001-404 SOUTHEASTKayOKOGE12/31/201612/17/2016  200200200ERWindRose Hill (Open Sky)-Sooner (Ranch Road) 345kV3/4/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-005IFS-2015-001-04DISIS-2015-001-403 CENTRALDeKalb CountyMOGMO12/31/201712/16/2016  200.1200.1200.1ERWindMullen Creek-Sibley (Ketchum) 345kV3/25/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-007IFS-2015-001-01DISIS-2015-001-402 NEBRASKAWayne CountyNENPPD11/8/201912/31/2019  160160160ERWindHoskins 345kV3/25/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-013IFS-2015-001-18DISIS-2015-001-404 SOUTHEASTKiowa CountyOKWFEC12/1/20165/1/2024  120120120ER/NRSolarSnyder 138kV3/31/2015IA FULLY EXECUTED/ON SCHEDULE   
GEN-2015-014IFS-2015-001-20DISIS-2015-001-405 SOUTHWESTCochran CountyTXSPS12/1/201612/15/2018  150150150ERWindTap Cochran - Lehman 115kV substation3/31/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-015IFS-2015-001-14DISIS-2015-001-404 SOUTHEASTGrant CountyOKOGE7/31/201612/8/2017  154.56154.56154.56ER/NRWindTap Medford Tap – Coyote 138kV3/27/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-016IFS-2015-001-05DISIS-2015-001-403 CENTRALAllen CountyKSKCPL12/31/20179/11/2019  200200200ER/NRWindTap Marmaton - Centerville 161kV3/20/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-021IFS-2015-001-16DISIS-2015-001-403 CENTRALStantonKSSUNC12/31/20164/7/2020  202020ER/NRSolarJohnson Corner 115kV4/1/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-023IFS-2015-001-08DISIS-2015-001-402 NEBRASKAAntelope & Wheeler CountyNENPPD12/31/20194/1/2024  300.7300.7300.7ER/NRWindGrand Prairie-Grand Island (Holt County NE) 345kV3/31/2015IA FULLY EXECUTED/ON SCHEDULE   
GEN-2015-024IFS-2015-001-02DISIS-2015-001-403 CENTRALPratt CountyKSWERE12/31/201612/9/2016  220220220ERWindThistle-Wichita Dbl Ckt (Buffalo Flats) 345kV3/26/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-025IFS-2015-001-03DISIS-2015-001-403 CENTRALPrattKSWERE12/31/201612/19/2016  220220220ERWindTap Thistle – Wichita 345kV Dbl CKT3/26/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-034IFS-2015-002-08DISIS-2015-002-704 SOUTHEASTKay CountyOKOGE10/31/201712/10/2020  200200200ERWindRose Hill (Open Sky)-Sooner (Ranch Road) 345kV8/28/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-036IFS-2016-001-44DISIS-2016-001-304 SOUTHEASTJohnston CountyOKOGE12/31/201712/13/2020  303.6303.6303.6ERWindJohnston County 345kV9/10/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-041IFS-2015-002-41DISIS-2016-00105 SOUTHWESTHale CountyTXSPS7/1/201510/19/2019  550ERThermalCTTUCO 345kV9/30/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-045IFS-2015-002-10DISIS-2015-002-704 SOUTHEASTGrady CountyOKAEP12/1/201712/12/2019  202020ERBattery/StorageLawton East Side-Sunnyside (Terry Road) 345kV10/5/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-046IFS-2015-002-46DISIS-2015-002-701 NORTHWilliams CountyNDBEPC12/1/20175/27/2021  300300300ERWindTande 345kV10/5/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-047IFS-2015-002-02DISIS-2015-002-704 SOUTHEASTNoble CountyOKOGE12/1/20171/1/2018  300300300ERWindSooner 345kV10/5/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-048IFS-2015-002-11DISIS-2015-002-704 SOUTHEASTMajor County, OKOKOGE12/1/20174/14/2021  200200200ERWindCleo Corner 138kV10/5/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-052IFS-2015-002-03DISIS-2015-002-703 CENTRALSumnerKSWERE12/1/201712/31/2022  300300300ERWindOpen Sky-Rose Hill 345kV10/5/2015IA FULLY EXECUTED/ON SCHEDULE   
GEN-2015-055IFS-2015-002-25DISIS-2015-002-704 SOUTHEASTBeckham CountyOKWFEC10/30/201612/1/2023  404040ERSolarErick 138kV Substation10/6/2015IA FULLY EXECUTED/ON SCHEDULE   
GEN-2015-057IFS-2015-002-33DISIS-2015-002-704 SOUTHEASTGrady CountyOKOGE12/1/201612/22/2018  100100100ERWindMinco 345kV10/6/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-062IFS-2015-002-15DISIS-2015-002-704 SOUTHEASTGarfield CountyOKOGE3/1/201612/31/2021  4.54.54.5ERWindBreckinridge 138kV10/6/2015IA FULLY EXECUTED/ON SCHEDULE   
GEN-2015-063IFS-2015-002-16DISIS-2015-002-704 SOUTHEASTKingfisher CountyOKOGE12/1/20171/1/2018  300300300ERWindWoodring-Matthewson 345kV10/6/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-064IFS-2015-002-18DISIS-2015-002-703 CENTRALThomas CountyKSSUNC11/1/20173/26/2020  197.8197.8197.8ERWindMingo 115kV10/7/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-065IFS-2015-002-19DISIS-2015-002-703 CENTRALThomas CountyKSSUNC11/1/20177/1/2019  202.4202.4202.4ERWindMingo 345kV10/7/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-066IFS-2015-002-38DISIS-2015-002-704 SOUTHEASTPawneeOKOGE12/1/201712/31/2022  248.4248.4248.4ERWindSooner - Cleveland 345kV10/7/2015IA FULLY EXECUTED/ON SCHEDULE   
GEN-2015-069IFS-2015-002-06DISIS-2015-002-703 CENTRALDickenson / Marion CountiesKSWERE12/1/201712/17/2018  300300300ERWindUnion Ridge 230kV9/21/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-073IFS-2015-002-20DISIS-2015-002-703 CENTRALLyon CountyKSWERE12/31/201812/19/2019  200.1200.1200.1ER/NRWindEmporia 345kV9/28/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-082IFS-2016-001-28DISIS-2016-001-305 SOUTHWESTBeaverOKOGE12/1/201711/25/2020  200200200ERWindBeaver County - Woodward EHV Dbl Ckt (Badger) 345kV9/28/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-088IFS-2015-002-32DISIS-2015-002-702 NEBRASKASalineNENPPD1/1/201912/29/2020  300300300ER/NRWindTobias 345kV Substation9/30/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-089IFS-2016-001-05DISIS-2016-001-301 NORTHBon HommeSDWAPA6/30/20174/22/2020  200200200ERWindUtica 230 kV Substation10/13/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-090IFS-2015-002-21DISIS-2015-002-703 CENTRALPrattKSWERE12/1/201712/14/2018  220220220ERWindThistle-Wichita Dbl Ckt (Buffalo Flats) 345kV9/29/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2015-092IFS-2015-002-36DISIS-2015-002-704 SOUTHEASTGradyOKAEP12/1/201712/31/2020  250250250ERWindLawton East Side-Sunnyside (Terry Road) 345kV9/30/2015IA FULLY EXECUTED/ON SCHEDULE   
GEN-2015-093IFS-2015-002-37DISIS-2015-002-704 SOUTHEASTCaddoOKOGE12/1/201712/31/2022  250250250ERWindGracemont 345kV9/29/2015IA FULLY EXECUTED/ON SCHEDULE   
GEN-2015-095IFS-2016-001-20DISIS-2016-001-304 SOUTHEASTWoods CountyOKOGE12/1/20176/1/2020  176176176ERWindTap Mooreland - Knob Hill 138kV9/21/2015IA FULLY EXECUTED/ON SCHEDULE   
GEN-2015-096IFS-2015-002-43DISIS-2015-002-701 NORTHHettinger CountyNDBEPC12/31/201712/29/2016  150150150ERWindBrady 230kV substation10/19/2015IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-003IFS-2016-001-45DISIS-2016-001-304 SOUTHEASTEllisOKOGE12/31/20178/31/2022  250.4250.4250.4ERWindBadger-Woodward EHV Dbl Ckt 345kV3/15/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-004IFS-2016-001-25DISIS-2016-001-301 NORTHOliverNDBEPC10/5/202212/31/2025  202202202ER/NRWindBasin Electric 230 kV3/10/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-007IFS-2016-001-37DISIS-2016-001-301 NORTHBarnesNDWAPA12/31/201812/31/2024  100.05100.05100.05ERWindValley City 115 kV3/28/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-009IFS-2016-001-02DISIS-2016-001-303 CENTRALPonca CityOKOGE9/30/201811/18/2020  292929ERThermalSteam TurbineOsage 69 kV Sub3/24/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-013IFS-2016-001-03DISIS-2016-001-303 CENTRALJoplinMOEDE4/25/20034/30/2020  101010ERThermalCTLaRussell Energy Center 161kV3/29/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-014IFS-2016-001-04DISIS-2016-001-303 CENTRALJoplinMOEDE4/25/20034/30/2020  101010ERThermalCTLaRussell Energy Center 161kV3/29/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-016IFS-2016-001-07DISIS-2016-001-303 CENTRALEdwardsKSMIDW12/1/201712/1/2023  78.278.278.2ERWindNorth Kinsley 115 kV3/29/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-017IFS-2016-001-08DISIS-2016-001-301 NORTHHyde CountySDBEPC12/1/201711/23/2020  250.24250.24250.24ERWindChappelle Creek 345kV3/29/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-020IFS-2016-001-27DISIS-2016-001-304 SOUTHEASTWoodward CountyOKWFEC12/31/201812/18/2020  148.4148.4148.4ERWINDMoreland 138kV Substation4/1/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-021IFS-2016-001-31DISIS-2016-001-302 NEBRASKADixon CountyNENPPD12/1/20183/9/2022  298.47298.47298.47ERWINDHoskins 345kV3/31/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-022IFS-2016-001-29DISIS-2016-001-304 SOUTHEASTNewkirk, Kay CountyOKOGE12/31/201712/10/2020  151.8151.8151.8ERWindRose Hill (Open Sky)-Sooner (Ranch Road) 345kV3/31/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-028IFS-2016-001-38DISIS-2016-001-304 SOUTHEASTLe Flore CoOKAEP12/31/201812/27/2019  100100100ERWindClayton 138 kV Sub3/29/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-030IFS-2016-001-26DISIS-2016-001-304 SOUTHEASTJohnston CoOKOGE8/28/20216/1/2023  100100100ER/NRSolarBrown 138kV3/30/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-031IFS-2016-001-10DISIS-2016-001-304 SOUTHEASTKay CountyOKOGE11/30/201612/17/2016  1.51.51.5ERWindRose Hill (Open Sky)-Sooner (Ranch Road) 345kV3/25/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-032IFS-2016-001-11DISIS-2016-001-304 SOUTHEASTKingfisher CoOKOGE2/1/202312/31/2023  200200200ER/NRWindCrescent Substation 138 kV3/30/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-036IFS-2016-002-42DISIS-2016-002-101 NORTHChippewa CountyMNWAPA11/17/201812/30/2018  44.644.644.6ERWindGranite Falls 115kV substation3/28/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-037IFS-2017-001-32DISIS-2017-00104 SOUTHEASTWashita CountyOKAEP6/1/202112/31/2022  300300300ERWindChisholm-Gracemont 345kV3/31/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-043IFS-2016-001-36DISIS-2016-001-302 NEBRASKAWayne CountyNENPPD9/1/20186/27/2020  230230230ERWindHoskins 345kV3/31/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-045IFS-2016-001-34DISIS-2016-001-304 SOUTHEASTCimarron, Texas CountyOKOGE8/31/20183/18/2022  499.1499.1499.1ERWindMathewson 345kV3/31/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-046IFS-2016-001-12DISIS-2016-001-303 CENTRALFord CountyKSSUNC12/1/201812/23/2021  299299299ERWindClark County-Ironwood 345kV3/31/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-047IFS-2016-001-22DISIS-2016-001-304 SOUTHEASTCanadianOKOGE12/31/20173/24/2018  24824ERThermalCTMustang 69kV3/31/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-050IFS-2016-001-42DISIS-2016-001-302 NEBRASKAWebster CoNENPPD12/1/201712/9/2021  250.7250.7250.7ERWindAxtell – Post Rock 345 kV3/30/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-051IFS-2016-001-13DISIS-2016-001-304 SOUTHEASTCusterOKAEP 12/18/2020  9.89.89.8ERWindClinton Junction-Weatherford Southeast 138kV3/30/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-057IFS-2016-001-35DISIS-2016-001-304 SOUTHEASTCimarron, Texas CountyOKOGE8/31/20183/18/2022  499.1499.1499.1ERWindMathewson 345kV3/31/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-061IFS-2016-001-15DISIS-2016-001-304 SOUTHEASTGarfield/NobleOKOGE12/1/201711/21/2020  250.7250.7250.7ERWindSooner-Woodring 345 kV line3/29/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-063IFS-2016-001-17DISIS-2016-001-304 SOUTHEASTJohnstonOKOGE12/31/20186/1/2023  200200200ER/NRWindHugo-Sunnyside 345 kV3/30/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-067IFS-2016-001-33DISIS-2016-001-303 CENTRALThomasKSSUNC11/1/20177/24/2019  73.673.673.6ERWindMingo 345kV3/31/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-068IFS-2016-001-40DISIS-2016-001-304 SOUTHEASTGarfieldOKOGE9/18/202012/15/2020  250250250ERWindWoodring 345kV3/30/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-070IFS-2016-001-18DISIS-2016-001-305 SOUTHWESTCarsonTXSPS11/1/201612/11/2020  5.35.35.3ERWindMartin 115 kV Substation3/30/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-071IFS-2016-001-19DISIS-2016-001-304 SOUTHEASTKayOKOGE9/30/20183/1/2024  200.1200.1200.1ERWindMiddleton Tap 138kV Substation3/30/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-073IFS-2016-001-48DISIS-2016-001-303 CENTRALKingman CountyKSWERE12/31/201710/29/2025  220220220ERWINDThistle-Wichita Dbl Ckt (Buffalo Flats) 345kV3/30/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-074IFS-2016-002-57DISIS-2016-002-102 NEBRASKACusterNENPPD10/30/20207/1/2024  200200200ERWindSweetwater 345kV4/14/2016IA FULLY EXECUTED/ON SUSPENSION   
GEN-2016-075IFS-2016-001-21DISIS-2016-001-302 NEBRASKAHoltNEWAPA12/31/201712/31/2024  505050ERWindFort Thompson-Grand Island (Grand Prairie) 345kV3/31/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-087IFS-2016-002-59DISIS-2016-002-101 NORTHCampbellSDWAPA11/15/201912/31/2023  98.998.998.9ERWindBismark-Glenham 230 kV line7/25/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-091IFS-2016-002-22DISIS-2016-002-104 SOUTHEASTCaddoOKAEP5/6/20201/8/2022  303.6303.6303.6ERWindGracemont-Lawton East Side 345kV10/3/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-094IFS-2016-002-25DISIS-2016-002-101 NORTHHydeSDWAPA10/1/20208/1/2024  200200200ERWindTap Ft Thompson - Oahe 230kV Line (Single Circuit)10/31/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-095IFS-2016-002-32DISIS-2016-002-104 SOUTHEASTCaddoOKAEP9/1/202012/31/2023  200200200ER/NRWindGracemont-Lawton East Side 345kV12/1/2020IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-097IFS-2016-002-31DISIS-2016-002-104 SOUTHEASTCaddoOKAEP9/1/202012/31/2023  100100100ER/NRWindTap Southwestern-Fletcher Tap 138kV10/19/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-102IFS-2016-002-01DISIS-2016-002-104 SOUTHEASTPontotocOKOGE11/1/202312/1/2024  150.9150.9150.9ER/NRWindBlue River 138kV11/7/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-111IFS-2016-002-18DISIS-2016-002-103 CENTRALMcPhersonKSWERE9/15/20191/15/2024  302302302ERWindReno - Summit 345kV11/30/2016IA FULLY EXECUTED/ON SUSPENSIONSuspension Start Date of 3/24/2021   
GEN-2016-115IFS-2016-002-24DISIS-2016-002-103 CENTRALAtchisonMOGMO11/16/20203/2/2021  300300300ERWindNebraska City-Mullen Creek (Holt County MO) 345kV11/30/2016IA FULLY EXECUTED/COMMERCIAL OPERATIONAs of the COD notice 120 MW have been placed in commercial operation.3/2/2021   
GEN-2016-118IFS-2016-002-05DISIS-2016-002-104 SOUTHEASTKingfisherOKWFEC5/15/20219/10/2021  288288288ERWindDover Switchyard 138 kV Line11/30/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-119IFS-2016-002-10DISIS-2016-002-104 SOUTHEASTKingfisherOKOGE5/15/202012/31/2025  600600600ERWindSpring Creek-Sooner 345kV11/30/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-121IFS-2016-002-26DISIS-2016-002-105 SOUTHWESTLeaNMSPS10/1/202212/1/2022  110110110ERSolarRoadrunner 115kV11/22/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-123IFS-2016-002-27DISIS-2016-002-105 SOUTHWESTRooseveltNMSPS12/31/201912/31/2020  298298298ERWindEddy County-Tolk (Crossroads) 345kV11/30/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-124IFS-2016-002-28DISIS-2016-002-105 SOUTHWESTRooseveltNMSPS12/31/201912/31/2020  150150150ERWindEddy County-Tolk (Crossroads) 345kV11/30/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-125IFS-2016-002-29DISIS-2016-002-105 SOUTHWESTRooseveltNMSPS12/31/201912/31/2020  747474ERWindEddy County-Tolk (Crossroads) 345kV11/30/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-126IFS-2016-002-06DISIS-2016-002-104 SOUTHEASTMurrayOKOGE12/31/201911/24/2021  172.5172.5172.5ER/NRWindArbuckle 138kV substation11/30/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-128IFS-2016-002-36DISIS-2016-002-104 SOUTHEASTAlfalfaOKOGE9/15/201912/31/2023  176176176ERWindWoodring 345kV11/30/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-130IFS-2016-002-21DISIS-2016-002-101 NORTHMercerNDBEPC9/15/201912/31/2022  202202202ERWindLeland Olds 345 kV11/30/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-131IFS-2016-002-37DISIS-2016-002-104 SOUTHEASTGradyOKOGE12/31/201710/25/2021  2.52.52.5ERWindMinco 345kV11/30/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-132IFS-2016-002-61DISIS-2016-002-104 SOUTHEASTRoger MillsOKAEP12/31/20176/5/2020  6.16.16.1ERWindSweetwater 230kV11/30/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-133IFS-2016-002-43DISIS-2016-002-104 SOUTHEASTTexasOKAEP9/1/202012/31/2025  187.5187.1187.5ERWindRiverside 345kV Substation11/29/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-134IFS-2016-002-44DISIS-2016-002-104 SOUTHEAST TexasOKAEP9/1/202012/31/2025  187.5187.5187.5ERWindRiverside 345kV Substation11/29/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-137IFS-2016-002-47DISIS-2016-002-104 SOUTHEASTTexasOKAEP9/1/202012/31/2025  187.5187.5187.5ERWindRiverside 345kV Substation11/29/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-138IFS-2016-002-48DISIS-2016-002-104 SOUTHEASTTexasOKAEP9/1/202012/31/2025  187.5187.5187.5ERWindRiverside 345kV Substation11/29/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-139IFS-2016-002-49DISIS-2016-002-104 SOUTHEASTTexasOKAEP9/1/202012/31/2025  100100100ERWindRiverside 345kV Substation11/29/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-141IFS-2016-002-51DISIS-2016-002-104 SOUTHEASTTexasOKAEP9/1/202012/31/2025  350350350ERWindRiverside 345kV Substation11/29/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-142IFS-2016-002-52DISIS-2016-002-104 SOUTHEASTTexasOKAEP9/1/202012/31/2025  350350350ERWindRiverside 345kV Substation11/29/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-145IFS-2016-002-55DISIS-2016-002-104 SOUTHEASTTexasOKAEP9/1/202012/31/2025  175175175ERWindRiverside 345kV Substation11/29/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-146IFS-2016-002-56DISIS-2016-002-104 SOUTHEASTTexasOKAEP9/1/202012/31/2025  175175175ERWindRiverside 345kV Substation11/29/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-147IFS-2016-002-33DISIS-2016-002-102 NEBRASKACheyenneNETri-State9/15/201912/31/2023  404040ERSolarSidney 115 kV Sub11/30/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-149IFS-2016-002-14DISIS-2016-002-103 CENTRALWashingtonKSWERE9/15/201912/31/2022  302302302ERWindStranger Creek 345kV11/30/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-150IFS-2016-002-15DISIS-2016-002-103 CENTRALNemahaKSWERE9/22/202212/30/2022  302302302ERWindStranger Creek 345kV11/30/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-151IFS-2016-002-62DISIS-2016-002-101 NORTHBurkeNDBEPC9/15/201912/22/2020  202202202ERWindTande 345kV11/30/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-153IFS-2016-002-11DISIS-2016-002-103 CENTRALHarper CountyKSWERE10/30/201911/1/2023  134134134ERWindViola 345kV11/30/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-157IFS-2016-002-20DISIS-2016-002-103 CENTRALAllen CountyKSKCPL9/15/201912/31/2025  252252252ERWindWest Gardner 345kV11/30/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-158IFS-2016-002-17DISIS-2016-002-103 CENTRALAllen CountyKSKCPL9/15/201912/31/2025  252252252ERWindWest Gardner 345kV11/30/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-160IFS-2016-002-04DISIS-2016-002-103 CENTRALEllisKSMIDW10/2/202312/31/2023  202020ER/NRBattery/StoragePost Rock 230kV11/21/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-167IFS-2016-002-02DISIS-2016-002-104 SOUTHEASTCaddo ParishLAAEP9/1/202312/1/2024  73.573.573.5ER/NRSolarLieberman - North Benton 138 kV Line11/29/2016IA FULLY EXECUTED/ON SCHEDULE   
GEN-2016-174IFS-2016-002-19DISIS-2016-002-103 CENTRALNemahaKSWERE9/15/201911/18/2020  302302302ERWindStranger Creek 345kV11/30/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-176IFS-2016-002-67DISIS-2016-002-103 CENTRALNemaha CountyKSWERE12/31/201912/6/2021  302302302ERWindStranger Creek 345kV12/15/2016IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2016-177IFS-2016-002-60DISIS-2016-002-105 SOUTHWESTGainesTXSPS 7/28/2021  1714.417ERThermalGas TurbineXTO-Cornell 115 kV station1/23/2017IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2017-004IFS-2017-001-05DISIS-2017-00103 CENTRALCloud CountyKSITCGP12/31/202111/30/2024  201.6201.6201.6ERWindElm Creek - Summit 345 kV4/14/2017IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-005IFS-2017-001-11DISIS-2017-00103 CENTRALBourbon and Crawford CountiesOKWERE12/31/202012/13/2021  190190190ERWindMarmaton - Litchfield 161 kV4/14/2017IA FULLY EXECUTED/ON SCHEDULEInterim IGIA effective 3/3/2021 - AB   
GEN-2017-009IFS-2017-001-39DISIS-2017-00103 CENTRALNeoshoe CountyKSWERE10/31/20205/1/2021  302302302ERWindNeosho - Caney River 345 kV4/14/2017IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2017-010IFS-2017-001-12DISIS-2017-00101 NORTHBowman CountyNDBEPC10/31/2022   200.1200.1200.1ERWindRhame 230 kV Sub4/14/2017IA PENDING   
GEN-2017-011IFS-2017-001-06DISIS-2017-00104 SOUTHEASTEllis CountyOKOGE12/31/201912/31/2023  151.8151.8151.8ERSolarBadger-Woodward EHV Dbl Ckt 345kV5/17/2017IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-014IFS-2017-001-29DISIS-2017-00101 NORTHHaakon CountySDWAPA12/1/202012/31/2025  300300300ERWindPhilip Tap 230 kV5/22/2017IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-018IFS-2017-001-27DISIS-2017-00103 CENTRALBarber CountyKSITCGP12/31/202012/15/2024  189189189ER/NRSolarThistle 345 kV sub5/30/2017IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-022IFS-2017-001-21DISIS-2017-00103 CENTRALWilson CountyKSWERE12/1/20196/1/2025  656565ER/NRSolarAltoona- NE Parson 138kV5/31/2017IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-023IFS-2017-001-22DISIS-2017-00104 SOUTHEASTChoctaw CountyOKWFEC12/1/202412/1/2024  858585ER/NRSolarHugo Power Plant 138 kV Sub5/31/2017IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-027IFS-2017-001-33DISIS-2017-00104 SOUTHEASTCarter CountyOKOGE11/1/202112/21/2021  140140140ERWindPooleville-Ratliff (Carter County) 138kV5/31/2017IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2017-033IFS-2017-001-28DISIS-2017-00105 SOUTHWESTWilbarger CountyTXAEP12/31/202012/31/2024  200200200ER/NRWindOklaunion 345 kV sub5/31/2017IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-036IFS-2017-001-23DISIS-2017-00104 SOUTHEASTKiowa CountyOKAEP12/1/202212/1/2024  100100100ERSolarSnyder - Cache 138 kV5/31/2017IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-040IFS-2017-001-03DISIS-2017-00104 SOUTHEASTOchiltree CountyTXOGE6/1/202012/31/2024  200.1200.1200.1ERSolarCanadian River-Muskogee and Muskogee-Seminole 345kV5/31/2017IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-047IFS-2017-001-19DISIS-2017-00105 SOUTHWESTBeaver CountyOKSPS12/31/201912/31/2023  102102102ER/NRWindCole 115kV5/18/2017IA PENDING   
GEN-2017-048IFS-2017-001-34DISIS-2017-00101 NORTHWilliams CountyNDBEPC8/30/20249/30/2024  300300300ERWindNeset 230 kV Substation5/31/2017IA PENDING   
GEN-2017-057IFS-2017-001-13DISIS-2017-00104 SOUTHEASTCaddo ParishLAAEP12/1/202112/1/2024  72.572.572.5ERSolarHosston 69kV5/30/2017IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-060IFS-2017-001-01DISIS-2017-00103 CENTRALBarton CountyMOEDE9/1/20204/21/2021  149.4149.4149.4ERWindLaRussell Energy Center 161kV5/30/2017IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2017-061IFS-2017-001-25DISIS-2017-00104 SOUTHEASTMayes CountyOKGRDA12/1/20218/1/2024  101.5101.5101.5ER/NRSolarGRDA1 to CLARMR 5 161kV line5/28/2017IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-068IFS-2017-001-26DISIS-2017-00103 CENTRALSumner CountyKSWERE12/31/202012/31/2023  103.5103.5103.5ER/NRSolarGordon Evans 138kV Substation5/30/2017IA PENDING   
GEN-2017-071IFS-2017-001-36DISIS-2017-00104 SOUTHEASTPayne CountyOKOGE12/1/20218/1/2024  124.7124.7124.7ERSolarGreenwood 138kV sub5/28/2017IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-072IFS-2017-001-37DISIS-2017-00104 SOUTHEASTPayne CountyOKOGE12/1/20218/1/2024  52.252.252.2ERSolarGreenwood 138kV sub5/28/2017IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-073IFS-2017-001-14DISIS-2017-00104 SOUTHEASTMayes CountyOKGRDA12/1/20218/1/2024  72.572.572.5ERSolarDry Gulch 161kV sub5/28/2017IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-074IFS-2017-001-15DISIS-2017-00104 SOUTHEASTMayes CountyOKAEP12/1/202112/9/2024  72.572.572.5ERSolarPryor Junction 138kV sub5/28/2017IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-075IFS-2017-001-16DISIS-2017-00104 SOUTHEASTJohnston CountyOKOGE12/1/202112/1/2024  200200200ERSolarHugo-Sunnyside 345 kV5/28/2017IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-076IFS-2017-001-17DISIS-2017-00104 SOUTHEASTBenton CountyARAEP12/1/202112/1/2024  52.252.252.2ERSolarChamber Springs 161kV sub5/28/2017IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-077IFS-2017-001-18DISIS-2017-00104 SOUTHEASTMayes CountyOKAEP12/1/202112/6/2024  124.7124.7124.7ERSolarExplorer Claremore Tap EXCLART45/28/2017IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-082IFS-2017-001-02DISIS-2017-00103 CENTRALBarton/Jasper CountiesMOEDE7/1/202012/31/2020  149.4149.4149.4ERWindAsbury Plant 161 kV5/31/2017IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2017-086IFS-2017-001-10DISIS-2017-00103 CENTRALHarper CountyKSWERE12/1/202111/1/2023  150150150ERWindViola 345kV5/25/2017IA PENDING   
GEN-2017-092IFS-2017-001-04DISIS-2017-00104 SOUTHEASTMuskogee CountyOKOGE6/1/202312/31/2024  200200200ERSolarCanadian River-Muskogee and Muskogee-Seminole 345kV5/30/2017IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-094IFS-2017-001-31DISIS-2017-00101 NORTHWessington/Hand CountiesSDWAPA10/6/202010/31/2023  200200200ERWindFort Thompson-Huron 230 kV5/24/2017IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-097IFS-2017-001-24DISIS-2017-00101 NORTHPennington CountySDWAPA1/9/20222/1/2024  128128128ERSolarUnderwood 115 kV Sub5/31/2017IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-100IFS-2017-001-20DISIS-2017-00105 SOUTHWESTTexas CountyOKSPS12/31/201912/31/2021  102.6102.6102.6ER/NRSolarTexas County 115kV5/31/2017IA PENDING   
GEN-2017-102DISIS-2017-00205 SOUTHWESTRoosevelt CountyNMSPS4/30/20204/30/2020  67.567.567.5ERSolarCrossroads 345kV4/30/2020DISIS STAGE   
GEN-2017-105DISIS-2017-00202 NEBRASKABurt CountyNEOPPD12/15/2018   757575ER/NRWindTekamah - Raun 161 kV Line7/12/2017DISIS STAGE   
GEN-2017-108DISIS-2017-00203 CENTRALHenry CountyMOKCPL12/1/2022   400400400ER/NRSolarStillwell - Clinton 161kV Line8/26/2017DISIS STAGE   
GEN-2017-111DISIS-2017-00203 CENTRALBatesMOKCPL9/1/2023   152152152ERSolarClinton – Stilwell 161 kV Line Tap11/27/2017DISIS STAGE   
GEN-2017-112DISIS-2017-00203 CENTRALBatesMOKCPL5/1/2027   200200200ERWindClinton – Stilwell 161 kV Line Tap11/27/2017DISIS STAGE   
GEN-2017-113DISIS-2017-00201 NORTHBennettSDWAPA12/31/2021   119119119ERWindMartin 115kV10/23/2017DISIS STAGE   
GEN-2017-114DISIS-2017-00201 NORTHDeweySDBEPC12/31/2021   450450450ERWindChappelle Creek - Leland Olds 345kV10/23/2017DISIS STAGE   
GEN-2017-115DISIS-2017-00203 CENTRALAtchinson/NodawayMOKCPL5/1/2027   244244244ERWindHolt County 345 kV11/10/2017DISIS STAGE   
GEN-2017-116DISIS-2017-00205 SOUTHWESTCurry/RooseveltNMSPS12/1/2021   192.5192.5192.5ERSolarOasis - Pleasant Hill 230kV11/17/2017DISIS STAGE   
GEN-2017-117DISIS-2017-00204 SOUTHEASTCanadianOKWFEC12/1/2020   19.819.819.8ER/NRBattery/StorageEl Reno SW 138kV11/17/2017DISIS STAGE   
GEN-2017-119DISIS-2017-00203 CENTRALCloud/MitchellKSSUNC5/1/2024   180180180ERWindElm Creek 345kV substation11/17/2017DISIS STAGE   
GEN-2017-120DISIS-2017-00203 CENTRALDickinson/MarionKSWERE5/1/2027   260260260ERWindAbilene Energy Center-Northview 115kV11/17/2017DISIS STAGE   
GEN-2017-121DISIS-2017-00203 CENTRALSumnerKSWERE12/1/2021   200200200ER/NRWindSumner 138kV11/17/2017DISIS STAGE   
GEN-2017-123DISIS-2017-00203 CENTRALLeavenworthKSWERE12/1/2020   180180180ER/NRWindStranger Creek 345kV11/20/2017DISIS STAGE   
GEN-2017-125DISIS-2017-00203 CENTRALOsageKSWERE12/1/2020   252252252ER/NRWindSwissvale 345kV11/20/2017DISIS STAGE   
GEN-2017-128DISIS-2017-00203 CENTRALJacksonKSWERE12/1/2020   202202202ER/NRWindSwissvale 345kV11/20/2017DISIS STAGE   
GEN-2017-131DISIS-2017-00203 CENTRALWilsonKSWERE12/1/2020   29.629.629.6ER/NRBattery/StorageAltoona- NE Parson 138kV11/22/2017DISIS STAGE   
GEN-2017-132DISIS-2017-00204 SOUTHEASTOklahomaOKOGE12/1/2020   400400400ER/NRWindArcadia 345kV11/22/2017DISIS STAGE   
GEN-2017-133DISIS-2017-00204 SOUTHEASTOklahomaOKOGE12/1/2020   200200200ER/NRWindArcadia 345kV11/22/2017DISIS STAGE   
GEN-2017-134DISIS-2017-00204 SOUTHEASTOklahomaOKOGE12/1/2020   250250250ER/NRWindArcadia 345kV11/22/2017DISIS STAGE   
GEN-2017-137DISIS-2017-00204 SOUTHEASTOklahomaOKOGE12/1/2020   295295295ER/NRWindArcadia 345kV11/22/2017DISIS STAGE   
GEN-2017-140DISIS-2017-00204 SOUTHEASTWagonerOKAEP12/1/2020   160160160ER/NRSolarClarksville 345kV Switching Station11/22/2017DISIS STAGE   
GEN-2017-141DISIS-2017-00204 SOUTHEASTWagonerOKAEP12/1/2020   241.7241.7241.7ER/NRSolarClarksville 345kV Switching Station11/22/2017DISIS STAGE   
GEN-2017-142DISIS-2017-00203 CENTRALJacksonKSWERE12/1/2020   170170170ER/NRWindSwissvale 345kV Station11/22/2017DISIS STAGE   
GEN-2017-144DISIS-2017-00202 NEBRASKAHolt, Antelope, WheelerNEWAPA12/31/2021   200200200ERWindHolt County 345kV11/27/2017DISIS STAGE   
GEN-2017-146DISIS-2017-00205 SOUTHWESTCastroTXSPS10/31/2020   151.8151.8151.8ERWindDeaf Smith-Plant X 230kV11/27/2017DISIS STAGE   
GEN-2017-147DISIS-2017-00203 CENTRALJohnsonKSKCPL12/1/2020   252252252ER/NRWindStilwell 345kV11/27/2017DISIS STAGE   
GEN-2017-148DISIS-2017-00203 CENTRALNewtonMOEDE12/1/2020   202202202ER/NRWindJoplin 161kV sub11/27/2017DISIS STAGE   
GEN-2017-149DISIS-2017-00204 SOUTHEASTJohnstonOKOGE12/1/2020   258258258ER/NRWindJohnson County 345kV Substation11/27/2017DISIS STAGE   
GEN-2017-150DISIS-2017-00204 SOUTHEASTGradyOKOGE12/1/2020   250250250ER/NRSolarMinco 345kV11/28/2017DISIS STAGE   
GEN-2017-151DISIS-2017-00205 SOUTHWESTCrosbyTXSPS10/31/2020   300300300ERWindTUCO-Oklaunion 345kV11/28/2017DISIS STAGE   
GEN-2017-152DISIS-2017-00204 SOUTHEASTMcClainOKOGE12/1/2020   252252252ER/NRWindMcClain 138kV11/28/2017DISIS STAGE   
GEN-2017-153DISIS-2017-00204 SOUTHEASTMcClainOKOGE12/1/2020   253253253ER/NRWindMcClain 138kV11/28/2017DISIS STAGE   
GEN-2017-154DISIS-2017-00204 SOUTHEASTJohnstonOKOGE12/1/2020   255255255ER/NRWindJohnson County 345kV Substation11/28/2017DISIS STAGE   
GEN-2017-155DISIS-2017-00204 SOUTHEASTMuskogeeOKOGE12/1/2020   300300300ER/NRWindMuskogee 345kV Substation11/28/2017DISIS STAGE   
GEN-2017-156DISIS-2017-00204 SOUTHEASTPittsburgOKAEP12/1/2020   234234234ER/NRWindPittsburg 345kV Substation11/28/2017DISIS STAGE   
GEN-2017-157DISIS-2017-00204 SOUTHEASTPittsburgOKAEP12/1/2020   202202202ER/NRWindPittsburg 345kV Substation11/28/2017DISIS STAGE   
GEN-2017-158DISIS-2017-00205 SOUTHWESTParmer/CastroTXSPS12/31/2020   265265265ERWindTolk 230kV Substation11/29/2017DISIS STAGE   
GEN-2017-164DISIS-2017-00204 SOUTHEASTGarfieldOKOGE12/1/2020   250250250ER/NRSolarWoodring 345kV Substation11/29/2017DISIS STAGE   
GEN-2017-166DISIS-2017-00204 SOUTHEASTCarterOKOGE12/1/2020   250250250ER/NRSolarSunnyside 345kV11/29/2017DISIS STAGE   
GEN-2017-167DISIS-2017-00204 SOUTHEASTCarterOKOGE12/31/2020   525252ER/NRBattery/StorageSunnyside 345kV11/29/2017DISIS STAGE   
GEN-2017-168DISIS-2017-00204 SOUTHEASTMcClainOKOGE12/1/2020   250250250ER/NRSolarMcClain 138kV11/29/2017DISIS STAGE   
GEN-2017-169DISIS-2017-00204 SOUTHEASTMcClainOKOGE12/31/2020   525252ER/NRBattery/StorageMcClain 138kV11/29/2017DISIS STAGE   
GEN-2017-171DISIS-2017-00204 SOUTHEASTStephenOKAEP12/1/2020   150150150ER/NRSolarLawton Eastside - Terry Road 345kV11/29/2017DISIS STAGE   
GEN-2017-172DISIS-2017-00204 SOUTHEASTStephenOKAEP12/1/2020   505050ER/NRSolarLawton Eastside - Terry Road 345kV11/29/2017DISIS STAGE   
GEN-2017-173DISIS-2017-00204 SOUTHEASTStephenOKAEP12/1/2020   505050ER/NRSolarLawton Eastside - Terry Road 345kV11/29/2017DISIS STAGE   
GEN-2017-175DISIS-2017-00201 NORTHTurnerSDWAPA9/30/2023   300300300ERWindVfodnes-Utica Jct. 230kV11/29/2017DISIS STAGE   
GEN-2017-176DISIS-2017-00205 SOUTHWESTHartTXSPS9/1/2023   300300300ER/NRHybridWind/SolarNewhart 230kV Substation11/29/2017DISIS STAGE   
GEN-2017-178DISIS-2017-00204 SOUTHEASTGarfieldOKOGE12/31/2020   525252ER/NRBattery/StorageWoodring 345kV Substation11/29/2017DISIS STAGE   
GEN-2017-179DISIS-2017-00203 CENTRALSedgwickKSWERE12/1/2020   222222222ER/NRWindGordon Evans 138kV Substation11/29/2017DISIS STAGE   
GEN-2017-181DISIS-2017-00202 NEBRASKALancasterNENPPD12/1/2020   300300300ER/NRWindTobias 345kV Substation11/29/2017DISIS STAGE   
GEN-2017-182DISIS-2017-00202 NEBRASKALancasterNENPPD12/1/2020   128128128ER/NRWindTobias 345kV Substation11/29/2017DISIS STAGE   
GEN-2017-183DISIS-2017-00203 CENTRALHodgeman/FordKSKCPL12/1/2021   400400400ER/NRWindNashua-St. Joe 345kV11/29/2017DISIS STAGE   
GEN-2017-184DISIS-2017-00203 CENTRALHodgeman/FordKSKCPL12/1/2021   400400400ER/NRSolarNashua-St. Joe 345kV11/29/2017DISIS STAGE   
GEN-2017-185DISIS-2017-00203 CENTRALSumnerKSOGE12/1/2020   200200200ER/NRWindViola - Hunters 345kV11/29/2017DISIS STAGE   
GEN-2017-186DISIS-2017-00203 CENTRALCass/BatesMOKCPL12/31/2020   100100100ERSolarKC South-N. Raymore 161 kV11/30/2017DISIS STAGE   
GEN-2017-187DISIS-2017-00205 SOUTHWESTTerryTXSPS12/31/2020   150150150ERSolarSulphur Springs 115kV Substation11/30/2017DISIS STAGE   
GEN-2017-188DISIS-2017-00203 CENTRALBarryMOEDE12/31/2020   130130130ERSolarAsbury 161 kV11/30/2017DISIS STAGE   
GEN-2017-191DISIS-2017-00203 CENTRALOsageKSWERE12/1/2020   201.6201.6201.6ER/NRSolarSwissvale 345kV11/30/2017DISIS STAGE   
GEN-2017-192DISIS-2017-00203 CENTRALOsageKSWERE12/31/2020   525252ER/NRBattery/StorageWERESwissvale 345kV11/30/2017DISIS STAGE   
GEN-2017-193DISIS-2017-00203 CENTRALShawneeKSWERE12/1/2020   201.6201.6201.6ER/NRSolarTecumseh 230kV Substation11/30/2017DISIS STAGE   
GEN-2017-194DISIS-2017-00203 CENTRALShawneeKSWERE12/31/2020   525252ER/NRBattery/StorageTecumseh 230kV Substation11/30/2017DISIS STAGE   
GEN-2017-195DISIS-2017-00203 CENTRALJohnsonKSKCPL12/1/2020   500.4500.4500.4ER/NRSolarWest Gardner 345kV11/30/2017DISIS STAGE   
GEN-2017-196DISIS-2017-00203 CENTRALJohnsonKSKCPL12/1/2020   128128128ER/NRBattery/StorageWest Gardner 345kV11/30/2017DISIS STAGE   
GEN-2017-198DISIS-2017-00202 NEBRASKAOmahaNEOPPD12/1/20226/1/2024  11.6411.6411.64ERBattery/StorageJones St. No 1201 69kV substation11/30/2017DISIS STAGE   
GEN-2017-199DISIS-2017-00201 NORTHBeadleSDBEPC12/1/2020   202202202ER/NRBattery/StorageGroton 345kV Substation11/30/2017DISIS STAGE   
GEN-2017-200DISIS-2017-00201 NORTHBeadleSDBEPC12/1/2020   302302302ER/NRWindGroton 345kV Substation11/30/2017DISIS STAGE   
GEN-2017-201DISIS-2017-00202 NEBRASKAWayne CountyNENPPD12/1/2022   250250250ER/NRWindHoskins 345kV Substation11/30/2017DISIS STAGE   
GEN-2017-202DISIS-2017-00203 CENTRALNew MadridMOSWPA12/1/2020   200200200ER/NRSolarNew Madrid - Sikeston 161kV11/30/2017DISIS STAGE   
GEN-2017-203DISIS-2017-00204 SOUTHEASTGrant/KayOKOGE7/1/20238/1/2023  210210210ERHybridSolarRenfrow 345kV Substation11/30/2017DISIS STAGE   
GEN-2017-209DISIS-2017-00203 CENTRALMcPhersonKSKCPL12/1/202112/31/2023  300300300ERHybridSolarLaCygne - Neosho 345kV11/30/2017DISIS STAGE   
GEN-2017-210DISIS-2017-00202 NEBRASKACedarNENPPD12/1/2021   310310310ERHybridSolarMcCool 345kV Substation11/30/2017DISIS STAGE   
GEN-2017-213DISIS-2017-00204 SOUTHEASTGrant/KayOKAEP12/1/2021   300300300ERHybridSolarClarksville 345kV Substation11/30/2017DISIS STAGE   
GEN-2017-214DISIS-2017-00201 NORTHWardNDBEPC12/1/2020   100100100ER/NRWindLogan 230kV Substation11/30/2017DISIS STAGE   
GEN-2017-215DISIS-2017-00201 NORTHWardNDBEPC12/1/2020   100100100ER/NRWindLogan 230kV Substation11/30/2017DISIS STAGE   
GEN-2017-216DISIS-2017-00201 NORTHWardNDBEPC12/1/2020   100100100ER/NRWindLogan 230kV Substation11/30/2017DISIS STAGE   
GEN-2017-217DISIS-2017-00205 SOUTHWESTLambTXSPS12/1/202012/31/2023  300300300ER/NRSolarPlant X 230kV Substation11/30/2017DISIS STAGE   
GEN-2017-218DISIS-2017-00205 SOUTHWESTLambTXSPS12/1/2020   600600600ER/NRSolarTolk-Plant X 230kV Line11/30/2017DISIS STAGE   
GEN-2017-220DISIS-2017-00203 CENTRALSedgwickKSWERE12/1/2020   201.6201.6201.6ER/NRSolarBuffalo Flats 345kV Substation11/30/2017DISIS STAGE   
GEN-2017-221DISIS-2017-00203 CENTRALSedgwickKSWERE12/31/2020   152152152ER/NRBattery/StorageBuffalo Flats 345kV Substation11/30/2017DISIS STAGE   
GEN-2017-222DISIS-2017-00201 NORTHDenisonIAWAPA10/6/2020   180180180ERWindDenison 230kV Substation11/30/2017DISIS STAGE   
GEN-2017-224DISIS-2017-00203 CENTRALJohnson CountyKSKCPL12/1/2020   302.4302.4302.4ER/NRSolarCraig 345kV Substation11/30/2017DISIS STAGE   
GEN-2017-225DISIS-2017-00203 CENTRALJohnson CountyKSKCPL12/31/2020   767676ER/NRBattery/StorageCraig 345kV Substation11/30/2017DISIS STAGE   
GEN-2017-226DISIS-2017-00203 CENTRALSedgwick CountyKSWERE12/1/2020   201.6201.6201.6ER/NRSolarGordon Evans 138kV Substation11/30/2017DISIS STAGE   
GEN-2017-227DISIS-2017-00203 CENTRALSedwick CountyKSWERE12/31/2020   201.6201.6201.6ER/NRBattery/StorageGordon Evans 138kV Substation11/30/2017DISIS STAGE   
GEN-2017-228DISIS-2017-00203 CENTRALJohnson CountyKSKCPL12/1/2020   302.4302.4302.4ER/NRSolarStilwell 345kV Substation11/30/2017DISIS STAGE   
GEN-2017-229DISIS-2017-00203 CENTRALJohnson CountyKSKCPL12/31/2020   767676ER/NRBattery/StorageStilwell 345kV Substation11/30/2017DISIS STAGE   
GEN-2017-230DISIS-2017-00204 SOUTHEASTLincoln CountyOKOGE6/1/2020   72.572.572.5ER/NRSolarTryon 138kV Substation11/28/2017DISIS STAGE   
GEN-2017-231DISIS-2017-00204 SOUTHEASTFranklin CountyAROGE6/1/2020   72.572.572.5ER/NRSolarBranch 161kV Substation11/28/2017DISIS STAGE   
GEN-2017-232DISIS-2017-00204 SOUTHEASTBryan CountyOKOGE6/1/2020   52.252.252.2ER/NRSolarBrown 138kV Substation11/28/2017DISIS STAGE   
GEN-2017-233DISIS-2017-00204 SOUTHEASTGradyOKOGE12/1/2020   215215215ER/NRWindMinco 345kV11/28/2017DISIS STAGE   
GEN-2017-234DISIS-2017-00202 NEBRASKAGreeleyNENPPD12/31/2019   115115115ERWindSpalding to North Loup 115kV11/6/2017DISIS STAGE   
GEN-2017-235DISIS-2017-00201 NORTHWardNDBEPC12/1/2020   505050ER/NRWindLogan 230kV Substation11/30/2017DISIS STAGE   
GEN-2017-236DISIS-2017-00201 NORTHWardNDBEPC12/1/2020   505050ER/NRWindLogan 230kV Substation11/30/2017DISIS STAGE   
GEN-2017-237DISIS-2017-00201 NORTHRooseveltMTBEPC9/1/2023   150150150ERWindSnake Butte 115kV Substation11/30/2017DISIS STAGE   
GEN-2017-239DISIS-2017-00205 SOUTHWESTYoakumTXSPS6/1/2023   300300300ERSolarMahoney 230kV Substation11/30/2017DISIS STAGE   
GEN-2017-240DISIS-2017-00204 SOUTHEASTOkmulgeeOKOGE12/1/2020   202202202ER/NRSolarBristow 138kV Substation11/30/2017DISIS STAGE   
GEN-2018-003DISIS-2018-00104 SOUTHEASTBowieTXAEP12/31/202111/30/2024  150150150ER/NRSolarNorth Boston-Bann 138kV Line4/25/2018DISIS STAGE   
GEN-2018-004DISIS-2018-00105 SOUTHWESTLeaNMSPS12/31/201912/22/2023  74.9974.9974.99ERSolarT14 Circuit 115kV line4/26/2018DISIS STAGE   
GEN-2018-007DISIS-2018-00101 NORTHGrant/RobertsSDWAPA12/31/202110/31/2025  150150150ER/NRSolarSummit 115kV Substation4/27/2018DISIS STAGE   
GEN-2018-008DISIS-2018-00101 NORTHMcIntoshNDBEPC9/30/20216/1/2025  252252252ER/NRWindGroton-Leland Olds 345kV Line4/27/2018DISIS STAGE   
GEN-2018-009DISIS-2018-00103 CENTRALSeward/MeadeKSSUNC12/1/202012/31/2025  150150150ERWindCimarron 115kV Substation4/27/2018DISIS STAGE   
GEN-2018-010DISIS-2018-00101 NORTHMontrailNDBEPC12/1/202112/31/2024  74.174.174.1ER/NRBattery/StorageNeset 230kV Substation4/27/2018DISIS STAGE   
GEN-2018-011DISIS-2018-00104 SOUTHEASTKingfisherOKWFEC12/1/202012/31/2028  74.174.174.1ER/NRBattery/StorageDover 138 kV Switching Station4/27/2018DISIS STAGE   
GEN-2018-012DISIS-2018-00102 NEBRASKAWayneNENPPD12/1/20216/1/2025  74.174.174.1ER/NRWindAntelope 345kV line4/27/2018DISIS STAGE   
GEN-2018-013DISIS-2018-00103 CENTRALDickinsonKSWERE 12/1/2021  74.174.174.1ER/NRWindAbilene Energy Center-Northview 115kV Line4/27/2018DISIS STAGE   
GEN-2018-014DISIS-2018-00103 CENTRALHoltMOTMO11/30/202011/30/2020  74.174.174.1ER/NRWindHolt County 345kV Substation4/27/2018DISIS STAGE   
GEN-2018-015DISIS-2018-00105 SOUTHWESTVernon/WilbargerTXSPS10/31/20216/1/2025  252252252ER/NRSolarTuco-Oklaunion 345kV Line4/27/2018DISIS STAGE   
GEN-2018-021DISIS-2018-00104 SOUTHEASTWashitaOKAEP12/1/202012/1/2020  74.174.174.1ER/NRSolarChisholm-Gracemont 345kV Line5/24/2018DISIS STAGE   
GEN-2018-022DISIS-2018-00103 CENTRALNodawayMOGMO12/31/20207/15/2025  300300300ER/NRSolarMullen Creek 345kV Substation5/25/2018DISIS STAGE   
GEN-2018-024DISIS-2018-00104 SOUTHEASTMuskogeeOKOGE10/15/202312/31/2024  100100100ERBattery/StorageCanadian River-Muskogee and Muskogee-Seminole 345kV5/28/2018DISIS STAGE   
GEN-2018-025DISIS-2018-00102 NEBRASKAWashington NEOPPD10/15/202312/31/2024  200200200ERBattery/StorageFort Calhoun 345kV Substation5/29/2018DISIS STAGE   
GEN-2018-026DISIS-2018-00104 SOUTHEASTCanadianOKOGE10/15/202312/31/2024  100100100ERBattery/StorageMustang 138kV Substation5/29/2018DISIS STAGE   
GEN-2018-027DISIS-2018-00104 SOUTHEASTTulsaOKAEP12/31/202410/15/2023  100100100ERBattery/StorageTulsa Power Station 38kV Substation5/29/2018DISIS STAGE   
GEN-2018-028DISIS-2018-00104 SOUTHEASTTulsaOKAEP10/15/202312/31/2024  200200200ERBattery/StorageTulsa North 138kV Substation5/29/2018DISIS STAGE   
GEN-2018-029DISIS-2018-00104 SOUTHEASTOklahomaOKOGE10/15/202312/31/2024  100100100ERBattery/StorageHorseshoe Lake 138kV Substation5/29/2018DISIS STAGE   
GEN-2018-030DISIS-2018-00103 CENTRALProwersCOSPS10/15/202312/31/2024  200200200ERBattery/StorageLamar-Finney 345kV Substation5/29/2018DISIS STAGE   
GEN-2018-031DISIS-2018-00103 CENTRALJacksonMOINDN12/31/202410/15/2023  505050ERBattery/StorageBlue Valley 161kV Substation5/29/2018DISIS STAGE   
GEN-2018-032DISIS-2018-00103 CENTRALMcPhearsonKSWERE12/1/202110/1/2026  310310310ERWindNeosho 345kV Substation5/29/2018DISIS STAGE   
GEN-2018-033DISIS-2018-00102 NEBRASKACassNEOPPD12/31/202310/15/2023  200200200ERBattery/StorageCass County 345kV Substation5/29/2018DISIS STAGE   
GEN-2018-036DISIS-2018-00102 NEBRASKAScotts BluffNEWAPA12/31/202410/15/2023  200200200ERBattery/StorageStegall 230kV Substation5/29/2018DISIS STAGE   
GEN-2018-037DISIS-2018-00102 NEBRASKADouglasNEOPPD12/31/202410/15/2023  100100100ERBattery/StorageLooping in OPPD (S1211) (S1220) (S1211) (S1299) 161kV5/29/2018DISIS STAGE   
GEN-2018-038DISIS-2018-00103 CENTRALRayMOGMO12/31/202012/31/2024  203.4203.4203.4ER/NRSolarSibley 345kV substation5/29/2018DISIS STAGE   
GEN-2018-039DISIS-2018-00101 NORTHLaMoureNDWAPA12/31/202012/31/2024  727272ER/NRSolarEdgeley 115kV substation5/29/2018DISIS STAGE   
GEN-2018-043DISIS-2018-00102 NEBRASKABurtNEOPPD12/31/202112/31/2025  500500500ERSolarFt. Calhoun - Raun 345 kV Line Break5/29/2018DISIS STAGE   
GEN-2018-044DISIS-2018-00102 NEBRASKAAntelopeNEOPPD12/31/202112/31/2025  500500500ERSolarFort Calhoun 345kV Substation5/29/2018DISIS STAGE   
GEN-2018-048DISIS-2018-00104 SOUTHEASTCaddoOKOGE12/31/20215/1/2025  300300300ERSolarPecan Creek 345kV Substation5/29/2018DISIS STAGE   
GEN-2018-049DISIS-2018-00103 CENTRALSumnerKSITCGP12/31/202112/31/2025  120120120ERSolarThistle 345kV Substation5/29/2018DISIS STAGE   
GEN-2018-050DISIS-2018-00104 SOUTHEASTCaddoLAAEP12/31/202112/1/2024  200200200ERSolarLongwood 345kV Substation5/29/2018DISIS STAGE   
GEN-2018-051DISIS-2018-00105 SOUTHWESTMuskogee CountyOKOGE12/31/20215/1/2025  353535ERBattery/StoragePecan Creek 345kV5/29/2018DISIS STAGE   
GEN-2018-052DISIS-2018-00105 SOUTHWESTLeaNMSPS12/31/202112/31/2024  707070ERBattery/StorageRoadrunner 115kV Substation5/29/2018DISIS STAGE   
GEN-2018-053DISIS-2018-00103 CENTRALJasperMOWERE12/31/202112/31/2025  100100100ERWindKelly 161kV Substation5/29/2018DISIS STAGE   
GEN-2018-054DISIS-2018-00103 CENTRALLinnKSGMO12/31/202112/31/2025  120120120ERSolarKC South - N. Raymore 161kV Line5/29/2018DISIS STAGE   
GEN-2018-055DISIS-2018-00104 SOUTHEASTGradyOKAEP12/31/202012/31/2024  252252252ER/NRSolarTerry Road 345kV station (shared with Rush Springs Windfarm on a common gentie) 5/29/2018DISIS STAGE   
GEN-2018-056DISIS-2018-00102 NEBRASKAKnox/HoltNEWAPA12/31/202012/31/2024  102.6102.6102.6ER/NRSolarFort Thompson-Grand Island (Grand Prairie) 345kV5/29/2018DISIS STAGE   
GEN-2018-057DISIS-2018-00103 CENTRALSedgwickKSWERE12/31/202012/31/2024  203.4203.4203.4ER/NRSolarGordon Evans 138kV5/29/2018DISIS STAGE   
GEN-2018-058DISIS-2018-00103 CENTRALLeavenworthKSWERE12/31/202012/31/2024  252252252ER/NRSolarStranger Creek 345kV5/29/2018DISIS STAGE   
GEN-2018-059DISIS-2018-00103 CENTRALLeavenworthKSWERE12/31/202012/31/2024  252252252ER/NRSolarStranger Creek 345kV5/29/2018DISIS STAGE   
GEN-2018-060DISIS-2018-00102 NEBRASKAWebsterNENPPD12/1/202012/31/2024  505050ER/NRWindAxtell-Post Rock 345 kV5/29/2018DISIS STAGE   
GEN-2018-061DISIS-2018-00103 CENTRALJasperMOWERE12/31/202112/31/2025  505050ERWindKelly 161kV Substation5/29/2018DISIS STAGE   
GEN-2018-062DISIS-2018-00103 CENTRALWyandotteKSKACY12/31/202012/31/2024  75.675.675.6ER/NRSolarNearman 161kV substation5/29/2018DISIS STAGE   
GEN-2018-063DISIS-2018-00203 CENTRALGreeneMOEDE6/30/202112/1/2025  575757ER/NRSolarSedalia Marshfield Springfield Nichols Street 69kV circuit10/23/2018DISIS STAGE   
GEN-2018-064DISIS-2018-00204 SOUTHEASTBentonARGRDA6/30/202112/31/2025  808080ER/NRSolarTonnece Substation 69kV10/24/2018DISIS STAGE   
GEN-2018-065DISIS-2018-00202 NEBRASKAMadisonNENPPD7/1/20206/1/2025  19.819.819.8ER/NRWindAntelope 345 kV Substation10/24/2018DISIS STAGE   
GEN-2018-067DISIS-2018-00201 NORTHWilliamsNDMWEC10/30/202010/30/2026  255255255ERWind115kV Strandahl sub 10/25/2018DISIS STAGE   
GEN-2018-068DISIS-2018-00202 NEBRASKAMadisonNENPPD9/1/20226/1/2025  302.4302.4302.4ER/NRWindAntelope 345 kV Substation10/26/2018DISIS STAGE   
GEN-2018-069DISIS-2018-00201 NORTHWibauxMTWAPA12/31/20206/1/2025  125125125ER/NRWindWAPA-UGP Mingusville 230kV10/26/2018DISIS STAGE   
GEN-2018-070DISIS-2018-00201 NORTHYanktonSDWAPA12/31/20194/22/2020  18.3118.3118.31ER/NRWindUtica Junction 230 kV substation10/29/2018DISIS STAGE   
GEN-2018-071DISIS-2018-00204 SOUTHEASTKayOKOGE11/30/202111/1/2024  151151151ER/NRBattery/StorageRanch Road 345 kV10/25/2018DISIS STAGE   
GEN-2018-072DISIS-2018-00204 SOUTHEASTOsageOKOGE11/30/202111/1/2024  151151151ER/NRBattery/StorageRanch Road 345 kV10/26/2018DISIS STAGE   
GEN-2018-073DISIS-2018-00205 SOUTHWESTFloydTXSPS10/30/202010/30/2026  250250250ERSolar345kV Crawfish Substation10/24/2018DISIS STAGE   
GEN-2018-074DISIS-2018-00201 NORTHCrawford and Carrol IAWAPA5/10/202210/31/2025  120120120ER/NRWindDenison 230kV Substation10/31/2018DISIS STAGE   
GEN-2018-079DISIS-2018-00204 SOUTHEASTCraig/NovataOKAEP12/31/202312/31/2027  148148148ER/NRSolarFarmland-Delaware 138kV line11/18/2018DISIS STAGE   
GEN-2018-081DISIS-2018-00205 SOUTHWESTLamb TXSPS12/31/202312/31/2027  175175175ER/NRSolarPlant X 230kV Substation11/18/2018DISIS STAGE   
GEN-2018-082DISIS-2018-00204 SOUTHEASTPittsburgOKAEP12/31/202312/31/2027  215215215ER/NRWindPittsburg 345kV Substation11/18/2018DISIS STAGE   
GEN-2018-083DISIS-2018-00202 NEBRASKAMadisonNENPPD12/31/202312/31/2023  250250250ER/NRWindShell Creek-Hoskins 345kv Line Break11/16/2018DISIS STAGE   
GEN-2018-086DISIS-2018-00205 SOUTHWESTTerryTXSPS12/31/202012/31/2027  505050ER/NRBattery/StorageSulphur Springs 115kV substation11/21/2018DISIS STAGE   
GEN-2018-087DISIS-2018-00204 SOUTHEASTBowieTXAEP12/31/202312/15/2027  757575ER/NRBattery/StorageLydia 345kV substation11/21/2018DISIS STAGE   
GEN-2018-088DISIS-2018-00204 SOUTHEASTBowieTXAEP12/31/202312/15/2027  130130130ER/NRSolarLydia 345kV substation11/21/2018DISIS STAGE   
GEN-2018-089DISIS-2018-00205 SOUTHWESTCastroTXSPS12/31/202312/31/2027  196196196ER/NRWindNewhart 230kV Substation11/21/2018DISIS STAGE   
GEN-2018-090DISIS-2018-00202 NEBRASKAWashingtonNEOPPD12/31/202312/31/2027  125125125ER/NRBattery/StorageRaun-Fort Calhoun 345kV Line11/21/2018DISIS STAGE   
GEN-2018-091DISIS-2018-00205 SOUTHWESTWilbargerTXSPS12/31/202312/15/2027  250250250ER/NRBattery/StorageOklaunion-Tuco 345kV Line Break11/21/2018DISIS STAGE   
GEN-2018-092DISIS-2018-00205 SOUTHWESTFoard/WilbargerTXSPS12/31/202312/15/2027  400400400ER/NRSolarOklaunion-Tuco 345kV Line Break11/21/2018DISIS STAGE   
GEN-2018-093DISIS-2018-00203 CENTRALSedgwickKSWERE12/31/202112/31/2027  606060ER/NRBattery/StorageGordan Evans 137kV Substation11/21/2018DISIS STAGE   
GEN-2018-097DISIS-2018-00205 SOUTHWESTParmerTXSPS12/31/202312/31/2027  100100100ER/NRSolarTolk 230kV Substation11/21/2018DISIS STAGE   
GEN-2018-099DISIS-2018-00205 SOUTHWESTParmerTXSPS12/31/202312/31/2027  300300300ER/NRWindTolk 230kV Substation11/21/2018DISIS STAGE   
GEN-2018-101DISIS-2018-00203 CENTRALBatesMOKCPL12/31/202312/31/2025  175175175ER/NRSolarLaCygne 345kV Substation11/21/2018DISIS STAGE   
GEN-2018-106DISIS-2018-00204 SOUTHEASTCaddoLAAEP12/31/202312/15/2025  330330330ER/NRSolarLongwood 345kV substation11/2/2018DISIS STAGE   
GEN-2018-108DISIS-2018-00203 CENTRALBarberKSITCGP12/31/202012/31/2020  959595ER/NRBattery/StorageThistle 345kV substation11/21/2018DISIS STAGE   
GEN-2018-111DISIS-2018-00205 SOUTHWESTParmerTXSPS12/31/202312/31/2027  757575ER/NRBattery/StorageTolk 230kV substation11/21/2018DISIS STAGE   
GEN-2018-112DISIS-2018-00205 SOUTHWESTParmerTXSPS12/31/202312/31/2027  185185185ER/NRSolarTolk 230kV substation11/21/2018DISIS STAGE   
GEN-2018-115DISIS-2018-00204 SOUTHEASTLawtonOKAEP12/1/202112/1/2021  250250250ER/NRHybridSolar/StorageLawton East Side 345kV/138kv Substation11/21/2018DISIS STAGE   
GEN-2018-116DISIS-2018-00203 CENTRALBartonKSSUNC12/31/20225/1/2026  150150150ER/NRSolarFrey Street 115kV bus11/20/2018DISIS STAGE   
GEN-2018-117DISIS-2018-00204 SOUTHEASTRoger MillsOKAEP12/31/20225/1/2026  150150150ER/NRSolarSweetwater 230kV11/20/2018DISIS STAGE   
GEN-2018-120DISIS-2018-00203 CENTRALNemahaKSWERE12/31/202312/15/2027  200200200ER/NRWindKelly 161kV Substation11/21/2018DISIS STAGE   
GEN-2018-121DISIS-2018-00203 CENTRALCassMOGMO12/31/202012/31/2027  505050ER/NRBattery/StorageKC South-N. Raymore 161kV Line11/21/2018DISIS STAGE   
GEN-2018-122DISIS-2018-00205 SOUTHWESTBaylorTXAEP12/31/202312/15/2027  200200200ER/NRWindOklaunion 345kV Substation11/21/2018DISIS STAGE   
GEN-2018-123DISIS-2018-00203 CENTRALEllsworthKSKCPL12/31/202312/31/2025  200200200ER/NRWindSibley to Overton 345kV11/21/2018DISIS STAGE   
GEN-2018-124DISIS-2018-00205 SOUTHWESTParmerTXSPS12/31/202312/31/2027  200200200ER/NRSolarTolk 230kV substation11/21/2018DISIS STAGE   
GEN-2018-125DISIS-2018-00202 NEBRASKALincolnNENPPD12/15/202212/1/2024  231231231ER/NRWindNew switching station on Gentleman to Sweetwater 345kV line11/19/2018DISIS STAGE   
GEN-2018-128DISIS-2018-00203 CENTRALSumnerKSWERE9/1/202110/1/2026  200.22200.22200.22ER/NRWindRenfrow-Viola 345 kV11/19/2018DISIS STAGE   
GEN-2018-129DISIS-2018-00201 NORTHHyde/HughesSDWAPA9/1/202110/1/2026  200.22200.22200.22ER/NRWindFort Thompson-Oahe 230kV11/19/2018DISIS STAGE   
GEN-2018-131DISIS-2018-00202 NEBRASKAPierceNENPPD12/31/202012/31/2024  221.4221.4221.4ER/NRSolarAntelope-Hoskins 345kV11/21/2018DISIS STAGE   
GEN-2018-132DISIS-2018-00202 NEBRASKAPierceNENPPD12/31/202012/31/2024  201.6201.6201.6ER/NRSolarNeligh-Hoskins 345kV line11/21/2018DISIS STAGE   
GEN-2019-001DISIS-2019-00103 CENTRALPrattKSWERE12/31/201812/31/2018  252525ERWindThistle-Wichita Dbl Ckt (Buffalo Flats) 345kV11/27/2018DISIS STAGE   
GEN-2019-002DISIS-2019-00104 SOUTHEASTMayesOKGRDA12/1/20206/1/2025  100100100ERBattery/StorageMaid 161kV substation11/26/2018DISIS STAGE   
GEN-2019-003DISIS-2019-00105 SOUTHWESTRooseveltNMSPS12/1/20226/1/2025  150150150ER/NRSolarRoosevelt to Tolk West 230kV4/19/2019DISIS STAGE   
GEN-2019-004DISIS-2019-00105 SOUTHWESTHobbsNMSPS6/4/20196/4/2019  565656ERThermalCTHobbs 230kV / 115kV Switchyard4/22/2019DISIS STAGE   
GEN-2019-009DISIS-2019-00102 NEBRASKANemahaNEOPPD10/31/202212/31/2025  100100100ER/NRSolarS1263 Brock 161kV substation4/24/2019DISIS STAGE   
GEN-2019-011DISIS-2019-00105 SOUTHWESTYoakumTXSPS5/1/20235/1/2025  230230230ER/NRBattery/StorageYoakum 345kV Substation4/22/2019DISIS STAGE   
GEN-2019-012DISIS-2019-00104 SOUTHEASTWoodwardOKOGE5/1/20235/1/2025  200200200ER/NRBattery/StorageWoodward 345kV substation5/22/2019DISIS STAGE   
GEN-2019-013DISIS-2019-00104 SOUTHEASTRoger MillsOKAEP12/31/20215/1/2026  505050ER/NRBattery/StorageDempsey 230kV sub/Sweetwater 230kV4/24/2019DISIS STAGE   
GEN-2019-014DISIS-2019-00103 CENTRALFinneyKSSUNC12/1/202212/1/2025  125125125ER/NRHybridSolar/StorageHolcomb 115kV substation4/24/2019DISIS STAGE   
GEN-2019-016DISIS-2019-00103 CENTRALPolk and DadeMOEDE11/30/202212/1/2025  200200200ER/NRSolarDadeville 161kV Substation 4/30/2019DISIS STAGE   
GEN-2019-017DISIS-2019-00101 NORTHButteSDWAPA12/31/20214/1/2025  142.8142.8142.8ER/NRWindTap 115kV Maurine to Newell transmission line4/24/2019DISIS STAGE   
GEN-2019-018DISIS-2019-00103 CENTRALRiceKSMIDW3/1/20206/1/2021  15.5611.9715.56ER/NRThermalGas TurbineSaxman 115kV substation4/24/2019DISIS STAGE   
GEN-2019-019DISIS-2019-00101 NORTHSiouxIANIPCO2/1/20207/22/2022  15.1515.1515.15ER/NRThermalGas TurbineSiouxland 69kV4/24/2019DISIS STAGE    
GEN-2019-021DISIS-2019-00105 SOUTHWESTRooseveltNMSPS12/1/20226/1/2025  505050ER/NRSolarRoosevelt 230kV Substation4/29/2019DISIS STAGE   
GEN-2019-022DISIS-2019-00105 SOUTHWESTLeaNMSPS12/31/20218/30/2024  414141ER/NRSolarOxy Substation 115kV4/24/2019DISIS STAGE   
GEN-2019-023DISIS-2019-00101 NORTHWibauxMTWAPA12/31/20236/1/2025  110110110ER/NRHybridWind/StorageWAPA-UGP Mingusville 230kV5/8/2019DISIS STAGE   
GEN-2019-025DISIS-2019-00105 SOUTHWESTLeaNMSPS12/23/202312/31/2025  240240240ER/NRHybridSolar/StorageHobbs 230kV Substation5/8/2019DISIS STAGE   
GEN-2019-028DISIS-2019-00102 NEBRASKALincoln County, NENENPPD12/1/202212/1/2025  400400400ER/NRSolarGerald Gentlemen 345kV Substation4/23/2019DISIS STAGE   
GEN-2019-029DISIS-2019-00102 NEBRASKAKeith and DeuelNENPPD12/1/202112/31/2024  404404404ER/NRWindSidney Keystone 345 kV line4/25/2019DISIS STAGE   
GEN-2019-030DISIS-2019-00103 CENTRALFordKSITCGP12/1/202112/31/2024  252252252ER/NRWindSpearville to Clark County 345 kV line4/25/2019DISIS STAGE   
GEN-2019-033DISIS-2019-00102 NEBRASKAKnoxNEBEPC12/1/202112/31/2024  182182182ER/NRSolarSidney Keystone 345 kV line5/1/2019DISIS STAGE   
GEN-2019-035DISIS-2019-00103 CENTRALBarryMOEDE12/31/202212/31/2025  808080ER/NRSolarReeds Spring-Aurora 161kV Line5/2/2019DISIS STAGE   
GEN-2019-037DISIS-2019-00101 NORTHMercerNDBEPC12/1/202311/19/2024  150150150ER/NRSolarBEPC 230kV substation5/17/2019DISIS STAGE   
GEN-2019-039DISIS-2019-00102 NEBRASKAButlerNENPPD5/16/202212/31/2023  174.5174.2174.5ER/NRSolarColumbus Southeast-Rising City 115kV5/21/2019DISIS STAGE   
GEN-2019-041DISIS-2019-00102 NEBRASKALancasterNENPPD12/1/202012/31/2024  787878ER/NRSolar115kV Monolith Substation5/23/2019DISIS STAGE   
GEN-2019-042DISIS-2019-00102 NEBRASKACheyenneNEBEPC12/1/202012/31/2024  104104104ER/NRSolarSidney 230 kV5/23/2019DISIS STAGE   
GEN-2019-043DISIS-2019-00101 NORTHFallonMTWAPA11/1/202312/1/2023  150150150ER/NRSolarBaker-Mile City 230kV line5/23/2019DISIS STAGE   
GEN-2019-044DISIS-2019-00103 CENTRALFordKSSUNC12/31/202312/15/2027  100100100ER/NRSolarNorth Fort Dodge 115kV Substation5/24/2019DISIS STAGE   
GEN-2019-045DISIS-2019-00104 SOUTHEASTWoodsOKOGE12/31/202212/31/2027  175175175ER/NRSolarDeGrasse 138kV Substation5/24/2019DISIS STAGE   
GEN-2019-046DISIS-2019-00104 SOUTHEASTWoodsOKOGE12/31/202212/31/2022  909090ER/NRBattery/StorageDeGrasse 138kV substation5/24/2019DISIS STAGE   
GEN-2019-047DISIS-2019-00103 CENTRALButlerKSWERE12/31/202212/31/2027  150150150ER/NRBattery/StorageButler 138kV substation5/24/2019DISIS STAGE   
GEN-2019-048DISIS-2019-00103 CENTRALJacksonMOKCPL12/31/202212/31/2027  505050ER/NRBattery/StorageDuncan 69kV substation5/24/2019DISIS STAGE   
GEN-2019-049DISIS-2019-00104 SOUTHEASTCaddo ParishLAAEP12/31/202212/31/2027  606060ER/NRBattery/StorageFlournoy 138kV Substation5/24/2019DISIS STAGE   
GEN-2019-051DISIS-2019-00103 CENTRALBartonKSSUNC6/1/20235/1/2026  404040ER/NRBattery/StorageFrey St 115kV bus5/24/2019DISIS STAGE   
GEN-2019-052DISIS-2019-00104 SOUTHEASTCanadianOKOGE6/1/20235/1/2025  135135135ER/NRSolarCimarron-Minco 345kV line5/24/2019DISIS STAGE   
GEN-2019-053DISIS-2019-00103 CENTRALEdwards/PawneeKSSUNC6/1/20235/1/2026  505050ER/NRBattery/StorageGreat Bend-Spearville 230kV line5/24/2019DISIS STAGE   
GEN-2019-054DISIS-2019-00103 CENTRALBartonKSSUNC6/1/20235/1/2026  150150150ER/NRSolarGreat Bend- Circle 230kV line5/24/2019DISIS STAGE   
GEN-2019-055DISIS-2019-00103 CENTRALEdwards, PawneeKSSUNC6/1/20235/1/2026  150150150ER/NRSolarGreat Bend-Spearville 230kV line5/24/2019DISIS STAGE   
GEN-2019-056DISIS-2019-00105 SOUTHWESTRandallTXSPS12/31/202212/31/2027  100100100ER/NRBattery/StorageRandall 115kV substation5/24/2019DISIS STAGE   
GEN-2019-058DISIS-2019-00103 CENTRALFord, ClarkKSITCGP6/1/20235/1/2026  150150150ER/NRSolarClark County 345kV substation5/24/2019DISIS STAGE   
GEN-2019-060DISIS-2019-00101 NORTHDay SDBEPC12/31/202212/31/2025  150150150ER/NRWindGroton 345 kV substation5/22/2019DISIS STAGE   
GEN-2019-062DISIS-2019-00103 CENTRALButlerKSWERE12/31/202212/31/2027  909090ER/NRBattery/StoragePony Meadows 161kV substation5/24/2019DISIS STAGE   
GEN-2019-063DISIS-2019-00103 CENTRALFord, ClarkKSITCGP6/1/20235/1/2026  505050ER/NRBattery/StorageClark County 345kV substation5/24/2019DISIS STAGE   
GEN-2019-065DISIS-2019-00104 SOUTHEASTSmith, RuskTXAEP6/1/202412/1/2025  200200200ERBattery/StorageOverton 138kV5/23/2019DISIS STAGE   
GEN-2019-066DISIS-2019-00104 SOUTHEASTBeckhamOKAEP6/1/20235/1/2026  505050ER/NRBattery/StorageSweetwater 230kV substation5/24/2019DISIS STAGE   
GEN-2019-067DISIS-2019-00104 SOUTHEASTCanadianOKOGE6/1/20235/1/2026  303030ER/NRBattery/StorageCimarron - Minco 345kV line5/24/2019DISIS STAGE   
GEN-2019-068DISIS-2019-00103 CENTRALBartonKSSUNC6/1/20235/1/2026  505050ER/NRBattery/StorageGreat Bend - Circle 230kV line5/24/2019DISIS STAGE   
GEN-2019-069DISIS-2019-00102 NEBRASKAMadisonNENPPD12/31/202312/31/2027  100100100ER/NRSolarShell Creek-Hoskins 345kV Line5/24/2019DISIS STAGE   
GEN-2019-070DISIS-2019-00102 NEBRASKAMadisonNENPPD12/31/202312/31/2027  505050ER/NRSolarShell Creek-Hoskins 345kv Line5/24/2019DISIS STAGE   
GEN-2019-073DISIS-2019-00102 NEBRASKAMadisonNENPPD12/31/202312/31/2027  100100100ER/NRSolarShell Creek-Hoskins 345kv Line5/24/2019DISIS STAGE   
GEN-2019-074DISIS-2019-00105 SOUTHWESTLambTXSPS12/31/202312/31/2023  100100100ER/NRBattery/StoragePlant X 230kV Substation5/24/2019DISIS STAGE   
GEN-2019-075DISIS-2019-00102 NEBRASKAJohnsonNEOPPD12/31/202312/31/2027  242424ER/NRSolarS969 South Sterling 69kV Substation5/24/2019DISIS STAGE   
GEN-2019-076DISIS-2019-00102 NEBRASKAJohnson NEOPPD12/31/202212/31/2027  141414ER/NRBattery/StorageS969 South Sterling 69kV Substation5/24/2019DISIS STAGE   
GEN-2019-079DISIS-2019-00103 CENTRALGrayKSSUNC6/30/201912/31/2024  131313ERWindGray County 115kV5/21/2019DISIS STAGE   
GEN-2020-001DISIS-2020-00102 NEBRASKACheyenne CountyNEBEPC11/30/202212/31/2022  200200200ER/NRSolarSidney Substation 345kV12/6/2019DISIS STAGE   
GEN-2020-002DISIS-2020-00102 NEBRASKAYutanNEOPPD11/15/20222/1/2024  818181ER/NRSolar6846 Substation 69 kV4/6/2020DISIS STAGE   
GEN-2020-003DISIS-2020-00103 CENTRALWinfieldKSWERE3/1/20236/1/2023  585858ER/NRThermalDiesel/GasEast Substation 69 kV4/1/2020DISIS STAGE   
GEN-2020-004DISIS-2020-00102 NEBRASKAOtoeNEOPPD10/1/202312/1/2023  250250250ER/NRSolarCass County to Nebraska City #2 345kV4/3/2020DISIS STAGE   
GEN-2020-005DISIS-2020-00105 SOUTHWESTCarson CountyTXSPS1/15/20232/15/2023  150150150ER/NRWindYarnall Tap - Conway 115 kV Line3/31/2020DISIS STAGE   
GEN-2020-006DISIS-2020-00101 NORTHBowman CountyNDBEPC11/1/202311/30/2023  250250250ER/NRSolarBowman 230kV substation4/23/2020DISIS STAGE   
GEN-2020-007DISIS-2020-00103 CENTRALLinn CountyKSKCPL7/1/20238/1/2023  650650650ER/NRSolarEvergy La Cygne 345kV Substation4/22/2020DISIS STAGE   
GEN-2020-008DISIS-2020-00103 CENTRALStevens CountyKSSUNC9/1/20239/24/2023  250250250ER/NRSolarSunflower Electric Carpenter 345kV Substation4/22/2020DISIS STAGE   
GEN-2020-009DISIS-2020-00104 SOUTHEASTFaxonOKAEP10/15/202612/31/2026  300300300ER/NRHybridSolarLawton to Oklaunion 345kV4/8/2020DISIS STAGE   
GEN-2020-010DISIS-2020-00104 SOUTHEASTMutualOKWFEC10/15/202612/31/2026  215215215ER/NRHybridSolarMooreland-Taloga Substations 138kV4/8/2020DISIS STAGE   
GEN-2020-011DISIS-2020-00102 NEBRASKAFunkNENPPD10/15/202612/31/2026  320320320ER/NRHybridSolarSweetwater Substation 345kV4/8/2020DISIS STAGE   
GEN-2020-012DISIS-2020-00104 SOUTHEASTWaltersOKWFEC10/15/202612/31/2026  113113113ER/NRHybridSolarWalters 2 Substation 69kV4/10/2020DISIS STAGE   
GEN-2020-013DISIS-2020-00102 NEBRASKAOrleansNENPPD10/15/202612/31/2026  215215215ER/NRHybridSolarHoldrege Substation 115kV4/10/2020DISIS STAGE   
GEN-2020-014DISIS-2020-00101 NORTHAlexanderNDBEPC6/17/202110/18/2021  60.54545ER/NRThermalGasLonesome Creek 115kV4/20/2020DISIS STAGE   
GEN-2020-015DISIS-2020-00103 CENTRALLawrence & Dade CountyMOEDE11/1/202112/1/2021  104104104ER/NRSolarDadeville 161 Station4/19/2020DISIS STAGE   
GEN-2020-016DISIS-2020-00104 SOUTHEASTGarvin CountyOKOGE10/31/202212/1/2022  202202202ER/NRSolar138kV Cromwell Substation4/20/2020DISIS STAGE   
GEN-2020-017DISIS-2020-00105 SOUTHWESTLamb CountyTXSPS10/1/202512/31/2025  74.8874.8874.88ER/NRSolar69kV Lamb County Interchange4/24/2020DISIS STAGE   
GEN-2020-018DISIS-2020-00101 NORTHSully CountySDBEPC7/30/20268/30/2026  205.2205.2205.2ER/NRWindLeland Olds-Ft. Thompson 345 kV4/28/2020DISIS STAGE   
GEN-2020-019DISIS-2020-00101 NORTHTripp CountySDWAPA7/30/20268/30/2026  182.4182.4182.4ER/NRWindWitten Substation 115 kV4/29/2020DISIS STAGE   
GEN-2020-020DISIS-2020-00104 SOUTHEASTBramanOKOGE9/30/202210/31/2022  201.6201.6201.6ER/NRWindRanch Road 345 kV Substation4/28/2020DISIS STAGE   
GEN-2020-021DISIS-2020-00101 NORTHSioux CountyNDBEPC11/30/202312/31/2023  235235235ER/NRWindLeLand Olds-Fort Thompson 345kV4/24/2020DISIS STAGE   
GEN-2020-022DISIS-2020-00103 CENTRALFinney CountyKSSUNC11/1/202312/1/2023  125125125ER/NRWindHOLCOMB SUB 115KV BUS4/29/2020DISIS STAGE   
GEN-2020-023DISIS-2020-00104 SOUTHEASTCarrierOKOGE11/1/202112/1/2021  202202202ER/NRBattery/StorageWoodring 345 KV Station4/7/2020DISIS STAGE   
GEN-2020-024DISIS-2020-00102 NEBRASKASarpy CountyNEOPPD4/30/20235/31/2023  424.5418424.5ER/NRThermalCTSubstation 1363; 161kV Substation4/29/2020DISIS STAGE   
GEN-2020-025DISIS-2020-00102 NEBRASKASarpy CountyNEOPPD4/30/20235/31/2023  303258303ER/NRThermalCTSubstation 1363; 161kV Substation4/29/2020DISIS STAGE   
GEN-2020-026DISIS-2020-00102 NEBRASKASarpy CountyNEOPPD4/30/20235/31/2023  56.5256.5256.52ER/NRThermalReciprocating EngineSubstation 1363; 161kV Substation4/29/2020DISIS STAGE   
GEN-2020-027DISIS-2020-00102 NEBRASKASarpy CountyNEOPPD4/30/20235/31/2023  505050ER/NRSolarS1281 – S1362 161kV (S1363)4/29/2020DISIS STAGE   
GEN-2020-028DISIS-2020-00102 NEBRASKASarpy CountyNEOPPD4/30/20235/31/2023  303258303ER/NRThermalCTSubstation 1363; 161kV Substation4/29/2020DISIS STAGE   
GEN-2020-029DISIS-2020-00102 NEBRASKASarpy CountyNEOPPD4/30/20235/31/2023  56.5256.5256.52ER/NRThermalReciprocating EngineSubstation 1363; 161kV Substation4/29/2020DISIS STAGE   
GEN-2020-030DISIS-2020-00102 NEBRASKASarpy CountyNEOPPD4/30/20235/31/2023  505050ER/NRSolarS1281 – S1362 161kV (S1363)4/29/2020DISIS STAGE   
GEN-2020-031DISIS-2020-00102 NEBRASKASarpy CountyNEOPPD4/30/20235/31/2023  303258303ER/NRThermalCTSubstation 1363; 161kV Substation4/29/2020DISIS STAGE   
GEN-2020-032DISIS-2020-00102 NEBRASKASarpy CountyNEOPPD4/30/20235/31/2023  56.5256.5256.52ER/NRThermalReciprocating EngineSubstation 1363; 161kV Substation4/29/2020DISIS STAGE   
GEN-2020-033DISIS-2020-00102 NEBRASKASarpy CountyNEOPPD4/30/20235/31/2023  505050ER/NRSolarS1281 – S1362 161kV (S1363)4/29/2020DISIS STAGE   
GEN-2020-034DISIS-2020-00102 NEBRASKASarpy CountyNEOPPD4/30/20235/31/2023  56.5256.5256.52ER/NRThermalReciprocating EngineSubstation 1363; 161kV Substation4/29/2020DISIS STAGE   
GEN-2020-035DISIS-2020-00102 NEBRASKAPlattsmouthNEOPPD4/30/20235/31/2023  424.5418424.5ER/NRThermalCTSubstation 3740; 345kV4/29/2020DISIS STAGE   
GEN-2020-036DISIS-2020-00102 NEBRASKAPlattsmouthNEOPPD4/30/20235/31/2023  303258303ER/NRThermalCTSubstation 3740; 345kV4/29/2020DISIS STAGE   
GEN-2020-037DISIS-2020-00102 NEBRASKAPlattsmouthNEOPPD4/30/20235/31/2023  56.5256.5256.52ER/NRThermalReciprocating EngineSubstation 3740; 345kV4/29/2020DISIS STAGE   
GEN-2020-038DISIS-2020-00102 NEBRASKAPlattsmouthNEOPPD4/30/20235/31/2023  303258303ER/NRThermalCTSubstation 3740; 345kV4/29/2020DISIS STAGE   
GEN-2020-039DISIS-2020-00102 NEBRASKAPlattsmouthNE4/30/20235/31/2023  56.5256.5256.52ER/NRThermalReciprocating EngineSubstation 3740; 345kV4/29/2020DISIS STAGE   
GEN-2020-040DISIS-2020-00102 NEBRASKAPlattsmouthNE4/30/20235/31/2023  303258303ER/NRThermalCTSubstation 3740; 345kV4/29/2020DISIS STAGE   
GEN-2020-041DISIS-2020-00102 NEBRASKAPlattsmouthNEOPPD4/30/20235/31/2023  56.5256.5256.52ER/NRThermalReciprocating EngineSubstation 3740; 345kV4/29/2020DISIS STAGE   
GEN-2020-042DISIS-2020-00102 NEBRASKAPlattsmouthNEOPPD4/30/20235/31/2023  56.5256.5256.52ER/NRThermalReciprocating EngineSubstation 3740; 345kV4/29/2020DISIS STAGE   
GEN-2020-043DISIS-2020-00102 NEBRASKADouglas CountyNEOPPD4/30/20235/31/2023  56.5256.5256.52ER/NRThermalReciprocating EngineBetween Substation 1209 and 1252; 161kV4/29/2020DISIS STAGE   
GEN-2020-044DISIS-2020-00102 NEBRASKADouglas CountyNEOPPD4/30/20235/31/2023  56.5256.5256.52ER/NRThermalReciprocating EngineBetween Substation 1209 and 1252; 161kV4/29/2020DISIS STAGE   
GEN-2020-045DISIS-2020-00102 NEBRASKADouglas CountyNEOPPD4/30/20235/31/2023  56.5256.5256.52ER/NRThermalReciprocating EngineBetween Substation 1209 and 1252; 161kV4/29/2020DISIS STAGE   
GEN-2020-046DISIS-2020-00102 NEBRASKADouglas CountyNEOPPD4/30/20235/31/2023  56.5256.5256.52ER/NRThermalReciprocating EngineBetween Substation 1209 and 1252; 161kV4/29/2020DISIS STAGE   
GEN-2020-047DISIS-2020-00102 NEBRASKAOmahaNEOPPD4/30/20235/31/2023  56.5256.5256.52ER/NRThermalReciprocating EngineSubstation 911; 69 kV4/29/2020DISIS STAGE   
GEN-2020-048DISIS-2020-00102 NEBRASKAOmahaNEOPPD4/30/20235/31/2023  56.5256.5256.52ER/NRThermalReciprocating EngineSubstation 1211; 161kV4/29/2020DISIS STAGE   
GEN-2020-049DISIS-2020-00102 NEBRASKAOmahaNEOPPD4/30/20235/31/2023  56.5256.5256.52ER/NRThermalReciprocating EngineSubstation 1211; 161kV4/29/2020DISIS STAGE   
GEN-2020-050DISIS-2020-00102 NEBRASKAOmahaNEOPPD4/30/20235/31/2023  56.5256.5256.52ER/NRThermalReciprocating EngineSubstation 1211; 161kV4/29/2020DISIS STAGE   
GEN-2020-051DISIS-2020-00102 NEBRASKASutherlandNENPPD11/30/202312/31/2023  250250250ER/NRSolarGerald Gentleman Substation 345 kV4/29/2020DISIS STAGE   
GEN-2020-052DISIS-2020-00103 CENTRALLabette CoKSWERE8/1/202312/15/2023  251251251ER/NRWindNeosho-Delware 345 kV4/29/2020DISIS STAGE   
GEN-2020-053DISIS-2020-00103 CENTRALNewton CoMOEDE8/1/202312/15/2023  240240240ER/NRWindMonette-Flint Creek 345 kV4/29/2020DISIS STAGE   
GEN-2020-054DISIS-2020-00104 SOUTHEASTBowie CountyTXAEP8/1/202312/15/2023  298298298ER/NRSolarLydia 345 kV Station4/27/2020DISIS STAGE   
GEN-2020-055DISIS-2020-00104 SOUTHEASTBowie CountyTXAEP8/1/202312/15/2023  717171ER/NRBattery/StorageLydia 345 kV Station4/27/2020DISIS STAGE   
GEN-2020-056DISIS-2020-00103 CENTRALRussell CountyKSSUNC3/30/20237/15/2024  202020ER/NRSolarRussell 115 kV Substation4/30/2020DISIS STAGE   
GEN-2020-057DISIS-2020-00103 CENTRALGarnerKSWERE11/1/202612/1/2026  433.2433.2433.2ER/NRSolarEast Waverly Substation 115 kV4/30/2020DISIS STAGE   
GEN-2020-058DISIS-2020-00103 CENTRALGarnerKSKCPL11/1/202612/1/2026  433.2433.2433.2ER/NRSolarCraig-West Gardner 345 kV4/30/2020DISIS STAGE   
GEN-2020-059DISIS-2020-00105 SOUTHWESTLovingtonNMSPS3/2/20254/1/2025  500500500ER/NRSolarTuco-Yoakum-Hobbs 345 kV4/29/2020DISIS STAGE   
GEN-2020-060DISIS-2020-00105 SOUTHWESTLubbockTXSPS5/1/20266/1/2026  200200200ER/NRBattery/StorageLubbock East Substation 230 kV4/30/2020DISIS STAGE   
GEN-2020-061DISIS-2020-00103 CENTRALPleasant HillMOGMO5/1/20215/1/2021  292921ER/NRThermalGasPleasant Hill 345/161/69 kV Substation4/28/2020DISIS STAGE   
GEN-2020-062DISIS-2020-00105 SOUTHWESTClovisNMSPS11/1/202312/1/2023  409.8409.8409.8ER/NRSolarOASIS 230/115 kV Substation4/29/2020DISIS STAGE   
GEN-2020-063DISIS-2020-00105 SOUTHWESTElidaNMSPS11/1/202312/1/2023  305.8305.8305.8ER/NRSolarOasis - San Juan Mesa 230 kV Line4/29/2020DISIS STAGE   
GEN-2020-064DISIS-2020-00103 CENTRALJoplinMOEDE10/1/202010/31/2020  643664ER/NRThermalCT4544 Stateline CC 161kV Substation4/22/2020DISIS STAGE   
GEN-2020-065DISIS-2020-00105 SOUTHWESTGainesNMSPS12/1/20255/1/2026  1003912.31003ERThermalCombined CycleHobbs-Andrews 345 kV Line4/30/2020DISIS STAGE   
GEN-2020-066DISIS-2020-00105 SOUTHWESTHockleyTXSPS11/1/202412/1/2024  253.8253.8253.8ER/NRWindTuco to Yoakum 345kV line4/24/2020DISIS STAGE   
GEN-2020-067DISIS-2020-00105 SOUTHWESTHockleyTXSPS11/1/202412/1/2024  352.5352.5352.5ER/NRWindTuco to Yoakum 345kV line4/24/2020DISIS STAGE   
GEN-2020-068DISIS-2020-00105 SOUTHWESTHockleyTXSPS11/1/202412/1/2024  400400400ER/NRSolarTuco to Yoakum 345kV line4/29/2020DISIS STAGE   
GEN-2020-069DISIS-2020-00102 NEBRASKACherryNENPPD11/30/202312/31/2023  52.8552.8552.85ER/NRWindCody to Valentine 115kV line4/24/2020DISIS STAGE   
GEN-2020-070DISIS-2020-00103 CENTRALOsborneKSSUNC9/30/202410/31/2024  255255255ER/NRWindPostrock to Axtell 345 KV line4/30/2020DISIS STAGE   
GEN-2020-071DISIS-2020-00103 CENTRALOsageKSWERE9/30/202410/31/2024  252252252ER/NRWindSwissvale to Morris 230 KV line4/30/2020DISIS STAGE   
GEN-2020-072DISIS-2020-00103 CENTRALWindsorMOGMO7/1/20258/1/2025  150150150ER/NRSolarWindsor to AEC Sedalia 161 kV line4/30/2020DISIS STAGE   
GEN-2020-073DISIS-2020-00103 CENTRALFranklinKSKCPL7/1/20258/1/2025  190190190ER/NRSolarS Ottawa to SE Ottawa 161 kV line4/30/2020DISIS STAGE   
GEN-2020-074DISIS-2020-00104 SOUTHEASTCarterOKAEP3/31/20235/1/2023  200200200ER/NRBattery/StorageLawton to Sunnyside 345 kV Line4/28/2020DISIS STAGE   
GEN-2020-075DISIS-2020-00104 SOUTHEASTComancheOKOGE5/1/20236/1/2023  200200200ER/NRBattery/StorageCimmarron to Lawton 345 kV Line4/28/2020DISIS STAGE   
GEN-2020-076DISIS-2020-00103 CENTRALButlerKSWERE11/30/202212/31/2022  200200200ER/NRBattery/StorageBenton to Wolf Creek 345 kV Line4/28/2020DISIS STAGE   
GEN-2020-077DISIS-2020-00102 NEBRASKAThayerNENPPD11/30/202312/31/2023  151.2151.2151.2ER/NRWindNorth Hebron to Fairbury 115 kV4/28/2020DISIS STAGE   
GEN-2020-078DISIS-2020-00102 NEBRASKAWashingtonNEOPPD11/30/202212/31/2022  100100100ER/NRSolarSubstation 1226 to Substation 1237, 161kV Tap4/30/2020DISIS STAGE   
GEN-2020-079DISIS-2020-00103 CENTRALJasperMOEDE7/1/20259/30/2025  225225225ER/NRSolarLa Russell 161 kV substation4/30/2020DISIS STAGE   
GEN-2020-080DISIS-2020-00105 SOUTHWESTElk CityNMSPS5/1/20226/1/2022  200200200ER/NRBattery/StorageTuco Interchange 345 kV Substation4/30/2020DISIS STAGE   
GEN-2020-081DISIS-2020-00104 SOUTHEASTTenaskaTXAEP5/1/20226/1/2022  200200200ER/NRBattery/StorageMt. Enterprise 345 kV substation4/30/2020DISIS STAGE   
GEN-2020-082DISIS-2020-00103 CENTRALSewardKSSUNC3/30/20234/30/2023  202020ER/NRSolarLiberal 115 kV Substation4/30/2020DISIS STAGE   
GEN-2020-083DISIS-2020-00101 NORTHFairviewMTWAPA10/20/202311/21/2023  74.574.574.5ER/NRSolarFairview 115kV Substation4/30/2020DISIS STAGE   
GEN-2020-084DISIS-2020-00102 NEBRASKATekamahNEOPPD4/1/20225/1/2022  350350350ER/NRSolarRaun - Fort Calhoun 345 kV4/30/2020DISIS STAGE   
GEN-2020-085DISIS-2020-00104 SOUTHEASTWilsonOKAEP4/2/20235/1/2023  500500500ER/NRSolarLawton to Sunnyside 345 kV Line4/23/2020DISIS STAGE   
GEN-2020-086DISIS-2020-00103 CENTRALEl DoradoKSWERE11/30/202212/31/2022  500500500ER/NRSolarBenton to Wolf Creek 345 kV Line4/23/2020DISIS STAGE   
GEN-2020-087DISIS-2020-00104 SOUTHEASTComancheOKOGE5/1/20236/1/2023  500500500ER/NRSolarCimmarron to Lawton 345 kV Line4/23/2020DISIS STAGE   
GEN-2020-088DISIS-2020-00103 CENTRALJasperMOEDE11/30/202212/31/2022  150150150ER/NRSolarLa Russel 161 kV Substation4/30/2020DISIS STAGE   
GEN-2020-089DISIS-2020-00103 CENTRALLabette CoKSWERE11/1/202112/1/2021  104104104ER/NRSolarNeosho 345kV Substation4/27/2020DISIS STAGE   
GEN-2020-090DISIS-2020-00103 CENTRALLabette CoKSWERE11/1/202112/1/2021  204.3204.3204.3ER/NRSolarNeosho 345kV Substation4/27/2020DISIS STAGE   
GEN-2020-091DISIS-2020-00101 NORTHAlexanderNDBEPC11/2/202512/1/2025  150150150ER/NRSolarPatent Gate Substation 115 kV4/30/2020DISIS STAGE   
GEN-2020-092DISIS-2020-00104 SOUTHEASTMayes CountyOKAEP11/2/202512/1/2024  100100100ER/NRSolarPryor Junction Substation 115 kV4/30/2020DISIS STAGE   
GEN-2020-093DISIS-2020-00101 NORTHPotter CountySDBEPC11/14/202512/1/2024  150150150ER/NRSolarWhitlock Substation 230 kV4/30/2020DISIS STAGE   
GEN-2020-094DISIS-2020-00102 NEBRASKASyracuseNEOPPD4/2/20235/1/2023  250250250ER/NRSolarNeb. City - 103rd & Rokeby 345 kV4/30/2020DISIS STAGE   
GEN-2020-SR1Surplus04 SOUTHEASTBeckhamOKWFEC12/1/20226/1/2024  404040ERBattery/StorageErick 138kV Substation8/4/2020IA FULLY EXECUTED/ON SCHEDULE   
GEN-2020-SR2Surplus04 SOUTHEASTJohnstonOKOGE12/1/20216/1/2023  100100100ER/NRBattery/StorageBrown 138kV8/4/2020IA FULLY EXECUTED/ON SCHEDULE   
GEN-2020-SR3Surplus04 SOUTHEASTJohnstonOKOGE9/1/20216/1/2023  200200200ER/NRBattery/StorageHugo-Sunnyside 345 kV8/4/2020IA FULLY EXECUTED/ON SCHEDULE   
GEN-2021-001DISIS-2021-00104 SOUTHEASTDurantOKOGE9/25/202412/24/2024  100100100ER/NRBattery/Storage138kV Brown Substation12/29/2020DISIS STAGE   
GEN-2021-002DISIS-2021-00104 SOUTHEASTOkeeneOKWFEC9/25/202412/24/2024  100100100ER/NRBattery/Storage138kV Okeene Substation12/29/2020DISIS STAGE   
GEN-2021-003DISIS-2021-00101 NORTHRichlandMTWAPA10/15/202312/1/2023  75.575.575.5ER/NRSolarFairview 115kV Substation12/11/2020DISIS STAGE   
GEN-2021-004DISIS-2021-00104 SOUTHEASTCarterOKOGE9/5/202612/1/2026  250250250ER/NRSolarSunnyside to Poolville 138kV Feeder4/30/2021DISIS STAGE   
GEN-2021-005DISIS-2021-00103 CENTRALSalineKSWERE11/1/20233/1/2024  350350350ER/NRBattery/StorageSummit 230kV substation in Saline County, KS5/7/2021DISIS STAGE   
GEN-2021-006DISIS-2021-00103 CENTRALLabetteKSWERE10/1/20242/1/2025  300300300ER/NRBattery/StorageNeosho 345kV substation in Labette County, KS5/7/2021DISIS STAGE   
GEN-2021-007DISIS-2021-00102 NEBRASKAKnox and CedarNENPPD9/30/202512/31/2025  600600600ER/NRWind345kV bus of Turtle Creek Substation5/10/2021DISIS STAGE   
GEN-2021-008DISIS-2021-00101 NORTHMcKenzieNDBEPC5/9/202612/1/2026  270270270ER/NRSolar345kV Bus at BEPC Patent Gate Substation, McKenzie County, ND5/10/2021DISIS STAGE   
GEN-2021-009DISIS-2021-00101 NORTHBeadleSDWAPA11/1/20253/1/2026  225225225ER/NRBattery/StorageCarpenter 230kV substation in Clark county, South Dakota5/11/2021DISIS STAGE   
GEN-2021-010DISIS-2021-00101 NORTHWilliams CountyNDBEPC4/1/202712/1/2027  231273.6273.6ER/NRBattery/StorageWheelock 115 kV4/30/2021DISIS STAGE   
GEN-2021-011DISIS-2021-00101 NORTHWilliams NDBEPC4/1/202712/1/2027  74.991.291.2ER/NRBattery/StorageWheelock 115 kV4/30/2021DISIS STAGE   
GEN-2021-012DISIS-2021-00104 SOUTHEASTFranklinTXAEP11/15/20237/15/2024  225232.32232.32ER/NRSolarChapel Hill 138kV4/30/2021DISIS STAGE   
GEN-2021-013DISIS-2021-00104 SOUTHEASTFranklinTXAEP11/15/20237/15/2024  74.991.291.2ER/NRBattery/StorageChapel Hill 138kV4/30/2021DISIS STAGE   
GEN-2021-014DISIS-2021-00103 CENTRALGrant, Haskell, FinneyKSSPS4/1/202712/1/2027  231273.6273.6ER/NRBattery/StorageFinney 345 kV4/30/2021DISIS STAGE   
GEN-2021-015DISIS-2021-00103 CENTRALGrant, Haskell, FinneyKSSPS4/1/202712/1/2027  74.991.291.2ER/NRBattery/StorageFinney 345 kV4/30/2021DISIS STAGE   
GEN-2021-016DISIS-2021-00101 NORTHMcIntoshNDBEPC4/1/202512/1/2025  250252252ER/NRWindTap Leland Olds – Groton 345 kV4/30/2021DISIS STAGE   
GEN-2021-017DISIS-2021-00101 NORTHMcIntoshNDBEPC4/1/202512/1/2025  74.991.291.2ER/NRBattery/StorageTap Leland Olds – Groton 345 kV4/30/2021DISIS STAGE   
GEN-2021-018DISIS-2021-00104 SOUTHEASTNobleOKOGE4/1/202712/1/2027  231273.6273.6ER/NRBattery/StorageSooner 345 kV4/30/2021DISIS STAGE   
GEN-2021-019DISIS-2021-00104 SOUTHEASTNobleOKOGE4/1/202712/1/2027  74.991.291.2ER/NRBattery/StorageSooner 345 kV4/30/2021DISIS STAGE   
GEN-2021-021DISIS-2021-00104 SOUTHEASTLemar and Red RiverTXWFEC9/1/202612/31/2026  450450450ERSolarHugo 138kV Substation4/20/2021DISIS STAGE   
GEN-2021-022DISIS-2021-00104 SOUTHEASTMuskogeeOKAEP9/1/202612/31/2026  470470470ERSolarNortheastern 345kV Substation4/20/2021DISIS STAGE   
GEN-2021-023DISIS-2021-00103 CENTRALSumnerKSWERE7/31/202312/31/2023  306.18306.18306.18ER/NRSolarSumner 138kV5/14/2021DISIS STAGE   
GEN-2021-024DISIS-2021-00101 NORTHLaMoureNDWAPA7/31/202312/31/2023  203.04203.04203.04ER/NRWindWAPA 230kV Jamestown Substation5/14/2021DISIS STAGE   
GEN-2021-025DISIS-2021-00104 SOUTHEASTWoodwardOKWFEC7/31/20237/31/2023  203.04203.04203.04ER/NRWindWestern Farmers 161kV Mooreland Substation5/14/2021DISIS STAGE   
GEN-2021-026DISIS-2021-00103 CENTRALNewtonMOSWPA7/31/202312/31/2023  204.12204.12204.12ER/NRSolarTap SWPA 161kV Springfield to La Russel Transmission Line5/14/2021DISIS STAGE   
GEN-2021-027DISIS-2021-00102 NEBRASKAGageNENPPD7/31/202312/31/2023  102.06102.06102.06ER/NRSolarNPPD 161kV Sheldon Substation5/14/2021DISIS STAGE   
GEN-2021-028DISIS-2021-00104 SOUTHEASTWoodwardOKWFEC7/31/202312/31/2023  204.12204.12204.12ER/NRSolarWestern Farmers 161 Mooreland Substation5/14/2021DISIS STAGE   
GEN-2021-029DISIS-2021-00103 CENTRALLinn KS and Bates MOKSKCPL7/31/202312/31/2023  253.2253.8253.8ER/NRBattery/StorageEvergy 345kV La Cygne Substation5/14/2021DISIS STAGE   
GEN-2021-030DISIS-2021-00103 CENTRALLinn KS and Bates MOKSKCPL7/31/202312/31/2023  510.3510.3510.3ER/NRSolarEvergy 345kV La Cygne Substation5/14/2021DISIS STAGE   
GEN-2021-031DISIS-2021-00104 SOUTHEASTChoctawOKWFEC7/31/202312/31/2023  201.6201.6201.6ER/NRBattery/StorageWestern Farmers 345kV Hugo Substation5/14/2021DISIS STAGE   
GEN-2021-032DISIS-2021-00104 SOUTHEASTChoctawOKWFEC7/31/202312/31/2023  255.15255.15255.15ER/NRSolarWestern Farmers 345kV Hugo Substation5/14/2021DISIS STAGE   
GEN-2021-033DISIS-2021-00104 SOUTHEASTFranklinAROGE7/31/202312/31/2023  204.12204.12204.12ER/NRSolar161kV Branch substation5/14/2021DISIS STAGE   
GEN-2021-034DISIS-2021-00102 NEBRASKADawsonNENPPD7/31/202312/31/2023  113113113ER/NRSolarNPPD 230KV Canaday Substation5/13/2021DISIS STAGE   
GEN-2021-035DISIS-2021-00103 CENTRALGrantKSSUNC7/31/202312/31/2023  113113113ER/NRSolarTap Sunflower Santana 161kV Transmission Line5/14/2021DISIS STAGE   
GEN-2021-036DISIS-2021-00104 SOUTHEASTLittle RiverARSUNC7/31/202312/31/2023  204.12204.12204.12ER/NRSolarTap Southwestern Electric Power Co. Craig to Patterson Transmission Line5/14/2021DISIS STAGE   
GEN-2021-037DISIS-2021-00102 NEBRASKASalineNENPPD7/31/202312/31/2023  244.22244.22244.22ER/NRSolarNPPD 161kV Sheldon Substation5/14/2021DISIS STAGE   
GEN-2021-038DISIS-2021-00104 SOUTHEASTTitusTXAEP3/31/20246/1/2024  200201.32201.32ER/NRBattery/StorageWelsh 345kV Substation4/30/2021DISIS STAGE   
GEN-2021-039DISIS-2021-00102 NEBRASKACassNEOPPD3/31/20236/1/2023  100200200ER/NRBattery/StorageOPPD District, North Omaha Power Plant Substation, 161kV Bus (1211 Substation)4/30/2021DISIS STAGE   
GEN-2021-040DISIS-2021-00102 NEBRASKACassNEOPPD3/31/20246/1/2024  200400400ER/NRBattery/StorageOPPD District, Cass County Power Plant Substation, 345kV Bus4/30/2021DISIS STAGE   
GEN-2021-041DISIS-2021-00104 SOUTHEASTCanadianOKOGE3/31/20246/1/2024  100100.657100.657ER/NRBattery/StorageMustang 138kV Substation4/30/2021DISIS STAGE   
GEN-2021-042DISIS-2021-00103 CENTRALJackson MOINDN3/31/20236/1/2023  50100100ER/NRBattery/StorageIndependence Power & Light, Blue Valley Substation, 161kV Bus4/30/2021DISIS STAGE   
GEN-2021-043DISIS-2021-00102 NEBRASKALancasterNEOPPD3/31/20246/1/2024  250250250ER/NRBattery/Storage8000 SW 12th (Rokeby) Station, 115kV Bus4/30/2021DISIS STAGE   
GEN-2021-044DISIS-2021-00102 NEBRASKADundyNENPPD7/1/202512/31/2025  300303303ER/NRWindNebraska Public Power District's (NPPD) 345 kV Red Willow substation4/28/2021DISIS STAGE   
GEN-2021-045DISIS-2021-00103 CENTRALSherman, WallaceKSSUNC7/1/202512/31/2025  300303303ER/NRWindSunflower Electric Power Corp's 345 kV Mingo substation4/28/2021DISIS STAGE   
GEN-2021-046DISIS-2021-00103 CENTRALProwers, KiowaCOSPS7/1/202512/31/2025  400406.02406.02ER/NRWindTap 345 kV line between Lamar and Finney4/28/2021DISIS STAGE   
GEN-2021-047DISIS-2021-00104 SOUTHEASTMayesOKGRDA3/1/202610/1/2026  250250250ERSolarTulsa North - Grand River Energy Center Tap 345 kV Line4/29/2021DISIS STAGE   
GEN-2021-048DISIS-2021-00102 NEBRASKALancasterNELES7/31/202512/31/2025  757575ER/NRBattery/StorageWagener 115kV Substation4/30/2021DISIS STAGE   
GEN-2021-049DISIS-2021-00102 NEBRASKALancasterNELES7/31/202512/31/2025  250250250ER/NRSolarWagener 115kV Substation4/30/2021DISIS STAGE   
GEN-2021-050DISIS-2021-00103 CENTRALHenryMOKCPL7/31/202512/31/2025  200200200ER/NRSolar161kV Stilwell-Clinton Line4/30/2021DISIS STAGE   
GEN-2021-051DISIS-2021-00103 CENTRALHenryMOKCPL7/31/202512/31/2025  757575ER/NRBattery/Storage161kV Stilwell-Clinton Line4/30/2021DISIS STAGE   
GEN-2021-052DISIS-2021-00104 SOUTHEASTMuskogeeOKOGE 12/31/2025  757575ERBattery/StoragePecan Creek 345kV substation4/29/2021DISIS STAGE   
GEN-2021-053DISIS-2021-00104 SOUTHEASTRed RiverTXAEP 12/31/2027  500500500ERSolarWelsh 345kV Substation4/29/2021DISIS STAGE   
GEN-2021-054DISIS-2021-00104 SOUTHEASTRed RiverTXAEP 12/31/2027  250250250ERSolarWelsh 345kV Substation4/29/2021DISIS STAGE   
GEN-2021-055DISIS-2021-00104 SOUTHEASTRed RiverTXAEP 12/31/2027  250250250ERSolarWelsh 345kV Substation4/29/2021DISIS STAGE   
GEN-2021-056DISIS-2021-00104 SOUTHEASTTexas CountyTXAEP 12/31/2027  100010001000ERWindWelsh 345kV Substation4/29/2021DISIS STAGE   
GEN-2021-057DISIS-2021-00102 NEBRASKAAntelopeNENPPD 12/31/2027  300300300ERWindAntelope 345kV substation4/29/2021DISIS STAGE   
GEN-2021-058DISIS-2021-00101 NORTHMadisonNENPPD 12/31/2027  300300300ERWindHolt 345kV substation4/29/2021DISIS STAGE   
GEN-2021-059DISIS-2021-00103 CENTRALNemahaKSWERE 4/30/2021  400400400ERWindKelley 161 kV substation4/29/2021DISIS STAGE   
GEN-2021-060DISIS-2021-00103 CENTRALBarberKSWERE 12/31/2026  300300300ERSolarPony Meadows 138 kV substation4/29/2021DISIS STAGE   
GEN-2021-061DISIS-2021-00102 NEBRASKAJohnson and Gage KSNPPD 12/31/2027  100100100ERWindBeatrice 115 kV substation4/29/2021DISIS STAGE   
GEN-2021-062DISIS-2021-00102 NEBRASKALincoln NENPPD 12/31/2026  108110110ERSolarCanaday 230 kV Substation4/29/2021DISIS STAGE   
GEN-2021-063DISIS-2021-00104 SOUTHEASTMcCurtainOKAEP2/15/20256/1/2025  200200200ER/NRHybridSolarCraig JCT 138kV4/28/2021DISIS STAGE   
GEN-2021-064DISIS-2021-00104 SOUTHEASTCaddoOKAEP2/15/20256/1/2025  100100100ER/NRHybridSolarCarnegie South 138kV4/28/2021DISIS STAGE   
GEN-2021-065DISIS-2021-00104 SOUTHEASTPittsburgOKAEP2/15/20256/1/2025  200200200ER/NRHybridSolarTalawanda to C-River 138kV4/28/2021DISIS STAGE   
GEN-2021-066DISIS-2021-00104 SOUTHEASTPittsburgOKWFEC2/15/20256/1/2025  150150150ER/NRHybridSolarMcAlester WFEC 138 kV4/28/2021DISIS STAGE   
GEN-2021-067DISIS-2021-00104 SOUTHEASTDelawareOKAEP2/15/20256/1/2025  100100100ER/NRHybridSolarTap Grove - Jay 138kV4/28/2021DISIS STAGE   
GEN-2021-068DISIS-2021-00103 CENTRALHodgeman and FordKSSUNC9/1/202512/1/2025  249.6249.6249.6ERWindSUNC Spearville - Holcomb 345kV4/26/2021DISIS STAGE   
GEN-2021-069DISIS-2021-00103 CENTRALHodgeman and FordKSSUNC8/1/202711/1/2027  249.6249.6249.6ERWindSUNC Spearville - Holcomb 345kV4/26/2021DISIS STAGE   
GEN-2021-070DISIS-2021-00103 CENTRALHodgeman and FordKSSUNC8/1/202711/1/2027  504504504ERWindSUNC Spearville - Holcomb 345kV4/26/2021DISIS STAGE   
GEN-2021-071DISIS-2021-00104 SOUTHEASTNobleOKOGE9/1/202512/1/2025  403.2403.2403.2ERWindOKGE Spring Creek – Sooner 345kV4/26/2021DISIS STAGE   
GEN-2021-072DISIS-2021-00101 NORTHMercerNDBEPC6/1/202412/1/2024  600600600ER/NRSolar345kV Transmission Line from Antelope Valley to Leland Olds Substation5/19/2021DISIS STAGE   
GEN-2021-073DISIS-2021-00102 NEBRASKALincolnNENPPD6/1/202412/1/2024  240240240ER/NRSolar345 kV BUS at Gerald Gentleman Substation5/19/2021DISIS STAGE   
GEN-2021-074DISIS-2021-00103 CENTRALProwersCOSPS9/1/202512/31/2025  500500500ER/NRSolarFinney - Lamar 345 kV5/19/2021DISIS STAGE   
GEN-2021-075DISIS-2021-00103 CENTRALProwersCOSPS9/1/202512/31/2025  300300300ER/NRWindFinney - Lamar 345 kV5/19/2021DISIS STAGE   
GEN-2021-076DISIS-2021-00103 CENTRALEllisKSMIDW7/31/202312/31/2023  113113113ER/NRSolarMidwest Energy 161kV Post Rock Substation5/13/2021DISIS STAGE   
GEN-2021-077DISIS-2021-00103 CENTRALPettisMOGMO7/1/20258/1/2025  150150150ERSolarWindsor to AEC Sedalia 161 kV4/30/2021DISIS STAGE   
GEN-2021-078DISIS-2021-00103 CENTRALFinneyKSSUNC10/15/202712/31/2027  160160160ER/NRHybridSolarPierceville – Plymell 115kV4/29/2021DISIS STAGE   
GEN-2021-079DISIS-2021-00104 SOUTHEASTDelaware (OK) / Benton (AR)OKAEP7/31/20238/31/2023  140140140ER/NRSolarFlint Creek to Tonnece 345 kV4/30/2021DISIS STAGE   
GEN-2021-080DISIS-2021-00105 SOUTHWESTLeaNMSPS7/1/20249/1/2024  100100100ER/NRSolarSPP / Lea County Electric Cooperative (LE) 69 kV4/26/2021DISIS STAGE   
GEN-2021-081DISIS-2021-00105 SOUTHWESTLeaNMSPS4/1/20246/1/2024  555555ER/NRSolarSPP / Lea County Electric Cooperative (LE) 69 kV transmission line4/26/2021DISIS STAGE   
GEN-2021-082DISIS-2021-00105 SOUTHWESTLeaNMSPS7/1/20249/1/2024  808080ER/NRSolarLE 69 kV Lewis substation4/23/2021DISIS STAGE   
GEN-2021-083DISIS-2021-00105 SOUTHWESTChavesNMSPS7/1/20249/1/2024  100100100ER/NRSolarSPP / Central Valley Electric Cooperative (CV) 69 kV transmission line4/26/2021DISIS STAGE   
GEN-2021-084DISIS-2021-00103 CENTRALKearneyKSSUNC10/15/202712/31/2027  200200200ER/NRHybridSolarWilliamson - Fletcher 115kV4/29/2021DISIS STAGE   
GEN-2021-085DISIS-2021-00103 CENTRALFordKSSUNC12/15/202712/31/2027  200200200ER/NRHybridSolarCrooked Creek - Fort Dodge 115kV4/29/2021DISIS STAGE   
GEN-2021-086DISIS-2021-00104 SOUTHEASTHowardARAEP10/15/202712/31/2027  165165165ER/NRHybridSolarOkay - Turk 138kV4/29/2021DISIS STAGE   
GEN-2021-087DISIS-2021-00103 CENTRALSewardKSSUNC10/15/202712/31/2027  185185185ER/NRHybridSolarWalkemeyer - North Cimarron 115kV4/29/2021DISIS STAGE   
GEN-2021-088DISIS-2021-00104 SOUTHEASTClevelandOKWFEC9/23/202412/24/2024  100100100ER/NRBattery/Storage138 kV Canadian SW Substation4/29/2021DISIS STAGE   
GEN-2021-090DISIS-2021-00105 SOUTHWESTYoakumTXSPS6/15/20227/15/2022  400400400ER/NRSolarYoakum 345kV Substation4/30/2021DISIS STAGE   
GEN-2021-091DISIS-2021-00104 SOUTHEASTPontotocOKOGE10/1/202512/31/2025  150150150ER/NRHybridSolarOG&E's Blue River 138kV Substation4/29/2021DISIS STAGE   
GEN-2021-092DISIS-2021-00105 SOUTHWESTHansfordTXSPS1/15/20263/15/2026  100100100ER/NRBattery/StorageXcel Hansford 115kV substation4/30/2021DISIS STAGE   
GEN-2021-093DISIS-2021-00104 SOUTHEASTOklahoma OKOGE6/1/20236/1/2025  109109132ER/NRThermalGas TurbineTinker4/30/2021DISIS STAGE   
GEN-2021-094DISIS-2021-00101 NORTHMercerNDBEPC8/1/20244/1/2025  446.5446.5446.5ERThermalCombustion TurbineAVS 345kV Substation4/30/2021DISIS STAGE   
GEN-2021-095DISIS-2021-00101 NORTHMercerNDBEPC8/1/20254/1/2026  446.5446.5446.5ERThermalCombustion TurbineAVS 345kV substation4/30/2021DISIS STAGE   
GEN-2021-096DISIS-2021-00103 CENTRALCoffeyKSWERE11/1/20235/1/2024  503.5503.5503.5ER/NRSolarWolf Creek - Benton 345 kV4/29/2021DISIS STAGE   
GEN-2021-097DISIS-2021-00105 SOUTHWESTElida NMSPS11/1/202512/21/2025  300300300ER/NRWindHisel 230 kV Substation5/24/2021DISIS STAGE   
GEN-2021-098DISIS-2021-00104 SOUTHEASTDeweyOKOGE11/1/202512/31/2025  300300300ER/NRWindDewey District 138 kV Substation5/24/2021DISIS STAGE   
GEN-2021-099DISIS-2021-00104 SOUTHEASTEllisOKNPPD11/1/20241/1/2025  250260.4260.4ER/NRWindBobcat 345 kV4/30/2021DISIS STAGE   
GEN-2021-100DISIS-2021-00101 NORTHMercerNDBEPC9/15/202612/1/2026  505050ER/NRBattery/StorageLine side tap using single breaker on Beulah to Center 42kV Feeder5/24/2021DISIS STAGE   
GEN-2021-101DISIS-2021-00103 CENTRALDouglasKSWERE8/1/20259/1/2025  159159159ER/NRSolarPOI is Evergy's Midland Station Northeast of Lawrence, KS5/25/2021DISIS STAGE   
GEN-2021-102DISIS-2021-00103 CENTRALDouglasKSWERE8/1/20259/1/2025  808080ER/NRBattery/StorageEvergy's Midland Substation 115kV bus5/25/2021DISIS STAGE   
GEN-2021-103DISIS-2021-00103 CENTRALJohnsonKSWERE8/1/20259/1/2025  150150150ER/NRBattery/StorageEvergy's Waverly Substation 115kV bus5/25/2021DISIS STAGE   
GEN-2021-104DISIS-2021-00104 SOUTHEASTBossierLAAEP9/5/202612/1/2026  100100100ER/NRSolarDirect Injection at 138kV buss at Red Point Substation5/26/2021DISIS STAGE   
GEN-2021-105DISIS-2021-00102 NEBRASKALincolnNENPPD9/5/202612/1/2026  200200200ER/NRSolarLine side tap using three breaker ring bus on 230kV Feeder from Gerald Gentleman to North Platte5/26/2021DISIS STAGE   
GEN-2021-106DISIS-2021-00102 NEBRASKAThayerNENPPD7/31/202312/31/2023  102.06102.06102.06ER/NRSolarNPPD Hebron 115Kv substation5/20/2021DISIS STAGE   
GEN-2021-107DISIS-2021-00103 CENTRALPottawatomieKSWERE7/31/202312/31/2023  201.6201.6201.6ER/NRBattery/StorageEvergy 345kV Jeffrey Energy Center5/20/2021DISIS STAGE   
GEN-2021-108DISIS-2021-00102 NEBRASKACassNEOPPD7/31/202312/31/2023  182.25182.25182.25ER/NRSolarOPPD 345KV Cass County Substation5/20/2021DISIS STAGE   
GEN-2021-SR8Surplus03 CENTRALHarperKSWERE11/1/202311/1/2023  424242ERSolarViola 345kV5/13/2021IA FULLY EXECUTED/ON SCHEDULE   
GEN-2021-SR9SurplusKansas CityMOKCPL 10/5/2022  101010ER/NRSolarHawthorn Power Plant8/24/2021IA FULLY EXECUTED/ON SCHEDULE   
GEN-2022-001DISIS-2022-00104 SOUTHEASTRogersOK9/23/202512/31/2025  100100100ER/NRBattery/StorageLine tap of Catoosa-Elm Creek line approximately 0.75 miles NW of Catoosa substation12/30/2021DISIS STAGE   
GEN-2022-002DISIS-2022-00103 CENTRALFinneyKS6/30/20256/30/2026  150150150NRSolarHolcomb-Setab 345 kV Tap Line5/24/2022DISIS STAGE   
GEN-2022-003DISIS-2022-00103 CENTRALJacksonOK6/30/20256/30/2026  125125125NRSolarRussell 138 kV Substation5/24/2022DISIS STAGE   
GEN-2022-004DISIS-2022-00103 CENTRALSedgwickKS8/1/202510/31/2026  333333NRSolarMurray Gill (MURR) 138 kV Substation (533045 GILL W 4)5/26/2022DISIS STAGE   
GEN-2022-005DISIS-2022-00103 CENTRALLabetteKS4/1/202510/31/2026  200200200NRSolarNE Parsons (NEPA) 138 kV Substation (533005 NEPARSN4)5/25/2022DISIS STAGE   
GEN-2022-006DISIS-2022-00103 CENTRALLabetteKS4/1/202510/31/2026  200200200NRSolarNeosho 161 kV Substation (532937 NEOSHO 5)5/25/2022DISIS STAGE   
GEN-2022-007DISIS-2022-00103 CENTRALLyonKS5/1/202510/31/2026  135135135NRSolarLang 115 kV Substation (533304 LANG 3)5/26/2022DISIS STAGE   
GEN-2022-008DISIS-2022-00105 SOUTHWESTRandallTX1/1/20254/1/2027  150150150ER/NRSolarNichols - Amarillo South 230 kV5/18/2022DISIS STAGE   
GEN-2022-009DISIS-2022-00101 NORTHWilliamsND7/1/20236/1/2025  125125125ERThermalJudson Substation 345 kV5/26/2022DISIS STAGE   
GEN-2022-010DISIS-2022-00101 NORTHWilliamsND7/1/20236/1/2025  250250250ERThermalJudson Substation 345 kV5/26/2022DISIS STAGE   
GEN-2022-011DISIS-2022-00101 NORTHStarkND6/1/202412/31/2025  374374374NRSolar230kV Daglum Substation6/3/2022DISIS STAGE   
GEN-2022-012DISIS-2022-00101 NORTHStarkND6/1/202412/31/2025  100100100NRBattery/Storage230kV Daglum Substation6/8/2022DISIS STAGE   
GEN-2022-013DISIS-2022-00103 CENTRALButlerKS6/1/202412/31/2025  300300300NRSolarTap of Wichita-Lang 345kV line6/8/2022DISIS STAGE   
GEN-2022-014DISIS-2022-00103 CENTRALButlerKS6/1/202412/30/2025  400400400NRHybridSolarTap of Wichita-Lang 345kV line6/8/2022DISIS STAGE   
GEN-2022-015DISIS-2022-00103 CENTRALButlerKS6/1/202412/31/2025  300300300NRSolarTap of Wichita-Lang 345kV line6/8/2022DISIS STAGE   
GEN-2022-016DISIS-2022-00104 SOUTHEASTWoodwardOK6/1/202412/31/2025  288288288NRSolarWoodward 345kV Substation6/8/2022DISIS STAGE   
GEN-2022-017DISIS-2022-00104 SOUTHEASTWoodwardOK6/6/202412/31/2025  150150150NRBattery/StorageWoodward 345kV Substation6/8/2022DISIS STAGE   
GEN-2022-018DISIS-2022-00102 NEBRASKAKnoxNE6/1/202412/31/2025  250250250NRSolarTap of Grand Prairie--Ft Thompson 345kV line6/8/2022DISIS STAGE   
GEN-2022-019DISIS-2022-00102 NEBRASKAKnoxNE6/1/202412/31/2025  100100100NRBattery/StorageTap of Grand Prairie--Ft Thompson 345kV line6/8/2022DISIS STAGE   
GEN-2022-020DISIS-2022-00101 NORTHWalworthSD6/1/202412/31/2025  355355355NRSolarTap of Ft Thompson--Leland 345kV line6/8/2022DISIS STAGE   
GEN-2022-021DISIS-2022-00101 NORTHWalworthSD6/1/202412/31/2025  100100100NRBattery/StorageTap of Ft Thompson--Leland 345kV line6/8/2022DISIS STAGE   
GEN-2022-022DISIS-2022-00105 SOUTHWESTChavezNM6/1/202412/31/2025  300300300NRSolarSan Juan Tap 230kv substation6/8/2022DISIS STAGE   
GEN-2022-023DISIS-2022-00105 SOUTHWESTChavezNM6/1/202412/31/2025  175175175NRBattery/StorageSan Juan Tap 230kv substation6/8/2022DISIS STAGE   
GEN-2022-024DISIS-2022-00103 CENTRALDecaturKS6/1/202412/31/2025  200200200NRBattery/StorageTap of Mingo--Red Willow 345kV line6/10/2022DISIS STAGE   
GEN-2022-025DISIS-2022-00103 CENTRALDecaturKS6/1/202412/31/2025  200200200NRSolarTap of Mingo--Red Willow 345kV line6/8/2022DISIS STAGE   
GEN-2022-026DISIS-2022-00103 CENTRALDecaturKS6/1/202412/31/2025  200200200NRSolarTap of Mingo--Red Willow 345kV line6/8/2022DISIS STAGE   
GEN-2022-027DISIS-2022-00105 SOUTHWESTCochranTX1/1/20254/4/2027  555555ER/NRBattery/StorageLehman 115 kV Substation6/13/2022DISIS STAGE   
GEN-2022-028DISIS-2022-00102 NEBRASKACheyenneNE1/1/20254/1/2027  125125125ER/NRSolarSidney - Stegall 230 kV6/13/2022DISIS STAGE   
GEN-2022-029DISIS-2022-00105 SOUTHWESTLeaNMSPS10/1/202712/1/2027  250250250NRHybridSolar/BatteryTap of Hobbs - Kiowa 345 kV Transmission Line 6/10/2022DISIS STAGE   
GEN-2022-030DISIS-2022-00105 SOUTHWESTLeaNMSPS10/1/202712/1/2027  250250250NRHybridSolar/BatteryTap of Hobbs - Kiowa 345 kV Transmission Line6/10/2022DISIS STAGE   
GEN-2022-031DISIS-2022-00103 CENTRALJackson CountyMOGMO9/30/20256/30/2026  100100100ER/NRBattery/StorageDuncan Road 161 kV Substation6/22/2022DISIS STAGE   
GEN-2022-032DISIS-2022-00102 NEBRASKAKimballNE1/1/20254/1/2027  155155155ER/NRSolarLaramie-Sidney 345 kV6/22/2022DISIS STAGE   
GEN-2022-033DISIS-2022-00105 SOUTHWESTChavesNM11/15/202512/1/2025  200200200ER/NRHybridSolar/StorageNorth Eddy - Chaves 230kV line6/23/2022DISIS STAGE   
GEN-2022-034DISIS-2022-00101 NORTHUnionSDWAPA4/1/202512/31/2025  300300300ER/NRWindSpring Mound Station6/23/2022DISIS STAGE   
GEN-2022-035DISIS-2022-00105 SOUTHWESTLambTXSWPA4/1/202512/31/2025  300300300ER/NRWindTolk 345 kV Substation6/23/2022DISIS STAGE   
GEN-2022-036DISIS-2022-00105 SOUTHWESTLambTXSWPA4/1/202512/31/2025  100010001000ER/NRSolarTolk 345 kV Substation6/23/2022DISIS STAGE   
GEN-2022-037DISIS-2022-00101 NORTHBurkeNDBEPC4/1/202512/31/2025  181181181WindPioneer 115 kV Substation6/23/2022DISIS STAGE   
GEN-2022-038DISIS-2022-00105 SOUTHWESTHarrisonTXSWPA4/1/202512/31/2025  200200200ER/NRSolarLongwood to Marshall 138 kV line6/23/2022DISIS STAGE   
GEN-2022-039DISIS-2022-00102 NEBRASKAGageNENPPD4/1/202512/31/2025  185185185ER/NRWindSteele City 115 kV Substation6/23/2022DISIS STAGE   
GEN-2022-040DISIS-2022-00104 SOUTHEASTStephensOKWFEC4/1/202512/31/2025  250250250ER/NRSolarComanche Switching Station 6/23/2022DISIS STAGE   
GEN-2022-041DISIS-2022-00103 CENTRALCowleyKS4/1/202512/31/2025  100100100ER/NRSolarTie Substation 69 kV6/29/2022DISIS STAGE   
GEN-2022-042DISIS-2022-00104 SOUTHEASTCarterOKOGE4/1/202512/31/2025  174174174ER/NRSolarSunnyside to Pooleville 138 kV line6/23/2022DISIS STAGE   
GEN-2022-043DISIS-2022-00104 SOUTHEASTBriscoeTXSPS4/1/202512/31/2025  200200200ER/NRSolarTule Canyon (Silverton) 345kV Substation6/23/2022DISIS STAGE   
GEN-2022-044DISIS-2022-00102 NEBRASKAWayne and PierceNENPPD4/1/202512/31/2025  808080ER/NRBattery/StorageHoskins 345 kV6/23/2022DISIS STAGE   
GEN-2022-045DISIS-2022-00103 CENTRALLittle RiverARAEP4/1/202512/31/2025  200200200ER/NRBattery/StorageSouth Foreman6/23/2022DISIS STAGE   
GEN-2022-046DISIS-2022-00102 NEBRASKAWebster and FranklinNEITCGP4/1/202512/31/2025  150150150ER/NRBattery/StorageAxtell to Post Rock 345 kV Line Tap6/23/2022DISIS STAGE   
GEN-2022-047DISIS-2022-00103 CENTRALLittle RiverARAEP4/1/202512/31/2025  200200200ER/NRSolarSouth Foreman6/23/2022DISIS STAGE   
GEN-2022-048DISIS-2022-00104 SOUTHEASTWoodwardOKWFEC4/1/202512/31/2025  250250250ER/NRWindMooreland 138 kV6/23/2022DISIS STAGE   
GEN-2022-049DISIS-2022-00103 CENTRALFranklinARAEP4/1/202512/31/2025  150150150ER/NRBattery/StorageGrand Prairie 138 kV Tap6/23/2022DISIS STAGE   
GEN-2022-050DISIS-2022-00102 NEBRASKADawson and BuffaloNENPPD4/1/202512/31/2025  272272272ER/NRWindCrooked Creek 230 kV6/23/2022DISIS STAGE   
GEN-2022-051DISIS-2022-00104 SOUTHEASTBossierLAAEP4/1/202512/31/2025  325325325ER/NRBattery/StorageLongwood to Sarepta 345 kV Line Tap6/23/2022DISIS STAGE   
GEN-2022-052DISIS-2022-00104 SOUTHEASTBossierLAAEP4/1/202512/31/2025  850850850ER/NRSolarLongwood to Sarepta 345 kV Line Tap6/23/2022DISIS STAGE   
GEN-2022-053DISIS-2022-00103 CENTRALBartonMOWERE4/1/202512/31/2025  137.5137.5137.5ER/NRSolarWolf Creek-Blackberry 345 kV6/23/2022DISIS STAGE   
GEN-2022-054DISIS-2022-00104 SOUTHEASTStephensOKAEP4/1/202512/31/2025  200200200ER/NRSolarLawton to Sunnyside 345 kV6/23/2022DISIS STAGE   
GEN-2022-055DISIS-2022-00104 SOUTHEASTGradyOKWFEC4/1/202512/31/2025  200200200ER/NRSolarSunshine North to Anadarko 138 kV6/23/2022DISIS STAGE   
GEN-2022-056DISIS-2022-00105 SOUTHWESTLambTXSWPA4/1/202512/31/2025  300300300ER/NRSolarPlant X 230kV Substation6/23/2022DISIS STAGE   
GEN-2022-057DISIS-2022-00102 NEBRASKATri-State4/1/202512/31/2025  878787ER/NRSolarElsie Tap 115 kV6/23/2022DISIS STAGE   
GEN-2022-058DISIS-2022-00103 CENTRALBentonAREDE4/1/202512/31/2025  180180180ER/NRSolarNoel Southwest (Sub 435) Decatur 161 kV6/23/2022DISIS STAGE   
GEN-2022-059DISIS-2022-00103 CENTRALStevensKSSWPA4/1/202512/31/2025  500500500ER/NRWindCarpenter 345 kV6/23/2022DISIS STAGE   
GEN-2022-060DISIS-2022-00104 SOUTHEASTOsageOK12/31/20264/1/2027  555555ER/NRBattery/StorageHwy 20 138 kV Substation6/23/2022DISIS STAGE   
GEN-2022-061DISIS-2022-00102 NEBRASKAScotts BluffNEWAPA1/1/20254/1/2027  180180180ER/NRSolarStegall - Victory Hill 230kV7/18/2022DISIS STAGE   
GEN-2022-062DISIS-2022-00103 CENTRALBourbonKSWERE4/1/202512/31/2025  200200200ER/NRSolarWolf Creek- Blackberry 345 kV7/8/2022DISIS STAGE   
GEN-2022-063DISIS-2022-00105 SOUTHWESTHutchinsonTX6/1/202512/31/2025  350350350NRSolarPringle 230-115 kV Substation7/13/2022DISIS STAGE   
GEN-2022-064DISIS-2022-00104 SOUTHEASTMajorOKWFEC1/1/20254/1/2027  808080ER/NRBattery/StorageClearville 138 kV Substation7/22/2022DISIS STAGE   
GEN-2022-065DISIS-2022-00103 CENTRALEdwardsKSMKEC9/4/202711/19/2027  145145145NRSolartap on Arthur Mullergreen-Spearville 230 kV line7/25/2022DISIS STAGE   
GEN-2022-066DISIS-2022-00101 NORTHPerkinsSDWAPA12/31/20264/1/2027  150150150ER/NRSolarBison - Maurine 230 kV Substation8/5/2022DISIS STAGE   
GEN-2022-067DISIS-2022-00101 NORTHMeadeSDWAPA12/31/20264/1/2027  150150150ER/NRSolarFaith - Maurine 115 kV Substation8/5/2022DISIS STAGE   
GEN-2022-068DISIS-2022-00101 NORTHHydeSD7/1/202611/1/2026  250250250ER/NRWindChappelle Creek 345 kV8/11/2022DISIS STAGE   
GEN-2022-069DISIS-2022-00101 NORTHHydeSD7/1/202711/1/2026  250250250ER/NRWindChappelle Creek 345 kV8/11/2022DISIS STAGE   
GEN-2022-070DISIS-2022-00101 NORTHHydeSD7/1/202611/1/2026  250250250ER/NRWindChappelle Creek 345 kV8/11/2022DISIS STAGE   
GEN-2022-SR1Surplus01 NORTHBurkeNDBEPC11/30/2022   104.4104.4104.4ERBattery/StorageTande 345 kV Substation3/2/2022None   
GEN-2022-SR2Surplus    100.8100.8100.8ERBattery/StorageHoskins 345 kV Substation3/21/2022None   
GEN-2022-SR3Surplus    100.24100.24100.24ERSolarHoskins 345 kV Substation3/29/2022None   
GEN-2022-SR4Surplus    858585ERBattery/StorageMinco 345 kV Substation5/23/2022None   
GEN-2022-SR5SurplusSeilingOK 12/31/2022  858585ERBattery/StorageTatonga 345 kV Substation5/24/2022None   
GEN-2022-SR6SurplusBlackwellOK 12/31/2022  505050ERBattery/StorageNardin 69 kV Substation5/24/2022None   

Download data as CSV