OASIS Apps

- Curtailment Viewer
- DC Tie Viewer
- Price Discounts
- Price Matrix
- Transmission Load Relief

- SPP OASIS Archive Map
    > SPP OASIS Archive Page
    > Market System Status
    > Member Related Postings
    > FERC890 Items

- Studies Postings
 

GI Active Requests

Last Updated: 12/11/2024    Download data as CSV

Generation Interconnection NumberIFS Queue NumberCurrent ClusterCluster GroupNearest Town or CountyStateTO at POIIn-Service Date (proposed) Commercial Operation DateCessation DateReplacement Generator Commercial Op. DateCapacity (MW)MAX Summer MWMAX Winter MWService TypeGeneration TypeFuel Type Substation or LineRequest ReceivedDate WithdrawnStatusCause of DelayAssociated StudiesFacility ReportExecuted GIA
GEN-2024-SR9Surplus05 SOUTHWESTBeaver CountyOKOG&E 1/1/2027  150150150ERBattery/StorageBeaver County Substation 345 kV1/26/2024 None   
GEN-2024-SR8Surplus02 NEBRASKAGreely CountyNENPPD 12/31/2026  707070ERBattery/StorageSpalding to North Loup 115kV4/3/2024 FACILITY STUDY STAGE   
GEN-2024-SR7Surplus05 SOUTHWESTBeaver CountyOKOG&E 6/1/2027  200200200ERSolarBeaver County Substation 345 kV1/26/2024 None   
GEN-2024-SR6Surplus04 SOUTHEASTJohnston CountyOKOG&E    200200200ERBattery/StorageInterconnecting at Hugo - Sunnyside 345 kV transmission line2/20/2024 None   
GEN-2024-SR5Surplus04 SOUTHEASTDrumrightOKOG&E 6/1/2025  176.9176.9176.9ERBattery/Storage138 kV Greenwood Station2/7/2024 IA PENDING   
GEN-2024-SR3Surplus04 SOUTHEASTLincoln CountyOKOG&E 5/1/2026  72.572.572.5ER/NRBattery/Storage138 kV TRYON 3 (Bus # 5156752/1/2024 IA PENDING   
GEN-2024-SR2Surplus04 SOUTHEASTFranklin CountyAROG&E 6/1/2026  72.572.572.5ER/NRBattery/Storage161 kV BRANCH 5 (Bus # 515316)2/6/2024 IA PENDING   
GEN-2024-SR15Surplus05 SOUTHWESTYoakumTXSPS 5/1/2026  300300300ERBattery/StorageMahoney 230kV Substation10/24/2024 None   
GEN-2024-SR14Surplus05 SOUTHWESTLea CountyNMXcel/SPS 4/1/2026  363636ERBattery/StorageCunningham 115kV7/8/2024 None   
GEN-2024-SR13Surplus04 SOUTHEASTBryan CountyOKOG&E 6/1/2026  52.252.252.2ER/NRBattery/StorageBrown 138kV Substation5/1/2024 None   
GEN-2024-SR12Surplus01 NORTHLa Moure CountyNDWAPA 10/1/2026  202020ERBattery/StorageEdgeley 115 kV Substation5/21/2024 None   
GEN-2024-SR11Surplus04 SOUTHEASTGarfieldOKOGE 12/31/2025  200200200ER/NRBattery/StorageWoodring 345kV Substation5/7/2024 IA PENDING   
GEN-2024-SR10Surplus02 NEBRASKALancasterNENPPD 12/31/2026  808080ER/NRBattery/StorageMonolith 115kV4/22/2024 FACILITY STUDY STAGE   
GEN-2024-SR1Surplus04 SOUTHEASTChouteauOKGRDA 12/31/2025  848484ERSolar345 kV bus of GRDA GREC 1 & 2 Substation11/29/2023 None   
GEN-2024-GR6Replacement04 SOUTHEASTNewkirkOKOG&E  12/1/20265/1/2027300300300ERWindOpen Sky 345kV Substation7/25/2024 None   
GEN-2024-GR5Replacement04 SOUTHEASTChouteauOKGRDA  10/1/20266/1/2027582542582ERHybridGREC #2 Interconnect Substation – 345kV8/2/2024 None   
GEN-2024-GR4Replacement03 CENTRALRivertonKSEDE  3/15/20266/30/2026313131ERThermalRiverton 4527/25/2024 None   
GEN-2024-GR3Replacement05 SOUTHWESTLea CountyNMXcel/SPS  4/1/20274/1/2027196196196ERSolar230kV Cunningham Substation6/7/2024 None   
GEN-2024-GR1Replacement04 SOUTHEASTHarrahOKOG&E 12/31/202612/31/2026 492492492ERThermalCTGHorseshoe Lake 138kV1/8/2024 None   
GEN-2024-013DISIS-2024-00104 SOUTHEASTMcClainOKOG&E4/1/20291/1/2030  495.6474.4495.6ER/NRThermalCTNorman Hills 345 kV8/2/2024 DISIS STAGE   
GEN-2024-012DISIS-2024-00104 SOUTHEASTOklahoma OKOG&E4/1/20281/1/2029  495.6474.4495.6ER/NRThermalGasHorseshoe Lake 138 kV8/2/2024 DISIS STAGE   
GEN-2024-011DISIS-2024-00105 SOUTHWESTLeaNMWFEC2/1/202612/29/2026  150150150ER/NRSolarLea County 115 kV Substation12/29/2023 DISIS STAGE   
GEN-2024-010DISIS-2024-00105 SOUTHWESTLeaNMSPS2/1/202612/28/2026  150150150ER/NRSolarCunningham 230 kV Substation12/29/2023 DISIS STAGE   
GEN-2024-009DISIS-2024-00105 SOUTHWESTLeaNMSPS2/26/202612/30/2026  150150150ER/NRSolarHobbs 230 kV Substation1/2/2024 DISIS STAGE   
GEN-2024-008DISIS-2024-00105 SOUTHWESTLeaNMSPS2/1/202612/28/2026  150150150ER/NRSolarWard 115 kV Substation12/29/2023 DISIS STAGE   
GEN-2024-007DISIS-2024-00103 CENTRALStafford KSEvergy1/30/202812/31/2028  808080ER/NRHybridSolar/StorageSeward 115 kV Substation4/30/2024 DISIS STAGE   
GEN-2024-006DISIS-2024-00104 SOUTHEASTLawrenceARSWPA10/1/20262/1/2028  100100100ER/NRSolarJonesboro - Water Valley 161 kV 4/25/2024 DISIS STAGE   
GEN-2024-005DISIS-2024-00103 CENTRALAndrew and NodawayMOEvergy11/1/20263/1/2028  150150150ER/NRSolarMidway - Avenue City 161 kV 4/25/2024 DISIS STAGE   
GEN-2024-003DISIS-2024-00104 SOUTHEASTFranklinARAECC9/12/202511/7/2025  102.2102.2102.2ERThermalCTFitzhugh 161kV4/25/2024 DISIS STAGE   
GEN-2024-002DISIS-2024-00105 SOUTHWESTRooseveltNMSPS5/27/20299/30/2029  909090ER/NRSolarRoosevelt - Portales 115 kV Line2/2/2024 DISIS STAGE   
GEN-2024-001DISIS-2024-00105 SOUTHWESTCurryNMSPS5/27/20299/30/2029  100100100ER/NRSolarCurry County 115 kV Substation2/2/2024 DISIS STAGE   
GEN-2023-SR9Surplus05 SOUTHWESTLorenzoTXXcel 6/1/2026  505050ERBattery/StorageTap Floyd County Interchange and Crosby County Interchange 115kV Line2/13/2023 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-SR8Surplus05 SOUTHWESTGruverTXXcel 6/1/2026  200200200ERBattery/StorageHitchland 345 kV Substation2/13/2023 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-SR7Surplus02 NEBRASKAWayne CoNENPPD 12/31/2024  135135135ERBattery/StorageHoskins 345 kV Substation12/16/2022 FACILITY STUDY STAGE   
GEN-2023-SR5Surplus04 SOUTHEASTSeilingOKOGE 6/1/2026  858585ERBattery/StorageTatonga 345 kV Substation12/15/2022 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-SR4Surplus01 NORTHBurkeNDBEPC 6/1/2026  170170170ERBattery/StorageTande 345 kV Substation12/15/2022 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-SR28Surplus03 CENTRALFordKSSUNC 9/15/2025  150150150ER Solar115 kV Fort Dodge Substation10/6/2023 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-SR27Surplus04 SOUTHEASTMayes CountyOKGRDA12/1/20218/1/2024  101.5101.5101.5ERBattery/StorageGRDA1 to CLARMR 5 161kV line7/12/2023 IA PENDING   
GEN-2023-SR26Surplus04 SOUTHEASTMayes CountyOKAEP12/1/202112/9/2024  72.572.572.5ERBattery/StoragePryor Junction 138kV sub7/12/2023 IA PENDING   
GEN-2023-SR25Surplus04 SOUTHEASTMayes CountyOKGRDA12/1/20218/1/2024  72.572.572.5ERBattery/StorageDry Gulch 161kV sub7/12/2023 IA PENDING   
GEN-2023-SR23Surplus04 SOUTHEASTCaddo ParrishLAAEP 12/1/2025  73.573.573.5ER/NRBattery/Storage138 kV G16-167-TAP Station (Bus# 588404); Tapping North Benton (Bus# 508811) to Lieberman (bus# 508806) Transmission Line6/20/2023 IA PENDING   
GEN-2023-SR22Surplus04 SOUTHEASTMayes CountyOKAEP 12/6/2024  124.7124.7124.7ERBattery/Storage138 kV Exclart Bus (Bus# 510401)6/20/2023 IA PENDING   
GEN-2023-SR20Surplus04 SOUTHEASTCuster/WasitaOKAEP 6/1/2025  120120120ERBattery/StorageWeatherford 138 kV Substation6/21/2023 IA PENDING   
GEN-2023-SR19Surplus02 NEBRASKAJefferson CountyNENPPD 6/1/2025  606060ERBattery/StorageSteele City 115 kV6/21/2023 FACILITY STUDY STAGE   
GEN-2023-SR18Surplus04 SOUTHEASTGrady CountyOKOGE 5/15/2025  808080ERBattery/StorageMinco 345 kV6/20/2023 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-SR16Surplus04 SOUTHEASTWoodward and Harper CountiesOKOG&E 6/1/2025  707070ERBattery/StorageTap Mooreland to Woodward 138 kV Line (FPLSwitch 138 kV Substation)4/26/2023 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-SR15Surplus04 SOUTHEASTChoctaw CountyOKWFEC 6/1/2026  505050ER/NRBattery/StorageHugo Power Plant 138 kV Substation3/27/2023 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-SR13Surplus04 SOUTHEASTGarfield CountyOKOG&E 6/1/2025  707070ERBattery/StorageBreckinridge 138 kV Substation1/26/2023 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-SR12Surplus05 SOUTHWESTWhitefaceTXXcel 9/30/2025  120120120ERBattery/StorageTap Cochran to Lehman 115 kV Line2/13/2023 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-SR1Surplus02 NEBRASKABrownNENPPD10/1/20056/21/2024  21.921.921.9ER/NRThermalAinsworth Wind 115 kV12/5/2022 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-GR5Replacement05 SOUTHWESTLamb CountyTXXcel/SPS  8/11/20224/1/2026150150150ERSolarPlant X 115 kV Substation7/18/2023 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-GR4Replacement05 SOUTHWESTLea CountyNMXcel/SPS  7/13/20225/1/2026727272ERSolarCunningham 115kV7/5/2023 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-GR3Replacement05 SOUTHWESTQuay CountyNMXcel/SPS12/1/200412/31/20049/16/202412/31/2024808080ER/NRWindNorton 115 kV6/30/2023 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-GR2Replacement04 SOUTHEASTOklahoma CityOKOG&E  4/1/20265/1/202694.24284.92694.242ERThermalGasTinker Air Force Base 138kV2/17/2023 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-GR1Replacement04 SOUTHEASTAnadarkoOKWFEC  11/30/202512/1/202597.48897.48895.64ERThermalGasAnadarko Power Plant 69 kV1/9/2023 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2023-241DISIS-2023-00104 SOUTHEASTFranklin & WoodTXAEP8/28/20271/5/2028  939393ERSolarWinnsboro 138 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-237DISIS-2023-00105 SOUTHWESTHaleTXSPS1/15/203012/31/2030  500500500ER/NRWindCrawfish Draw 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-236DISIS-2023-00105 SOUTHWESTLeaNMSPS1/15/203012/31/2030  400400400ER/NRSolarHobbs - Yoakum 345 kV10/2/2023 DISIS STAGE   
GEN-2023-231DISIS-2023-00103 CENTRALCrawfordKSEvergy5/1/202812/1/2028  310310310ERHybridWind/StorageNeosho - LaCynge 345 kV Line10/2/2023 DISIS STAGE   
GEN-2023-230DISIS-2023-00104 SOUTHEASTBossierLAAEP2/4/202811/19/2028  150150150ER/NRHybridSolar/StorageRed Pointe 138 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-229DISIS-2023-00104 SOUTHEASTCaddoOKAEP4/1/202810/31/2028  230230230ER/NRWindSouthwestern Power Station 138 kV Substation (SWS4)10/2/2023 DISIS STAGE   
GEN-2023-228DISIS-2023-00105 SOUTHWESTCottleTXSPS8/15/202612/1/2026  250250250ER/NRBattery/StorageTuco-Okalunion 345 kV line10/2/2023 DISIS STAGE   
GEN-2023-227DISIS-2023-00104 SOUTHEASTTitusTXAEP5/1/20269/1/2026  200200200ER/NRBattery/StoragePetty to Chapel 138 kV Line10/2/2023 DISIS STAGE   
GEN-2023-225DISIS-2023-00102 NEBRASKALancasterNENPPD3/1/20276/1/2027  217217217ERThermalRICEOlive Creek 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-224DISIS-2023-00102 NEBRASKALancasterNENPPD3/1/20276/1/2027  478478478ERThermalCTGOlive Creek 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-223DISIS-2023-00102 NEBRASKAGage NENPPD3/1/20276/1/2027  239239239ER/NRThermalCTGNew Beatrice Power Station 345 kV10/2/2023 DISIS STAGE   
GEN-2023-222DISIS-2023-00102 NEBRASKAGageNENPPD3/1/20276/1/2027  478478478ER/NRThermalCTGNew Beatrice Power Station 345 kV10/2/2023 DISIS STAGE   
GEN-2023-221DISIS-2023-00103 CENTRALOsageKSEvergy9/1/202912/1/2029  250250250ER/NRSolarEmporia Energy Center - Swissvale 345 kV Line10/2/2023 DISIS STAGE   
GEN-2023-220DISIS-2023-00103 CENTRALOsageKSEvergy8/1/202912/1/2029  250250250ER/NRSolarEmporia Energy Center - Swissvale 345 kV Line10/2/2023 DISIS STAGE   
GEN-2023-219DISIS-2023-00103 CENTRALOsageKSEvergy8/1/202912/1/2029  125125125ER/NRSolarReading - Osage Jct 115 kV Line10/2/2023 DISIS STAGE   
GEN-2023-218DISIS-2023-00102 NEBRASKAKnox and CedarNENPPD9/30/202612/31/2026  200200200ER/NRWindTurtle Creek 345 kV Substation 10/2/2023 DISIS STAGE   
GEN-2023-217DISIS-2023-00102 NEBRASKAKnox and CedarNENPPD9/30/202612/31/2026  200200200ER/NRWindTurtle Creek 345 kV Substation 10/2/2023 DISIS STAGE   
GEN-2023-216DISIS-2023-00102 NEBRASKAKnox and CedarNENPPD9/30/202612/31/2026  200200200ER/NRWindTurtle Creek 345 kV Substation 10/2/2023 DISIS STAGE   
GEN-2023-213DISIS-2023-00104 SOUTHEASTBentonARAEP4/15/20289/1/2028  100100100ER/NRBattery/StorageChamber Springs 161 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-212DISIS-2023-00104 SOUTHEASTBowieTX/OKAEP3/1/202712/1/2027  400400400ER/NRHybridSolar/StorageNorthwest Texarkana - Valliant 345 kV Line10/2/2023 DISIS STAGE   
GEN-2023-211DISIS-2023-00104 SOUTHEASTKayOKOGE3/1/202811/1/2028  250250250ER/NRHybridSolar/Battery/WindRanch Road 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-210DISIS-2023-00104 SOUTHEASTLincolnOKWFEC5/4/20269/1/2026  191191191ER/NRSolarPrague - Chernicky 138 kV Line10/2/2023 DISIS STAGE   
GEN-2023-209DISIS-2023-00105 SOUTHWESTRandallTXSPS4/1/20276/1/2027  125125125ER/NRBattery/StorageAmarillo South 115 kV10/2/2023 DISIS STAGE   
GEN-2023-208DISIS-2023-00105 SOUTHWESTPotterTXSPS 12/31/2029  200200200ERBattery/StorageRolling Hills 115 kV10/2/2023 DISIS STAGE   
GEN-2023-206DISIS-2023-00104 SOUTHEASTSebastianAROGE1/1/202912/31/2029  505050ER/NRBattery/StorageBattlefield BESS 161 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-205DISIS-2023-00104 SOUTHEASTHughesOKAEP7/1/202612/31/2026  180180180ER/NRSolarMcAlester City - Weleetka 138 kV line10/2/2023 DISIS STAGE   
GEN-2023-204DISIS-2023-00104 SOUTHEASTMorrisTXAEP4/1/202812/1/2028  953953953ERThermalCTGWelsh-Lydia 345kV Line 10/2/2023 DISIS STAGE   
GEN-2023-203DISIS-2023-00105 SOUTHWESTLeaNMSPS7/31/202812/31/2028  300300300ER/NRHybridSolar/StorageHobbs - Ink Basin 230 kV Transmission Line10/2/2023 DISIS STAGE   
GEN-2023-201DISIS-2023-00105 SOUTHWESTLeaNMNEET7/31/202812/31/2028  300300300ER/NRHybridSolar/StorageCrossroads - Hobbs 345 kV Line10/2/2023 DISIS STAGE   
GEN-2023-199DISIS-2023-00102 NEBRASKADakota NENPPD3/1/20303/28/2027  250250250ER/NRHybridSolar/StorageTwin Church 230 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-195DISIS-2023-00105 SOUTHWESTBaileyTXSPS2/1/20286/1/2028  250250250ER/NRSolarRoosevelt - Tolk 230 kV line tap10/2/2023 DISIS STAGE   
GEN-2023-194DISIS-2023-00103 CENTRALCherokee KSEDE6/1/202812/31/2028  225225225ER/NRSolarRiverton - Neosho 161 kV Line Tap10/2/2023 DISIS STAGE   
GEN-2023-193DISIS-2023-00104 SOUTHEASTHarrisonTXAEP1/15/20283/31/2028  175175175ER/NRHybridSolar/StoragePirkey - Whitney 138 kV Line10/2/2023 DISIS STAGE   
GEN-2023-189DISIS-2023-00102 NEBRASKALancasterNELES8/30/203012/31/2030  200200200ERBattery/StorageNW 68th - Holdrege 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-188DISIS-2023-00105 SOUTHWESTCottonOKAEP2/15/20279/1/2027  160160160ER/NRHybridSolar/StorageOklaunion - Lawton 345 kV Line10/2/2023 DISIS STAGE   
GEN-2023-184DISIS-2023-00105 SOUTHWESTEddyNMSPS8/30/203012/31/2030  200200200ERSolarPhantom 115 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-183DISIS-2023-00105 SOUTHWESTHale TXSPS3/31/20272/28/2027  217217217ERThermalCTGTuco 345kV10/2/2023 DISIS STAGE   
GEN-2023-182DISIS-2023-00101 NORTHLogan & McIntoshNDBEPC8/15/202612/1/2026  300300300ERWindGroton - Leland Olds 345 kV Line10/2/2023 DISIS STAGE   
GEN-2023-180DISIS-2023-00104 SOUTHEASTSebastianARAEP2/1/20286/1/2028  150150150ER/NRSolarHackett - N Huntington 161 kV Line Tap10/2/2023 DISIS STAGE   
GEN-2023-178DISIS-2023-00105 SOUTHWESTRooseveltNMSPS8/15/202612/1/2026  200200200ER/NRSolarRoosevelt 230kV Substation10/2/2023 DISIS STAGE   
GEN-2023-177DISIS-2023-00104 SOUTHEASTGarvinOKOGE2/1/20286/1/2028  200200200ER/NRSolarPaoli - Seminole 138 kV line tap10/2/2023 DISIS STAGE   
GEN-2023-176DISIS-2023-00105 SOUTHWESTLambTXSPS8/30/203012/31/2030  300300300ERWindPlant X 230 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-174DISIS-2023-00104 SOUTHEASTGarvinOKWFEC2/1/20286/1/2028  150150150ERBattery/StoragePaoli West 138 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-173DISIS-2023-00103 CENTRALKearnyKSSUNC9/1/202712/31/2027  100100100ER/NRWindHolcomb 345 kV 10/2/2023 DISIS STAGE   
GEN-2023-172DISIS-2023-00103 CENTRALKearnyKSSUNC9/1/202712/31/2027  200200200ER/NRWindHolcomb 345 kV 10/2/2023 DISIS STAGE   
GEN-2023-171DISIS-2023-00103 CENTRALJacksonMOINDN2/1/20286/1/2028  150150150ER/NRBattery/StorageSub M 161 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-170DISIS-2023-00103 CENTRALCharitonMOEvergy2/1/20286/1/2028  150150150ERBattery/StorageSalisbury 161 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-169DISIS-2023-00103 CENTRALClayMOEvergy2/1/20286/1/2028  125125125ER/NRBattery/StorageMissouri City - Liberty South 161 kV Line10/2/2023 DISIS STAGE   
GEN-2023-168DISIS-2023-00104 SOUTHEASTOklahomaOKOGE2/1/20286/1/2028  175175175ER/NRBattery/StorageClassen 138 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-167DISIS-2023-00104 SOUTHEASTOklahomaOKOGE2/1/20286/1/2028  250250250ER/NRBattery/StorageWashington Park 138 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-166DISIS-2023-00104 SOUTHEASTOklahomaOKOGE2/1/20286/1/2028  150150150ERBattery/Storage84th Street - Tennessee Tap 138 kV Line10/2/2023 DISIS STAGE   
GEN-2023-165DISIS-2023-00104 SOUTHEASTCaddoOKOGE3/1/20285/1/2028  210210210ER/NRBattery/StorageGracemont 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-164DISIS-2023-00104 SOUTHEASTCaddo OKOGE3/1/20285/1/2028  210210210ER/NRBattery/StorageGracemont 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-161DISIS-2023-00104 SOUTHEASTBlaineOKOGE9/3/202611/4/2026  74.974.974.9ER/NRBattery/StorageRoman Nose 138 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-159DISIS-2023-00105 SOUTHWESTBailey and LambTXSPS3/1/20299/15/2029  170170170ER/NRBattery/StorageNeedmore - Yoakum 230 kV Line10/2/2023 DISIS STAGE   
GEN-2023-158DISIS-2023-00105 SOUTHWESTBailey and LambTXSPS3/1/20299/15/2029  335335335ER/NRSolarNeedmore - Yoakum 230 kV Line10/2/2023 DISIS STAGE   
GEN-2023-154DISIS-2023-00101 NORTHHandSDWAPA3/1/20299/30/2029  175175175ERSolarFort Thompson - Huron 230 kV Tap10/2/2023 DISIS STAGE   
GEN-2023-153DISIS-2023-00102 NEBRASKAPerkinsNETri-State6/30/20288/31/2028  120120120ER/NRHybridSolar/StorageGrant 115 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-151DISIS-2023-00104 SOUTHEASTHempsteadARAEP4/1/20288/1/2028  100100100ER/NRHybridSolar/StorageSouth Nashville - South Murfreesboro 138kV10/2/2023 DISIS STAGE   
GEN-2023-150DISIS-2023-00104 SOUTHEASTCaddoOKOGE9/1/202712/31/2027  150150150ER/NRSolarGracemont 138 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-149DISIS-2023-00103 CENTRALLinKSEvergy2/15/20297/1/2029  300300300ER/NRBattery/StorageLaCygne - Stilwell 345 kV Line10/2/2023 DISIS STAGE   
GEN-2023-143DISIS-2023-00105 SOUTHWESTLambTXSPS3/1/20299/15/2029  200200200ER/NRBattery/StoragePlant X 230 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-142DISIS-2023-00105 SOUTHWESTLambTXSPS3/1/20299/15/2029  275275275ERSolarPlant X 230 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-138DISIS-2023-00104 SOUTHEASTDelewareOKGRDA7/15/202811/30/2028  250250250ERWindGRDA1 - Tonece7 345 kV Line10/2/2023 DISIS STAGE   
GEN-2023-135DISIS-2023-00104 SOUTHEASTBowieTXAEP9/15/202612/31/2026  525252ER/NRSolarLydia 345kV substation10/2/2023 DISIS STAGE   
GEN-2023-134DISIS-2023-00104 SOUTHEASTHughes/OkfuskeeOKAEP9/15/202612/31/2026  252252252ER/NRWindFixico Tap to Weleetka 138 kV Line10/2/2023 DISIS STAGE   
GEN-2023-133DISIS-2023-00102 NEBRASKACusterNENPPD5/1/203012/30/2030  250250250ERWindSweetwater 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-132DISIS-2023-00104 SOUTHEASTCraigheadARSWPA6/30/202612/31/2026  150150150ER/NRSolarJonesboro - Independence 161 kV 10/2/2023 DISIS STAGE   
GEN-2023-123DISIS-2023-00105 SOUTHWESTOchiltree/HandsfordTXSPS8/30/203012/31/2030  285285285ERWindPringle Interchange 230 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-120DISIS-2023-00105 SOUTHWESTSwisherTXSPS8/30/203012/31/2030  130130130ERSolarKress 115 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-117DISIS-2023-00102 NEBRASKAKeith, Deuel, GardenNENPPD8/30/203012/30/2030  300300300ERWindKeystone 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-116DISIS-2023-00102 NEBRASKAKeith, Deuel, GardenNENPPD8/30/203012/30/2030  500500500ERWindKeystone 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-110DISIS-2023-00105 SOUTHWESTHallTXSPS8/30/203012/31/2030  250250250ERSolarTap Border to Tuco 345 kV Line10/2/2023 DISIS STAGE   
GEN-2023-107DISIS-2023-00103 CENTRALFinney/KearnyKSSUNC5/1/203012/31/2030  300300300ERWindSetab 345 kV 10/2/2023 DISIS STAGE   
GEN-2023-105DISIS-2023-00101 NORTHHydeSDBEPC9/1/202812/1/2028  249249249ER/NRWindChappelle Creek 345 kV10/2/2023 DISIS STAGE   
GEN-2023-104DISIS-2023-00104 SOUTHEASTWoodsOKWFEC8/30/202712/17/2027  100100100ER/NRHybridSolar/StorageMooreland - Noel 138 kV Line10/2/2023 DISIS STAGE   
GEN-2023-102DISIS-2023-00104 SOUTHEASTWoodsOKOGE8/30/202712/17/2027  475475475ER/NRHybridSolar/StorageDegrasse 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-101DISIS-2023-00104 SOUTHEASTWheelerTXSPS10/1/202712/31/2027  150150150ER/NRHybridSolar/StorageTap Stateline Demarc - Wheeler 230 kV Line10/2/2023 DISIS STAGE   
GEN-2023-100DISIS-2023-00104 SOUTHEASTWoodsOKOGE8/30/202712/17/2027  300300300ER/NRHybridSolar/StorageDegrasse 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-099DISIS-2023-00103 CENTRALJacksonKSEvergy8/30/203012/31/2030  300300300ERSolarJeffery Energy Center 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-097DISIS-2023-00101 NORTHWilliamsNDBEPC2/15/20297/1/2029  250250250ER/NRBattery/StorageJudson 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-092DISIS-2023-00104 SOUTHEASTChoctawOKWFEC8/30/202712/17/2027  125125125ER/NRHybridSolar/StorageUnger - Frogville 138 kV line10/2/2023 DISIS STAGE   
GEN-2023-088DISIS-2023-00104 SOUTHEASTOkfuskee/OkmulgeeOKWFEC9/15/202812/31/2028  117117117ER/NRWindPharaoh 138 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-087DISIS-2023-00103 CENTRALCassMOEvergy8/30/203012/31/2030  200200200ERSolarArchie 161 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-086DISIS-2023-00105 SOUTHWESTRandallTXSPS10/1/20285/1/2029  300300300ER/NRHybridSolar/StoragePotter - Newhart 230 kV line10/2/2023 DISIS STAGE   
GEN-2023-085DISIS-2023-00103 CENTRALDouglas/WrightMOSWPA9/15/202612/31/2026  150150150ER/NRWindMansfield - Logan 161 kV Line10/2/2023 DISIS STAGE   
GEN-2023-082DISIS-2023-00101 NORTHBrookings SDWAPA2/15/20297/1/2029  175175175ER/NRBattery/StorageWhite 115 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-081DISIS-2023-00105 SOUTHWESTLeaNMNEET8/1/202810/1/2028  625625625ER/NRHybridSolar/StorageCrossroads - Hobbs 345 kV Line10/2/2023 DISIS STAGE   
GEN-2023-079DISIS-2023-00102 NEBRASKACassNEOPPD7/1/20282/1/2029  303303303ERThermalGas TurbineSubstation 3740 345 kV10/2/2023 DISIS STAGE   
GEN-2023-078DISIS-2023-00102 NEBRASKACassNEOPPD7/1/20272/1/2028  255255255ERThermalGas TurbineSubstation 3740 345 kV10/2/2023 DISIS STAGE   
GEN-2023-077DISIS-2023-00102 NEBRASKACassNEOPPD7/1/20272/1/2028  255255255ERThermalGas TurbineSubstation 3740 345 kV10/2/2023 DISIS STAGE   
GEN-2023-076DISIS-2023-00104 SOUTHEASTNowata/CraigOKEvergy9/1/202712/31/2027  100100100ER/NRWindDelaware - Neosho 345 kV10/2/2023 DISIS STAGE   
GEN-2023-075DISIS-2023-00104 SOUTHEASTNowata/CraigOKEvergy10/1/202712/1/2027  200200200ER/NRWindDelaware to Neosho 345 kV10/2/2023 DISIS STAGE   
GEN-2023-073DISIS-2023-00103 CENTRALButlerKSEvergy8/30/202712/27/2027  250250250ER/NRBattery/StorageRose Hill 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-069DISIS-2023-00104 SOUTHEASTAtokaOKWFEC8/30/202712/17/2027  100100100ER/NRHybridSolar/StorageTupelo - Atoka 138 kV Line10/2/2023 DISIS STAGE   
GEN-2023-065DISIS-2023-00103 CENTRALHarveyKSEvergy5/1/20269/1/2026  140140140ER/NRBattery/StorageHalstead 69 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-064DISIS-2023-00104 SOUTHEASTLeFloreOKSWPA8/1/202812/1/2028  200200200ER/NRHybridSolar/StorageRS Kerr-Stigler 161 kV line10/2/2023 DISIS STAGE   
GEN-2023-063DISIS-2023-00104 SOUTHEASTRogersOKAEP8/1/202812/1/2028  135135135ER/NRHybridSolar/StorageCatoosa - Owasso 88th 138 kV line10/2/2023 DISIS STAGE   
GEN-2023-062DISIS-2023-00101 NORTHWilliamsNDLYREC4/30/20287/31/2028  989898ERThermalSteamREN 115 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-061DISIS-2023-00103 CENTRALJasperMOSWPA9/30/202712/31/2027  100100100ER/NRBattery/StorageCarthage 161 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-060DISIS-2023-00105 SOUTHWESTLambTXSPS9/30/202612/31/2026  256256256ER/NRSolarPlant X 230kV Substation10/2/2023 DISIS STAGE   
GEN-2023-059DISIS-2023-00104 SOUTHEASTHarrison and PanolaTXAEP9/30/202612/31/2026  200200200ER/NRHybridSolar\RECIP GasTap Rockhill to South Shreveport 138 kV line9/11/2023 DISIS STAGE   
GEN-2023-057DISIS-2023-00104 SOUTHEASTPawneeOKGRDA12/28/20275/31/2028  150150150ER/NRBattery/StoragePawnee Switch 138 kV10/2/2023 DISIS STAGE   
GEN-2023-056DISIS-2023-00104 SOUTHEASTVan Buren CountyARSWPA12/28/20275/31/2028  150150150ER/NRBattery/StorageVan Buren 161 kV10/2/2023 DISIS STAGE   
GEN-2023-055DISIS-2023-00104 SOUTHEASTMayes CountyOKGRDA12/28/20275/31/2028  100100100ER/NRBattery/StorageKerr Grove 161 kV10/2/2023 DISIS STAGE   
GEN-2023-050DISIS-2023-00103 CENTRALLabetteKSEvergy6/30/202812/31/2028  400400400ER/NRHybridSolar/StorageNeosho 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-049DISIS-2023-00104 SOUTHEASTMayesOKGRDA6/30/202812/31/2028  150150150ER/NRHybridSolar/StorageDry Gulch - Pensacola 161 kV Line10/2/2023 DISIS STAGE   
GEN-2023-038DISIS-2023-00104 SOUTHEASTCoalOKOGE5/24/20269/1/2026  200200200ER/NRSolarLula 138 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-037DISIS-2023-00103 CENTRALWyandotte KSKACY4/15/20287/1/2028  200200200ER/NRBattery/StorageNearman 161 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-036DISIS-2023-00103 CENTRALJacksonMOINDN8/30/202612/31/2026  165165165ER/NRBattery/StorageEckles Road 161 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-035DISIS-2023-00104 SOUTHEASTGradyOKWFEC5/4/20269/1/2026  200200200ER/NRSolarCleveland - Amber Tap 138 kV Line10/2/2023 DISIS STAGE   
GEN-2023-034DISIS-2023-00103 CENTRALSedgwickKSEvergy5/24/20269/1/2026  130130130ER/NRSolarClear Water - Waco 138 kV line10/2/2023 DISIS STAGE   
GEN-2023-033DISIS-2023-00103 CENTRALClayMOEvergy4/15/20287/1/2028  200200200ER/NRBattery/StorageLiberty South 161 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-032DISIS-2023-00103 CENTRALLafayetteMOEvergy1/1/20286/1/2028  200200200ER/NRSolarOdessa and Lexington 161 kV Line10/2/2023 DISIS STAGE   
GEN-2023-030DISIS-2023-00104 SOUTHEASTDeSoto ParishLAAEP9/1/202712/31/2027  252525ER/NRSolarTap between 345 kV SW Shreveport to Dolet Hills Substations10/2/2023 DISIS STAGE   
GEN-2023-028DISIS-2023-00104 SOUTHEASTMayesOKGRDA4/30/202810/31/2028  230230230ER/NRHybridSolar/BatteryDry Gulch - Pensacola 161 kV Line10/2/2023 DISIS STAGE   
GEN-2023-027DISIS-2023-00104 SOUTHEASTMayesOKAEP4/30/202811/30/2027  150150150ER/NRHybridSolar/BatteryBird Hollow (Langley) - Pryor Junction 138 kV Line10/2/2023 DISIS STAGE   
GEN-2023-023DISIS-2023-00103 CENTRALWyandotte KSKACY4/15/20287/1/2028  200200200ER/NRBattery/StorageCenter City 161 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-022DISIS-2023-00104 SOUTHEASTMcIntosh OKOGE9/1/202712/31/2027  250250250ER/NRWindCanadian River 345 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-015DISIS-2023-00103 CENTRALFinney CountyKSSPS5/4/20269/1/2026  330330330ER/NRSolarFinney-Carpenter 345 KV line10/2/2023 DISIS STAGE   
GEN-2023-012DISIS-2023-00101 NORTHLake PrestonSDEREC6/15/202610/31/2026  98.698.698.6ER/NRWindKingsbury County 115kV Substation10/2/2023 DISIS STAGE   
GEN-2023-011DISIS-2023-00102 NEBRASKAJeffersonNENPPD8/30/203012/31/2030  190190190ERWindHarbine 115 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-010DISIS-2023-00105 SOUTHWESTShermanTXSPS8/30/203012/31/2030  280280280ERWindMoore Co 230 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-009DISIS-2023-00104 SOUTHEASTSawyerOKWFEC6/1/202812/1/2028  250250250ER/NRBattery/StorageHugo 138 kV Substation10/2/2023 DISIS STAGE   
GEN-2023-008DISIS-2023-00105 SOUTHWESTHaleTXSPS8/8/203012/31/2030  757575ERSolarTuco - Carlisle 230 kV line10/2/2023 DISIS STAGE   
GEN-2023-006DISIS-2023-00103 CENTRALBarton, VernonMONEET5/1/202912/31/2029  202202202ERWindWolf Creek- Blackberry 345 kV Line Break10/2/2023 DISIS STAGE   
GEN-2023-005DISIS-2023-00105 SOUTHWESTLambTXSPS9/30/202612/31/2026  256256256ER/NRSolarPlant X 230kV Substation9/25/2023 DISIS STAGE   
GEN-2023-001DISIS-2023-00105 SOUTHWESTLeaNMSPS7/15/202512/31/2025  230230230ER/NRSolarT14 Circuit 115 V Line5/26/2023 DISIS STAGE10/3/2023 Updated TO from XCEL to SPS. kr   
GEN-2022-GR1Replacement04 SOUTHEASTHallsvilleTXAEP 3/30/20263/31/2023 580580580ERSolarPirkey 138 kV3/23/2022 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2022-241DISIS-2022-00104 SOUTHEASTHempsteadARAEP3/1/20289/15/2028  200200200ER/NRBattery/StorageJohn W Turk Jr Power Plant 345 kV sub2/28/2023 DISIS STAGE   
GEN-2022-240DISIS-2022-00104 SOUTHEASTHempsteadARAEP3/1/20289/15/2028  200200200ER/NRBattery/StorageJohn W Turk Jr Power Plant 345 kV sub2/28/2023 DISIS STAGE   
GEN-2022-239DISIS-2022-00104 SOUTHEASTHempsteadARAEP3/1/20289/15/2028  350350350ER/NRSolarJohn W Turk Jr Power Plant 345 kV sub2/28/2023 DISIS STAGE   
GEN-2022-238DISIS-2022-00104 SOUTHEASTPottawatomieOKOGE3/1/20289/15/2028  150150150ER/NRBattery/StorageMaud 138 kV substation2/28/2023 DISIS STAGE   
GEN-2022-237DISIS-2022-00104 SOUTHEASTPottawatomieOKOGE3/1/20289/15/2028  150150150ER/NRSolarMaud 138 kV substation2/28/2023 DISIS STAGE   
GEN-2022-235DISIS-2022-00104 SOUTHEASTCanadianOKWFEC3/1/20289/15/2028  150150150ER/NRBattery/StorageEl Reno SW 138 kV 2/28/2023 DISIS STAGE   
GEN-2022-234DISIS-2022-00104 SOUTHEASTRogersOKAEP3/1/20289/15/2028  200200200ER/NRSolarAlluwe Tap – Chelsea 138 kV line2/28/2023 DISIS STAGE   
GEN-2022-231DISIS-2022-00104 SOUTHEASTLoganOKOGE3/1/20289/15/2028  166166166ER/NRSolarCrescent to Cottonwood Creek 138 kV Line2/28/2023 DISIS STAGE   
GEN-2022-219DISIS-2022-00101 NORTHDawsonMTWAPA10/6/202612/31/2026  350350350ER/NRSolarBelfield 230 kV Substation3/2/2023 DISIS STAGE   
GEN-2022-214DISIS-2022-00103 CENTRALSumnerKSWERE5/1/202712/15/2028  239239239ERSolarGill - Viola 138 kV Line Break3/2/2023 DISIS STAGE   
GEN-2022-209DISIS-2022-00103 CENTRALAndrew/Gentry/DekalbMOKCPL7/1/202712/1/2027  600600600ER/NRHybridSolar/StorageTap on the Mullen Creek to Ketchum 345 kV Line3/1/2023 DISIS STAGE   
GEN-2022-208DISIS-2022-00103 CENTRALAndrew/Gentry/DekalbMOKCPL7/1/202712/1/2027  400400400ER/NRWindTap on the Mullen Creek to Ketchum 345 kV Line3/1/2023 DISIS STAGE   
GEN-2022-206DISIS-2022-00103 CENTRALEdwards/HodgemanKSITCGP7/1/202711/1/2027  250250250ER/NRWindPost Rock - Spearville 345 kV3/1/2023 DISIS STAGE   
GEN-2022-205DISIS-2022-00103 CENTRALEdwards/HodgemanKSITCGP7/1/202711/1/2027  250250250ER/NRWindPost Rock - Spearville 345 kV3/1/2023 DISIS STAGE   
GEN-2022-204DISIS-2022-00103 CENTRALEdwards/HodgemanKSITCGP7/1/202711/1/2027  250250250ER/NRWindPost Rock - Spearville 345 kV3/1/2023 DISIS STAGE   
GEN-2022-196DISIS-2022-00104 SOUTHEASTPittsburgOKAEP5/1/202712/15/2027  215215215ERWindPittsburg 345kV Substation2/28/2023 DISIS STAGE   
GEN-2022-186DISIS-2022-00103 CENTRALCoffeyKSWERE5/6/20265/30/2026  684684684ER/NRSolarWolf Creek - Benton 345 kV Substation2/28/2023 DISIS STAGE   
GEN-2022-176DISIS-2022-00104 SOUTHEASTNowataOKAEP4/1/202610/31/2026  215215215ER/NRWindNortheastern - Delaware 345 kV transmission line2/17/2023 DISIS STAGE   
GEN-2022-171DISIS-2022-00105 SOUTHWESTCurryNMSPS8/1/202612/1/2026  200200200ERWindPleasant Hill 230 kV Substation2/26/2023 DISIS STAGE   
GEN-2022-168DISIS-2022-00103 CENTRALHenryMOKCPL7/31/202712/31/2027  380380380ER/NRSolarSilwell - Clinton 161 kV Line2/26/2023 DISIS STAGE   
GEN-2022-167DISIS-2022-00104 SOUTHEASTTulsaOKAEP6/30/202810/1/2028  250250250ER/NRSolarTulsa North - Northeastern 345 kV Line2/26/2023 DISIS STAGE   
GEN-2022-163DISIS-2022-00104 SOUTHEASTCanadianOKOGE3/15/20266/15/2026  200200200ER/NRBattery/StorageCimarron 345kV Substation2/26/2023 DISIS STAGE   
GEN-2022-162DISIS-2022-00102 NEBRASKASaline NENPPD5/1/202512/31/2025  118118118ER/NRWindFriend 115 kV Substation2/24/2023 DISIS STAGE   
GEN-2022-161DISIS-2022-00103 CENTRALButlerKSWERE12/31/20263/1/2027  400400400ERWindBurns 345kV Substation2/24/2023 DISIS STAGE   
GEN-2022-160DISIS-2022-00105 SOUTHWESTChaves and LeaNMNEET5/1/202812/1/2028  280280280ER/NRWindCrossroads - Hobbs 345 kV Line2/24/2023 DISIS STAGE   
GEN-2022-159DISIS-2022-00105 SOUTHWESTChaves and LeaNMNEET5/1/202812/1/2027  280280280ER/NRWindCrossroads - Hobbs 345 kV Line2/24/2023 DISIS STAGE   
GEN-2022-156DISIS-2022-00104 SOUTHEASTCreekOKGRDA9/15/202612/31/2026  100100100ERBattery/StorageSilver City 138 kV Substation2/24/2023 DISIS STAGE   
GEN-2022-155DISIS-2022-00104 SOUTHEASTOklahomaOKOGE9/15/202612/31/2026  200200200ERBattery/StorageHorseshoe Lake 138 kV Substation2/24/2023 DISIS STAGE   
GEN-2022-154DISIS-2022-00104 SOUTHEASTClevelandOKWFEC9/15/202612/31/2026  100100100ERBattery/StorageCanadian Switch 138 kV Substation2/24/2023 DISIS STAGE   
GEN-2022-152DISIS-2022-00102 NEBRASKARichardsonNENPPD5/10/20268/21/2026  808080ER/NRBattery/StorageHumboldt 161 kV Substation2/23/2023 DISIS STAGE   
GEN-2022-150DISIS-2022-00105 SOUTHWESTRandallTXSPS5/10/20268/21/2026  150171171ER/NRBattery/StorageRandall 115 kV Substation2/23/2023 DISIS STAGE   
GEN-2022-147DISIS-2022-00105 SOUTHWESTHaleTXSPS2/27/20244/15/2025  203196203ERThermalCTGTuco 345kV2/21/2023 DISIS STAGE   
GEN-2022-145DISIS-2022-00104 SOUTHEASTClusterOKAEP9/15/202712/31/2027  195195195ERBattery/StorageWeatherford Jct. to Hinton 138 kV line2/21/2023 DISIS STAGE   
GEN-2022-144DISIS-2022-00103 CENTRALJacksonMOKCPL9/15/202712/31/2027  200210.4210.4ER/NRBattery/StorageBlue Mills BESS 161kV Substation2/21/2023 DISIS STAGE   
GEN-2022-143DISIS-2022-00104 SOUTHEASTMarshallOKOGE9/15/202712/31/2027  200210.4210.4ER/NRBattery/StorageCaney Creek 138 kV Substation2/21/2023 DISIS STAGE   
GEN-2022-142DISIS-2022-00103 CENTRALClayMOKCPL9/15/202712/31/2027  200210.4210.4ER/NRBattery/StorageShoal Creek 161 kV Substation2/21/2023 DISIS STAGE   
GEN-2022-139DISIS-2022-00104 SOUTHEASTHarrisonTXAEP9/15/202712/31/2027  300315.7315.7ER/NRBattery/StoragePirkey 345kV Substation2/21/2023 DISIS STAGE   
GEN-2022-138DISIS-2022-00104 SOUTHEASTRogerOKAEP9/15/202712/31/2027  300316.6316.6ER/NRBattery/StorageTulsa North - Northeast Station 345 kV Substation2/21/2023 DISIS STAGE   
GEN-2022-137DISIS-2022-00104 SOUTHEASTClevelandOKWFEC9/15/202712/31/2027  200210.4210.4ER/NRBattery/StorageCanadian Switchyard 138kV2/21/2023 DISIS STAGE   
GEN-2022-136DISIS-2022-00104 SOUTHEASTBryanOKWFEC9/15/202712/31/2027  200210.5210.5ER/NRBattery/StorageColbert 138 kV Substation2/21/2023 DISIS STAGE   
GEN-2022-135DISIS-2022-00105 SOUTHWESTLeaNMSPS9/15/202712/31/2027  150155.1155.1ER/NRBattery/StorageTaylor Switching Station 115kV2/21/2023 DISIS STAGE   
GEN-2022-132DISIS-2022-00104 SOUTHEASTCaddoOKWFEC9/15/202712/31/2027  300315.8315.8ER/NRBattery/StorageAnadarko 138kV Substation 2/21/2023 DISIS STAGE   
GEN-2022-131DISIS-2022-00103 CENTRALJohnsonMOKCPL9/15/202712/31/2027  200200200ER/NRBattery/StorageWarrensburg East - Odessa161kV Substation2/21/2023 DISIS STAGE   
GEN-2022-130DISIS-2022-00104 SOUTHEASTSebastianAROGE9/15/202712/31/2027  200200200ER/NRBattery/StorageBattlefield BESS 161kV2/21/2023 DISIS STAGE   
GEN-2022-129DISIS-2022-00104 SOUTHEASTOsageOKAEP9/15/202712/31/2027  200200200ER/NRBattery/StorageWebb City Tap - Shidler 138 kV line2/21/2023 DISIS STAGE   
GEN-2022-128DISIS-2022-00105 SOUTHWESTEddyNMSPS9/15/202712/31/2027  150150150ER/NRBattery/StoragePecos Interchange 115 kV Substation 2/21/2023 DISIS STAGE   
GEN-2022-114DISIS-2022-00105 SOUTHWESTTillmanOKAEP12/1/202712/31/2027  250250250ER/NRWindLawton to Oklaunion 345kV Line2/16/2023 DISIS STAGE   
GEN-2022-113DISIS-2022-00103 CENTRALNewtonMOEDE4/1/202612/31/2027  200200200ER/NRSolarTipton Station 161 kV Substation2/16/2023 DISIS STAGE   
GEN-2022-111DISIS-2022-00104 SOUTHEASTMarionTXAEP6/30/20269/30/2026  150150150ER/NRHybridSolar/StorageWilkes 345 kV Substation2/10/2023 DISIS STAGE   
GEN-2022-110DISIS-2022-00104 SOUTHEASTCoalOKAEP1/30/20264/30/2026  150150150ER/NRBattery/StorageLehigh 138kV Station2/10/2023 DISIS STAGE   
GEN-2022-109DISIS-2022-00105 SOUTHWESTLeaNMSPS5/1/202610/1/2026  150150150ER/NRSolarHobbs - Yoakum 345 kV transmission line1/6/2023 DISIS STAGE   
GEN-2022-108DISIS-2022-00104 SOUTHEASTDeSoto ParishLAAEP9/1/202712/31/2027  100100100ER/NRSolarTap between 345kV SW Shreveport to Dolet Hills Substations1/8/2023 DISIS STAGE   
GEN-2022-107DISIS-2022-00105 SOUTHWESTTillmanOKAEP3/1/20267/31/2026  400400400ER/NRSolarTap of Oklaunion to Lawton Eastside 345 kV Transmission Line1/9/2023 DISIS STAGE   
GEN-2022-106DISIS-2022-00105 SOUTHWESTTillmanOKAEP3/1/20267/31/2026  300300300ER/NRSolarTap of Oklaunion to Lawton Eastside 345 kV Transmission Line1/9/2023 DISIS STAGE   
GEN-2022-105DISIS-2022-00105 SOUTHWESTTillmanOKAEP3/1/20267/31/2026  300300300ER/NRSolarTap of Oklaunion to Lawton Eastside 345 kV Transmission Line1/9/2023 DISIS STAGE   
GEN-2022-104DISIS-2022-00104 SOUTHEASTBryanOKWFEC11/3/20252/2/2026  113.078113.078113.078ER/NRSolarBrown - South Coleman Junction 138kV line1/26/2023 DISIS STAGE   
GEN-2022-103DISIS-2022-00103 CENTRALChristianMOEDE10/1/20261/1/2027  74.9974.9974.99ER/NRBattery/StorageOzark South 161kV 1/30/2023 DISIS STAGE   
GEN-2022-102DISIS-2022-00103 CENTRALClayMOKCPL10/1/20261/1/2027  100100100ER/NRBattery/StorageLiberty West 161 kV1/6/2023 DISIS STAGE   
GEN-2022-100DISIS-2022-00103 CENTRALCooper MOKCPL8/1/202510/1/2026  808080ER/NRHybridSolar/StorageOverton - Sedalia East 161 kV Substation3/24/2023 DISIS STAGE   
GEN-2022-098DISIS-2022-00104 SOUTHEASTJohnston OKOGE3/1/202412/1/2024  200200200ER/NRSolarBison 345kV Substation12/6/2022 DISIS STAGE   
GEN-2022-094DISIS-2022-00103 CENTRALOsborne KSITCGP5/27/202812/31/2028  250250250ERWindPostrock to Axtell 345 kV line11/15/2022 DISIS STAGE   
GEN-2022-093DISIS-2022-00104 SOUTHEASTHempsteadARAEP10/1/20264/1/2027  838383ER/NRSolarTurk - Hope 115 kV line11/15/2022 DISIS STAGE   
GEN-2022-092DISIS-2022-00104 SOUTHEASTNowata and CraigOKAEP9/1/202612/15/2026  299.2299.2299.2ER/NRWindNeosho-Delaware 345 kV11/15/2022 DISIS STAGE   
GEN-2022-091DISIS-2022-00104 SOUTHEASTMcCurtainOKAEP9/30/20269/30/2026  150150150ER/NRBattery/StorageValiant Substation 138kV11/15/2022 DISIS STAGE   
GEN-2022-090DISIS-2022-00104 SOUTHEASTMcCurtainOKAEP9/30/20269/30/2026  150150150ER/NRSolarValiant Substation 138kV11/15/2022 DISIS STAGE   
GEN-2022-089DISIS-2022-00104 SOUTHEASTLittle RiverARAEP9/30/20269/30/2026  74.9974.9974.99ER/NRBattery/StorageSouth Foreman 138 kV Substation 11/15/2022 DISIS STAGE   
GEN-2022-088DISIS-2022-00104 SOUTHEASTLittle RiverARAEP9/30/20269/30/2026  74.9974.9974.99ER/NRSolarSouth Foreman 138 kV Substation 11/15/2022 DISIS STAGE   
GEN-2022-085DISIS-2022-00104 SOUTHEASTOfuskee and HughesOKOGE9/1/202512/31/2025  241.4241.4241.4ER/NRWindSeminole to Muskogee 345kV Substation11/5/2022 DISIS STAGE   
GEN-2022-083DISIS-2022-00101 NORTHWilliamsNDBEPC6/1/20252/1/2025  250250265ERThermalCTGJudson Substation 345 kV10/21/2022 DISIS STAGE   
GEN-2022-082DISIS-2022-00105 SOUTHWESTHaleTXSPS4/1/202512/31/2028  180180180ER/NRSolarTuco - Carlisle 230 kV line9/22/2022 DISIS STAGE   
GEN-2022-081DISIS-2022-00103 CENTRALWashington KSSUNC4/1/202511/29/2027  218218218ER/NRBattery/StorageClifton 115kV Substation 9/22/2022 DISIS STAGE   
GEN-2022-080DISIS-2022-00103 CENTRALCedarMOEDE1/1/202610/31/2027  969696ERBattery/StorageDadeville East - Bolivar South 161kV 9/22/2022 DISIS STAGE   
GEN-2022-079DISIS-2022-00103 CENTRALCedarMOEDE1/1/202610/31/2027  192192192ERSolarDadeville East - Bolivar South 161kV9/22/2022 DISIS STAGE   
GEN-2022-077DISIS-2022-00102 NEBRASKAChaseNENPPD1/1/202612/1/2026  255255255ER/NRSolarEnders 115 kV Substation9/21/2022 DISIS STAGE   
GEN-2022-076DISIS-2022-00103 CENTRALStevensKSSPS3/15/202611/15/2026  500500500ER/NRSolarCarpenter 345 kV Substation9/7/2022 DISIS STAGE   
GEN-2022-075DISIS-2022-00103 CENTRALEllisKSITCGP9/3/202711/19/2027  175175175ER/NRSolarTap on the Spearville - Post Rock 345kV line9/2/2022 DISIS STAGE   
GEN-2022-074DISIS-2022-00104 SOUTHEASTEufaula, McIntoshOKWFEC3/1/202510/31/2025  220.86220.86220.86ER/NRWindHanna 138kV Substation9/6/2022 DISIS STAGE   
GEN-2022-073DISIS-2022-00103 CENTRALKayMOKCPL4/1/202512/31/2027  300300300ER/NRBattery/StorageNashua 161 kV Substation9/2/2022 DISIS STAGE   
GEN-2022-072DISIS-2022-00104 SOUTHEASTMayesOKGRDA7/1/202512/31/2028  181181181ER/NRSolarGrand River Dam - Claremore 161 kV Line8/12/2022 DISIS STAGE   
GEN-2022-071DISIS-2022-00104 SOUTHEASTPittsburgOKAEP11/3/20252/2/2026  90.82490.82490.824ER/NRSolarTalawanda to Canadian River 138 kV Line Tap8/12/2022 DISIS STAGE   
GEN-2022-068DISIS-2022-00101 NORTHHydeSDBEPC7/1/202611/1/2026  250250250ER/NRWindChappelle Creek 345 kV8/11/2022 DISIS STAGE   
GEN-2022-065DISIS-2022-00103 CENTRALEdwardsKSSUNC9/4/202711/19/2027  145145145ER/NRSolartap on Arthur Mullergreen-Spearville 230 kV line7/25/2022 DISIS STAGE   
GEN-2022-062DISIS-2022-00103 CENTRALBourbonKSNEET4/1/202512/31/2025  200200200ER/NRSolarWolf Creek- Blackberry 345 kV7/8/2022 DISIS STAGE   
GEN-2022-058DISIS-2022-00103 CENTRALBentonAREDE7/1/202812/31/2028  180180180ER/NRSolarNoel Southwest - Decatur 161 kV line tap6/23/2022 DISIS STAGE   
GEN-2022-055DISIS-2022-00104 SOUTHEASTGradyOKWFEC4/1/202512/31/2025  200200200ER/NRSolarSunshine North to Anadarko 138 kV6/23/2022 DISIS STAGE   
GEN-2022-054DISIS-2022-00103 CENTRALBourbonKSNEET4/1/202512/31/2025  200200200ER/NRSolarWolf Creek - Blackberry 345 kV Tap6/23/2022 DISIS STAGE   
GEN-2022-048DISIS-2022-00104 SOUTHEASTWoodwardOKWFEC4/1/202512/31/2025  250250250ER/NRWindMooreland 138 kV6/23/2022 DISIS STAGE   
GEN-2022-042DISIS-2022-00104 SOUTHEASTCarterOKOGE4/1/202512/31/2025  174174174ER/NRSolarSunnyside to Pooleville 138 kV line6/23/2022 DISIS STAGE   
GEN-2022-041DISIS-2022-00103 CENTRALCowleyKSWERE4/1/202512/31/2025  100100100ER/NRSolarTie Substation 69 kV6/29/2022 DISIS STAGE   
GEN-2022-038DISIS-2022-00104 SOUTHEASTHarrisonTXAEP4/1/202512/31/2025  200200200ER/NRSolarLongwood to Scottville 138 kV line6/23/2022 DISIS STAGE   
GEN-2022-026DISIS-2022-00103 CENTRALDecaturKSSUNC6/1/202412/31/2025  200200200ER/NRSolarTap of Mingo--Red Willow 345kV line6/8/2022 DISIS STAGE   
GEN-2022-025DISIS-2022-00103 CENTRALDecaturKSSUNC6/1/202412/31/2025  200200200ER/NRSolarTap of Mingo--Red Willow 345kV line6/8/2022 DISIS STAGE   
GEN-2022-024DISIS-2022-00103 CENTRALBourbonKSWERE6/1/202412/31/2025  200200200ER/NRBattery/StorageTap of Neosho - LaCygne 345 kV Line6/10/2022 DISIS STAGE   
GEN-2022-021DISIS-2022-00105 SOUTHWESTTillmanOKAEP6/1/202412/31/2025  100100100ER/NRBattery/StorageTap of Oklaunion - Lawton Eastside 345 kV line6/8/2022 DISIS STAGE   
GEN-2022-019DISIS-2022-00105 SOUTHWESTTillman OKAEP6/1/202412/31/2025  100100100ER/NRBattery/StorageTap of Oklaunion - Lawton Eastside 345 kV line6/8/2022 DISIS STAGE   
GEN-2022-017DISIS-2022-00104 SOUTHEASTWoodwardOKOGE6/6/202412/31/2025  150150150ER/NRBattery/StorageWoodward 345kV Substation6/8/2022 DISIS STAGE   
GEN-2022-016DISIS-2022-00104 SOUTHEASTWoodwardOKOGE6/1/202412/31/2025  288288288ER/NRSolarWoodward 345kV Substation6/8/2022 DISIS STAGE   
GEN-2022-015DISIS-2022-00103 CENTRALDecaturKSSUNC6/1/202412/31/2025  270270270ER/NRSolarTap of Mingo - Red Willow 345 kV Line6/8/2022 DISIS STAGE   
GEN-2022-013DISIS-2022-00103 CENTRALBourbonKSWERE6/1/202412/31/2025  300300300ER/NRSolarTap of Neosho - LaCygne 345 kV Line6/8/2022 DISIS STAGE   
GEN-2022-012DISIS-2022-00104 SOUTHEASTWoodward OKOGE6/1/202412/31/2025  100100100ER/NRBattery/StorageWoodward 345 kV Substation6/8/2022 DISIS STAGE   
GEN-2022-011DISIS-2022-00105 SOUTHWESTTillmanOKAEP6/1/202412/31/2025  374374374ER/NRSolarTap of Oklaunion - Lawton Eastside 345 kV line6/3/2022 DISIS STAGE   
GEN-2022-010DISIS-2022-00101 NORTHWilliamsNDBEPC7/1/20232/1/2025  250250250ERThermalJudson Substation 345 kV5/26/2022 DISIS STAGE   
GEN-2022-009DISIS-2022-00101 NORTHWilliamsNDBEPC7/1/20232/1/2025  125125125ERThermalJudson Substation 345 kV5/26/2022 DISIS STAGE   
GEN-2022-007DISIS-2022-00103 CENTRALLyonKSWERE5/1/202510/31/2026  135135135ER/NRSolarLang - Reading 115 kV Transmission Line5/26/2022 DISIS STAGE   
GEN-2022-006DISIS-2022-00103 CENTRALLabetteKSWERE4/1/202510/31/2026  200200200ER/NRSolarNeosho - N345 161 kV Substation5/25/2022 DISIS STAGE   
GEN-2022-005DISIS-2022-00103 CENTRALLabetteKSWERE4/1/202510/31/2026  200200200ER/NRSolarNortheast Parsons 138kV Substation5/25/2022 DISIS STAGE   
GEN-2022-004DISIS-2022-00103 CENTRALSedgwickKSWERE8/1/202510/31/2026  333333ER/NRSolarMurray Gill 138 kV Substation5/26/2022 DISIS STAGE   
GEN-2022-001DISIS-2022-00104 SOUTHEASTRogersOKAEP9/26/20261/7/2027  100100100ER/NRBattery/StorageCatoosa 138 kV Substation12/30/2021 DISIS STAGE   
GEN-2021-SR9SurplusKansas CityMOKCPL 1/11/2023  101010ER/NRSolarHawthorn Power Plant8/24/2021 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2021-SR8Surplus03 CENTRALHarperKSWERE11/1/202311/1/2023  424242ERSolarViola 345kV5/13/2021 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2021-108DISIS-2021-00102 NEBRASKACassNEOPPD5/27/20255/14/2025  182.25182.25182.25ER/NRSolarOPPD 345KV Cass County Substation5/20/2021 DISIS STAGE   
GEN-2021-107DISIS-2021-00103 CENTRALPottawatomieKSWERE10/1/202612/1/2026  201.6201.6201.6ERSolarEvergy 345kV Jeffrey Energy Center5/20/2021 DISIS STAGE   
GEN-2021-103DISIS-2021-00103 CENTRALJohnsonKSWERE8/1/20259/1/2026  150150150ER/NRBattery/StorageEvergy's Atlantic Substation115kV bus5/25/2021 DISIS STAGE   
GEN-2021-101DISIS-2021-00103 CENTRALDouglasKSWERE8/1/20259/1/2025  159159159ER/NRSolarEvergy's Midland Substation 115kV bus5/25/2021 DISIS STAGE   
GEN-2021-098DISIS-2021-00104 SOUTHEASTDeweyOKOGE7/1/202612/31/2026  160160160ER/NRHybridWind/StorageDewey District 138 kV Substation5/24/2021 DISIS STAGE   
GEN-2021-096DISIS-2021-00103 CENTRALCoffeyKSWERE5/1/202612/1/2027  500500500ER/NRSolarWolf Creek - Benton 345 kV4/29/2021 DISIS STAGE   
GEN-2021-090DISIS-2021-00105 SOUTHWESTYoakumTXSPS6/15/20226/30/2028  400400400ER/NRHybridSolar/StorageYoakum 345kV Substation4/30/2021 DISIS STAGE   
GEN-2021-088DISIS-2021-00104 SOUTHEASTClevelandOKOGE12/21/20251/7/2027  100100100ER/NRBattery/StorageCedar Lane - Canadian 138 kV Transmission Line4/29/2021 DISIS STAGE   
GEN-2021-077DISIS-2021-00103 CENTRALPettisMOGMO7/1/202512/31/2027  959595ER/NRHybridSolar/StorageWindsor to AEC Sedalia 161 kV4/30/2021 DISIS STAGE   
GEN-2021-076DISIS-2021-00103 CENTRALEllisKSITCGP7/1/202612/31/2026  113113113ER/NRSolarITC Post Rock 345 kV Substation5/13/2021 DISIS STAGE   
GEN-2021-075DISIS-2021-00104 SOUTHEASTCampTXAEP7/1/202612/31/2027  300300300ER/NRHybridSolar/StorageCAMPCOR4 138kV Substation 5/19/2021 DISIS STAGE   
GEN-2021-070DISIS-2021-00103 CENTRALHodgeman and FordKSSUNC8/1/202712/1/2027  504504504ERWindSUNC Spearville - Holcomb 345kV4/26/2021 DISIS STAGE   
GEN-2021-069DISIS-2021-00103 CENTRALHodgeman and FordKSSUNC8/1/202712/1/2027  249.6249.6249.6ERWindSUNC Spearville - Holcomb 345kV4/26/2021 DISIS STAGE   
GEN-2021-068DISIS-2021-00103 CENTRALHodgeman and FordKSSUNC9/1/202512/1/2027  249.6249.6249.6ERWindSUNC Spearville - Holcomb 345kV4/26/2021 DISIS STAGE   
GEN-2021-064DISIS-2021-00104 SOUTHEASTCaddoOKAEP10/25/202512/31/2027  100100100ER/NRHybridSolar/StorageCarnegie South 138kV4/28/2021 DISIS STAGE   
GEN-2021-063DISIS-2021-00104 SOUTHEASTMcCurtainOKAEP10/25/202512/31/2027  155155155ER/NRHybridSolar/StorageCraig JCT 138kV4/28/2021 DISIS STAGE   
GEN-2021-057DISIS-2021-00102 NEBRASKAAntelopeNENPPD 12/31/2027  300300300ERWindAntelope 345kV substation4/29/2021 DISIS STAGE   
GEN-2021-056DISIS-2021-00103 CENTRALHarper and KingmanKSWERE 12/31/2028  300300300ERWindViola 345kV Substation4/29/2021 DISIS STAGE   
GEN-2021-053DISIS-2021-00104 SOUTHEASTMuskogeeOKOGE 5/30/2026  300300300ERSolarPecan Creek 345 kV Substation4/29/2021 DISIS STAGE   
GEN-2021-052DISIS-2021-00104 SOUTHEASTMuskogeeOKOGE 5/30/2026  757575ERBattery/StoragePecan Creek 345kV substation4/29/2021 DISIS STAGE   
GEN-2021-051DISIS-2021-00103 CENTRALHenryMOKCPL7/31/20259/1/2027  757575ER/NRBattery/Storage161kV Stilwell-Clinton Line4/30/2021 DISIS STAGE   
GEN-2021-050DISIS-2021-00103 CENTRALHenryMOKCPL7/31/20259/1/2028  200200200ER/NRSolar161kV Stilwell-Clinton Line4/30/2021 DISIS STAGE   
GEN-2021-049DISIS-2021-00102 NEBRASKALancasterNELES7/31/20259/1/2027  225225225ER/NRSolarWagener 115kV Substation4/30/2021 DISIS STAGE   
GEN-2021-048DISIS-2021-00102 NEBRASKALancasterNELES7/31/20259/1/2027  757575ER/NRBattery/StorageWagener 115kV Substation4/30/2021 DISIS STAGE   
GEN-2021-047DISIS-2021-00104 SOUTHEASTMayesOKGRDA3/1/20269/30/2029  250250250ERSolarTulsa (Bus #509852) - Igloo (Bus #513596) 345kV line4/29/2021 DISIS STAGE   
GEN-2021-043DISIS-2021-00102 NEBRASKALancasterNELES2/1/20265/31/2028  250250250ERBattery/Storage8000 SW 12th (Rokeby) Station, 115kV Bus4/30/2021 DISIS STAGE   
GEN-2021-042DISIS-2021-00103 CENTRALJackson MOINDN2/1/20256/1/2028  50100100ER/NRBattery/StorageIndependence Power & Light, Blue Valley Substation, 161kV Bus4/30/2021 DISIS STAGE   
GEN-2021-041DISIS-2021-00104 SOUTHEASTCanadianOKOGE2/1/20256/1/2026  100100.657100.657ER/NRBattery/StorageMustang 138kV Substation4/30/2021 DISIS STAGE   
GEN-2021-040DISIS-2021-00102 NEBRASKACassNEOPPD2/1/202511/30/2029  200200200ERBattery/StorageOPPD District, Cass County Power Plant Substation, 345kV Bus4/30/2021 DISIS STAGE   
GEN-2021-039DISIS-2021-00102 NEBRASKADouglasNEOPPD2/1/20255/31/2030  100100100ERBattery/StorageNew 161kV substation looping in OPPD 161kV lines S1211 to S1220 and S1211 to S12994/30/2021 DISIS STAGE   
GEN-2021-038DISIS-2021-00104 SOUTHEASTTitusTXAEP2/1/20265/31/2028  200201.32201.32ER/NRBattery/StorageWelsh 345kV Substation4/30/2021 DISIS STAGE   
GEN-2021-036DISIS-2021-00104 SOUTHEASTLittle RiverARAEP10/29/202512/31/2027  204.12204.12204.12ER/NRSolarCraig to Patterson 138 kV Transmission Line5/14/2021 DISIS STAGE   
GEN-2021-035DISIS-2021-00103 CENTRALGrantKSSUNC10/29/202512/31/2026  113113113ERSolarTap Sunflower Santana 115kV Transmission Line5/14/2021 DISIS STAGE   
GEN-2021-034DISIS-2021-00102 NEBRASKALancasterNELES10/31/202712/31/2027  113113113ERSolarRokeby 115 kV Substation5/13/2021 DISIS STAGE   
GEN-2021-033DISIS-2021-00104 SOUTHEASTFranklinAROGE7/1/202712/31/2027  204.12204.12204.12ERSolarBranch 161kV Substation 5/14/2021 DISIS STAGE   
GEN-2021-030DISIS-2021-00103 CENTRALLinn KS and Bates MOKSKCPL9/28/202612/31/2026  510.3510.3510.3ERSolarEvergy Tap the La Cygne to Stillwel 345 kV Line5/14/2021 DISIS STAGE   
GEN-2021-029DISIS-2021-00103 CENTRALLinn KS and Bates MOKSKCPL7/1/202612/31/2026  253.8253.8253.8ERBattery/StorageEvergy Tap the La Cygne to Stillwel 345 kV Line5/14/2021 DISIS STAGE   
GEN-2021-027DISIS-2021-00102 NEBRASKALancasterNENPPD7/1/202612/31/2026  102.06102.06102.06ERSolarOlive Creek 115 kV Substation5/14/2021 DISIS STAGE   
GEN-2021-025DISIS-2021-00104 SOUTHEASTWoodwardOKWFEC10/31/202512/1/2026  203.04203.04203.04ERWindWestern Farmers 138kV Mooreland Substation5/14/2021 DISIS STAGE   
GEN-2021-023DISIS-2021-00103 CENTRALGrantKSWERE9/30/202611/30/2026  306.18306.18306.18ERSolarWild Plains 345kV Substation5/14/2021 DISIS STAGE   
GEN-2021-021DISIS-2021-00103 CENTRALStevensKSSPS9/1/202612/31/2027  150150150ERWindCarpenter 345 kV Substation4/20/2021 DISIS STAGE   
GEN-2021-019DISIS-2021-00104 SOUTHEASTNobleOKOGE4/1/202712/31/2028  74.975.8975.89ER/NRBattery/StorageSooner 345 kV4/30/2021 DISIS STAGE   
GEN-2021-018DISIS-2021-00104 SOUTHEASTNobleOKOGE4/1/202712/31/2028  231235.35235.35ERSolarSooner 345 kV4/30/2021 DISIS STAGE   
GEN-2021-017DISIS-2021-00103 CENTRALCloud and MitchellKSITCGP4/1/202512/31/2027  37.537.537.5ERWindElm Creek 345 kV interconnection substation4/30/2021 DISIS STAGE   
GEN-2021-016DISIS-2021-00104 SOUTHEASTJohnston and MurrayOKAEP4/1/202512/31/2029  250250250ERWindSunnyside-Johnston 345 kV4/30/2021 DISIS STAGE   
GEN-2021-015DISIS-2021-00104 SOUTHEASTEllisOKOGE4/1/202712/1/2028  74.975.9175.91ERSolarBobcat 345 kV interconnection substation4/30/2021 DISIS STAGE   
GEN-2021-014DISIS-2021-00104 SOUTHEASTBeckhamOKOGE4/1/202712/31/2029  208233.98233.98ERSolarBorder 345 kV interconnection substation4/30/2021 DISIS STAGE   
GEN-2021-012DISIS-2021-00104 SOUTHEASTBeckhamOKOGE11/15/202312/31/2029  203227227ERBattery/StorageBorder 345 kV interconnection substation4/30/2021 DISIS STAGE   
GEN-2021-010DISIS-2021-00104 SOUTHEASTBeckhamOKOGE4/1/202712/31/2029  208233.98233.98ERSolarBorder 345 kV interconnection substation4/30/2021 DISIS STAGE   
GEN-2021-008DISIS-2021-00101 NORTHMcKenzieNDBEPC5/9/202610/19/2030  200200200ER/NRSolar345kV Bus at BEPC Patent Gate Substation, McKenzie County, ND5/10/2021 DISIS STAGE   
GEN-2021-006DISIS-2021-00103 CENTRALLabetteKSWERE10/1/20252/1/2026  300300300ER/NRBattery/StorageNeosho 345kV substation in Labette County, KS5/7/2021 DISIS STAGE   
GEN-2021-005DISIS-2021-00103 CENTRALSalineKSWERE11/1/20243/1/2025  350350350ER/NRBattery/StorageSummit 345 kV substation in Saline County, KS5/7/2021 DISIS STAGE   
GEN-2021-001DISIS-2021-00104 SOUTHEASTBryanOKOGE9/25/202412/24/2027  100100100ER/NRBattery/Storage138kV Brown Substation12/29/2020 DISIS STAGE   
GEN-2020-SR2Surplus04 SOUTHEASTJohnstonOKOGE12/1/20213/31/2026  100100100ER/NRBattery/StorageBrown 138kV8/4/2020 IA FULLY EXECUTED/ON SCHEDULE  View
GEN-2020-094DISIS-2020-00102 NEBRASKASyracuseNEOPPD4/2/202312/24/2026  250250250ER/NRSolarNeb. City - 103rd & Rokeby 345 kV4/30/2020 DISIS STAGE   
GEN-2020-092DISIS-2020-00104 SOUTHEASTMayes CountyOKAEP11/2/202511/19/2026  100100100ER/NRSolarPryor Junction - Midwest Carbide 138kV line 4/30/2020 DISIS STAGE   
GEN-2020-091DISIS-2020-00101 NORTHMcKenzieNDBEPC11/2/202511/19/2026  150150150ER/NRSolarPatent Gate Substation 345 kV4/30/2020 DISIS STAGE   
GEN-2020-090DISIS-2020-00103 CENTRALBourbonKSWERE4/1/202612/1/2026  204.3204.3204.3ER/NRBattery/StorageWolf Creek - Blackberry 345 kV Substation4/27/2020 DISIS STAGE   
GEN-2020-088DISIS-2020-00103 CENTRALJasperMOEDE11/30/202212/31/2025  150150150ER/NRSolarLa Russell 161 kV Substation4/30/2020 DISIS STAGE   
GEN-2020-087DISIS-2020-00104 SOUTHEASTComancheOKAEP5/1/202310/1/2026  500500500ER/NRSolarCimmarron to Lawton 345 kV Line4/23/2020 DISIS STAGE   
GEN-2020-085DISIS-2020-00104 SOUTHEASTCarterOKAEP4/2/202310/1/2026  500500500ER/NRSolarLawton to Sunnyside 345 kV Line4/23/2020 DISIS STAGE   
GEN-2020-084DISIS-2020-00102 NEBRASKABurtNEOPPD4/1/202210/31/2026  350350350ER/NRSolarRaun - Fort Calhoun 345 kV4/30/2020 DISIS STAGE   
GEN-2020-083DISIS-2020-00101 NORTHFairviewMTWAPA10/1/202412/1/2026  74.574.574.5ER/NRHybridSolar/StorageFairview 115kV Substation4/30/2020 DISIS STAGE   
GEN-2020-081DISIS-2020-00104 SOUTHEASTRuskTXAEP5/1/20226/1/2028  200200200ER/NRBattery/StorageTenaska Switching Substation 345kV4/30/2020 DISIS STAGE   
GEN-2020-079DISIS-2020-00103 CENTRALCherokee KSEDE7/1/202512/31/2025  225225225ER/NRHybridSolar/StorageRiverton-Neosho 161kV line4/30/2020 DISIS STAGE   
GEN-2020-078DISIS-2020-00102 NEBRASKAWashingtonNEOPPD11/30/202212/31/2025  100100100ER/NRSolarSubstation 1226 to Substation 1237, 161kV Tap4/30/2020 DISIS STAGE   
GEN-2020-075DISIS-2020-00104 SOUTHEASTComancheOKAEP5/1/202310/1/2026  200200200ER/NRBattery/StorageCimmarron to Lawton 345 kV Line4/28/2020 DISIS STAGE   
GEN-2020-074DISIS-2020-00104 SOUTHEASTCarterOKAEP3/31/202310/1/2026  200200200ER/NRBattery/StorageLawton to Sunnyside 345 kV Substation4/28/2020 DISIS STAGE   
GEN-2020-073DISIS-2020-00103 CENTRALFranklinKSKCPL7/1/202512/1/2027  150150150ER/NRHybridSolar/StorageSE Ottawa to Pleasant Valley 161kV4/30/2020 DISIS STAGE   
GEN-2020-072DISIS-2020-00103 CENTRALWindsorMOGMO7/1/202512/1/2027  150150150ER/NRHybridSolar/StorageWindsor to AEC Sedalia 161 kV line4/30/2020 DISIS STAGE   
GEN-2020-069DISIS-2020-00102 NEBRASKACherryNENPPD11/30/202311/30/2025  52.8552.8552.85ER/NRWindCody to Valentine 115kV line4/24/2020 DISIS STAGE   
GEN-2020-068DISIS-2020-00105 SOUTHWESTTerry & HockleyTXSPS11/1/202412/1/2026  400400400ERSolarTuco to Yoakum 345kV line4/29/2020 DISIS STAGE   
GEN-2020-067DISIS-2020-00105 SOUTHWESTTerry & HockleyTXSPS11/1/202412/1/2026  352.5352.5352.5ERWindTuco to Yoakum 345kV line4/24/2020 DISIS STAGE   
GEN-2020-065DISIS-2020-00105 SOUTHWESTGainesNMSPS12/1/20255/15/2028  1003912.31003ERThermalCombined CycleHobbs-Andrews 345 kV Line4/30/2020 DISIS STAGE   
GEN-2020-064DISIS-2020-00103 CENTRALJoplinMOEDE10/1/20205/17/2021  643664ER/NRThermalCT4544 Stateline CC 161kV Substation4/22/2020 DISIS STAGE   
GEN-2020-062DISIS-2020-00105 SOUTHWESTCurryNMSPS11/1/20234/1/2028  256256256ERSolarOASIS 230kV Substation4/29/2020 DISIS STAGE   
GEN-2020-061DISIS-2020-00103 CENTRALPleasant HillMOGMO5/1/20215/1/2022  292921ER/NRThermalGasPleasant Hill 345/161/69 kV Substation4/28/2020 DISIS STAGE   
GEN-2020-060DISIS-2020-00105 SOUTHWESTLubbockTXSPS5/1/20266/1/2027  200200200ERBattery/StorageLubbock East Substation 230 kV4/30/2020 DISIS STAGE   
GEN-2020-059DISIS-2020-00105 SOUTHWESTLovingtonNMSPS3/2/20256/1/2027  250250250ERHybridSolar/StorageTuco-Yoakum-Hobbs 345 kV4/29/2020 DISIS STAGE   
GEN-2020-058DISIS-2020-00103 CENTRALGarnerKSWERE11/1/20266/1/2028  424.5424.5424.5ER/NRSolarAtlantic 345 kV Substation4/30/2020 DISIS STAGE   
GEN-2020-057DISIS-2020-00103 CENTRALGarnerKSWERE11/1/20266/1/2028  424.5424.5424.5ER/NRBattery/StorageAtlantic 345 kV Substation4/30/2020 DISIS STAGE   
GEN-2020-056DISIS-2020-00103 CENTRALRussell CountyKSSUNC3/30/20231/3/2025  202020ER/NRSolarRussell 115 kV Substation4/30/2020 DISIS STAGE   
GEN-2020-054DISIS-2020-00104 SOUTHEASTBowie CountyTXAEP8/1/20239/1/2026  298298298ER/NRSolarLydia 345 kV Station4/27/2020 DISIS STAGE   
GEN-2020-045DISIS-2020-00102 NEBRASKADouglas CountyNEOPPD4/30/20238/1/2024  56.5256.5256.52ERThermalReciprocating EngineBetween Substation 1209 and 1252; 161kV4/29/2020 DISIS STAGE ViewView
GEN-2020-044DISIS-2020-00102 NEBRASKADouglas CountyNEOPPD4/30/20238/1/2024  56.5256.5256.52ERThermalReciprocating EngineBetween Substation 1209 and 1252; 161kV4/29/2020 DISIS STAGE ViewView
GEN-2020-043DISIS-2020-00102 NEBRASKADouglas CountyNEOPPD4/30/20238/1/2024  56.5256.5256.52ERThermalReciprocating EngineBetween Substation 1209 and 1252; 161kV4/29/2020 DISIS STAGE ViewView
GEN-2020-038DISIS-2020-00102 NEBRASKAPlattsmouthNEOPPD4/30/20234/21/2028  272.7258303ERThermalCTSubstation 3740; 345kV4/29/2020 DISIS STAGE   
GEN-2020-031DISIS-2020-00102 NEBRASKASarpy CountyNEOPPD4/30/20234/21/2028  272.7258303ERThermalCTSubstation 1363; 161kV Substation4/29/2020 DISIS STAGE   
GEN-2020-028DISIS-2020-00102 NEBRASKASarpy CountyNEOPPD4/30/20238/1/2024  255235255ERThermalCTSubstation 1363; 161kV Substation4/29/2020 DISIS STAGE ViewView
GEN-2020-025DISIS-2020-00102 NEBRASKASarpy CountyNEOPPD4/30/20238/1/2024  255235255ERThermalCTSubstation 1363; 161kV Substation4/29/2020 DISIS STAGE ViewView
GEN-2020-021DISIS-2020-00101 NORTHSioux CountyNDBEPC11/30/202312/31/2026  235235235ER/NRWindLeLand Olds-Chapelle Creek 345kV line 4/24/2020 DISIS STAGE   
GEN-2020-020DISIS-2020-00104 SOUTHEASTMcCurtainOKAEP5/15/202512/15/2025  201.6201.6201.6ER/NRHybridSolar/StorageTap the 345 kV Northwest Texarkana - Valliant line4/28/2020 DISIS STAGE   
GEN-2020-017DISIS-2020-00105 SOUTHWESTLamb CountyTXSPS10/1/202512/31/2025  74.8874.8874.88ER/NRSolar230kV Lamb County Interchange4/24/2020 DISIS STAGE   
GEN-2020-014DISIS-2020-00101 NORTHAlexanderNDBEPC6/17/202110/18/2021  454545ER/NRThermalGasLonesome Creek 115kV4/20/2020 DISIS STAGE   
GEN-2020-013DISIS-2020-00102 NEBRASKAOrleansNENPPD10/15/20266/1/2027  215215215ER/NRHybridSolar/StorageOrleans-Holdrege Substation 115kV4/10/2020 DISIS STAGE   
GEN-2020-012DISIS-2020-00104 SOUTHEASTHeadrickOKAEP10/15/20266/1/2027  113113113ER/NRHybridSolar/StorageSnyder – Altus Jct. 138kV4/10/2020 DISIS STAGE   
GEN-2020-011DISIS-2020-00102 NEBRASKAFunkNENPPD10/15/20266/1/2027  320320320ER/NRHybridSolar/StorageAxtell-Sweetwater Substation 345kV4/8/2020 DISIS STAGE   
GEN-2020-010DISIS-2020-00104 SOUTHEASTMutualOKWFEC10/15/20266/1/2027  140140140ER/NRHybridSolar/StorageSeiling-Taloga Substations 138kV4/8/2020 DISIS STAGE   
GEN-2020-009DISIS-2020-00105 SOUTHWESTCottonOKAEP10/15/202612/31/2025  300300300ER/NRHybridSolar/StorageLawton East Side to Oklaunion 345kV4/8/2020 DISIS STAGE   
GEN-2020-008DISIS-2020-00103 CENTRALStevens CountyKSSPS9/1/202312/31/2026  250250250ERHybridSolar/StorageCorporation Carpenter 345kV Substation4/22/2020 DISIS STAGE   
GEN-2020-007DISIS-2020-00103 CENTRALLinn & BatesKSKCPL7/1/202312/31/2025  650650650ER/NRHybridSolar/StorageEvergy La Cygne to Wolf Creek 345kV Substation4/22/2020 DISIS STAGE   
GEN-2020-003DISIS-2020-00103 CENTRALWinfieldKSKPP3/1/20236/1/2025  585858ER/NRThermalDiesel/GasEast Substation 69 kV4/1/2020 DISIS STAGE   
GEN-2020-002DISIS-2020-00102 NEBRASKAYutanNEOPPD11/15/20225/1/2024  818181ERSolar6846 Substation 69 kV4/6/2020 DISIS STAGE ViewView
GEN-2019-073DISIS-2019-00102 NEBRASKAMadisonNENPPD12/31/202312/31/2027  100100100ERSolarShell Creek-Hoskins 345kv Line5/24/2019 DISIS STAGE   
GEN-2019-070DISIS-2019-00102 NEBRASKAMadisonNENPPD12/31/202312/31/2027  505050ERSolarShell Creek-Hoskins 345kv Line5/24/2019 DISIS STAGE   
GEN-2019-069DISIS-2019-00102 NEBRASKAMadisonNENPPD12/31/202312/31/2027  100100100ERSolarShell Creek-Hoskins 345kV Line5/24/2019 DISIS STAGE   
GEN-2019-068DISIS-2019-00103 CENTRALBartonKSSUNC6/1/20235/1/2026  505050ER/NRBattery/StorageGreat Bend - Circle 230kV line5/24/2019 DISIS STAGE   
GEN-2019-065DISIS-2019-00104 SOUTHEASTSmithTXAEP6/1/202412/1/2026  180180180ERBattery/StorageOverton-Northwest Henderson 138kV5/23/2019 DISIS STAGE   
GEN-2019-063DISIS-2019-00103 CENTRALFord, ClarkKSITCGP6/1/20235/1/2026  505050ER/NRBattery/StorageClark County 345kV substation5/24/2019 DISIS STAGE   
GEN-2019-058DISIS-2019-00103 CENTRALFord, ClarkKSITCGP6/1/20235/1/2026  150150150ER/NRSolarClark County 345kV substation5/24/2019 DISIS STAGE   
GEN-2019-055DISIS-2019-00103 CENTRALEdwards, PawneeKSSUNC6/1/20235/1/2026  150150150ER/NRSolarGreat Bend-Spearville 230kV line5/24/2019 DISIS STAGE   
GEN-2019-054DISIS-2019-00103 CENTRALBartonKSSUNC6/1/20235/1/2026  150150150ER/NRSolarGreat Bend- Circle 230kV line5/24/2019 DISIS STAGE   
GEN-2019-053DISIS-2019-00103 CENTRALEdwards/PawneeKSSUNC6/1/20235/1/2026  505050ER/NRBattery/StorageGreat Bend-Spearville 230kV line5/24/2019 DISIS STAGE   
GEN-2019-051DISIS-2019-00103 CENTRALBartonKSSUNC6/1/20235/1/2026  404040ER/NRBattery/StorageFrey St 115kV bus5/24/2019 DISIS STAGE   
GEN-2019-048DISIS-2019-00103 CENTRALJacksonMOKCPL12/31/202212/31/2027  505050ERBattery/StorageDuncan 69kV substation5/24/2019 DISIS STAGE   
GEN-2019-045DISIS-2019-00104 SOUTHEASTWoodsOKOGE12/31/202212/31/2027  155155155ERSolarDeGrasse 138kV Substation5/24/2019 DISIS STAGE   
GEN-2019-044DISIS-2019-00103 CENTRALFordKSSUNC12/31/202312/15/2027  100100100ERSolarNorth Fort Dodge 115kV Substation5/24/2019 DISIS STAGE   
GEN-2019-041DISIS-2019-00102 NEBRASKALancasterNENPPD12/1/202012/31/2026  787878ER/NRSolar115kV Monolith Substation5/23/2019 DISIS STAGE   
GEN-2019-039DISIS-2019-00102 NEBRASKAButlerNENPPD5/16/20225/1/2025  174.5174.5174.5ER/NRSolarColumbus Southeast-Rising City 115kV5/21/2019 DISIS STAGE   
GEN-2019-037DISIS-2019-00101 NORTHMercerNDBEPC12/1/202312/1/2027  150150150ER/NRSolarLeland Olds 345kV substation5/17/2019 DISIS STAGE   
GEN-2019-035DISIS-2019-00103 CENTRALBarryMOEDE12/31/202212/31/2025  808080ER/NRSolarReeds Spring-Aurora 161kV Line5/2/2019 DISIS STAGE   
GEN-2019-030DISIS-2019-00103 CENTRALFordKSITCGP12/1/20213/31/2027  252252252ER/NRWindSpearville to Clark County 345 kV line4/25/2019 DISIS STAGE   
GEN-2019-023DISIS-2019-00101 NORTHWibauxMTWAPA12/31/20236/1/2025  110110110ER/NRHybridWind/StorageWAPA-UGP Mingusville 230kV5/8/2019 DISIS STAGE   
GEN-2019-021DISIS-2019-00105 SOUTHWESTRooseveltNMSPS12/1/20226/1/2025  505050ER/NRSolarRoosevelt 230kV Substation4/29/2019 DISIS STAGE   
GEN-2019-019DISIS-2019-00101 NORTHSiouxIANIPCO2/1/20202/16/2023  15.1515.1515.15ER/NRThermalGas TurbineSiouxland 69kV4/24/2019 DISIS STAGE    
GEN-2019-018DISIS-2019-00103 CENTRALRiceKSMIDW3/1/20206/1/2021  15.5611.9715.56ER/NRThermalGas TurbineSaxman 115kV substation4/24/2019 DISIS STAGE   
GEN-2019-016DISIS-2019-00103 CENTRALPolk and DadeMOEDE11/30/202212/31/2026  200200200ERSolarDadeville 161kV Substation 4/30/2019 DISIS STAGE   
GEN-2019-013DISIS-2019-00104 SOUTHEASTRoger MillsOKAEP12/31/20215/1/2026  505050ER/NRBattery/StorageDempsey 230kV sub/Sweetwater 230kV4/24/2019 DISIS STAGE   
GEN-2019-012DISIS-2019-00104 SOUTHEASTWoodwardOKOGE5/1/20235/1/2027  200200200ER/NRBattery/StorageWoodward 345kV substation5/22/2019 DISIS STAGE   
GEN-2019-011DISIS-2019-00105 SOUTHWESTYoakumTXSPS5/1/20235/1/2025  207207207ER/NRBattery/StorageYoakum 345kV Substation4/22/2019 DISIS STAGE   
GEN-2019-009DISIS-2019-00102 NEBRASKANemahaNEOPPD10/31/202211/30/2026  100100100ERSolarS1263 Brock 161kV substation4/24/2019 DISIS STAGE   
GEN-2019-003DISIS-2019-00105 SOUTHWESTRooseveltNMSPS12/1/20226/1/2025  150150150ER/NRSolarRoosevelt 230kV Substation4/19/2019 DISIS STAGE   
GEN-2019-002DISIS-2019-00104 SOUTHEASTMayesOKGRDA12/1/20206/1/2025  100100100ERBattery/StorageMaid 161kV substation11/26/2018 DISIS STAGE   
GEN-2019-001DISIS-2019-00103 CENTRALPrattKSWERE12/31/201812/31/2026  252525ERWindThistle-Wichita Dbl Ckt (Buffalo Flats) 345kV11/27/2018 DISIS STAGE   
GEN-2018-132DISIS-2018-00202 NEBRASKAPierceNENPPD12/31/202012/31/2026  201.6201.6201.6ER/NRSolarAntelope - Hoskins 345 kV11/21/2018 DISIS STAGE   
GEN-2018-131DISIS-2018-00202 NEBRASKAPierceNENPPD12/31/202012/31/2026  221.4221.4221.4ER/NRSolarAntelope - Hoskins 345 kV11/21/2018 DISIS STAGE   
GEN-2018-128DISIS-2018-00203 CENTRALSumnerKSWERE9/1/202110/1/2027  200.22200.22200.22ER/NRWindRenfrow-Viola 345 kV11/19/2018 DISIS STAGE   
GEN-2018-125DISIS-2018-00202 NEBRASKALincolnNENPPD12/15/202212/1/2027  231231231ER/NRWindNew switching station on Gentleman to Sweetwater 345kV line11/19/2018 DISIS STAGE   
GEN-2018-116DISIS-2018-00203 CENTRALBartonKSSUNC12/31/20225/1/2026  150150150ER/NRSolarFrey Street 115kV bus11/20/2018 DISIS STAGE   
GEN-2018-115DISIS-2018-00204 SOUTHEASTLawtonOKAEP12/1/202112/1/2027  250250250ER/NRHybridSolar/StorageLawton East Side 345kV/138kv Substation11/21/2018 DISIS STAGE   
GEN-2018-108DISIS-2018-00203 CENTRALBarberKSITCGP12/31/202712/31/2027  959595ERBattery/StorageThistle 345kV substation11/21/2018 DISIS STAGE   
GEN-2018-106DISIS-2018-00204 SOUTHEASTCaddoLAAEP12/31/202312/31/2027  165165165ERSolarLongwood 345kV substation11/2/2018 DISIS STAGE   
GEN-2018-099DISIS-2018-00205 SOUTHWESTParmerTXSPS12/31/202312/31/2027  300300300ERWindTolk 230kV Substation11/21/2018 DISIS STAGE   
GEN-2018-089DISIS-2018-00205 SOUTHWESTCastroTXSPS12/31/202312/31/2027  196196196ERWindNewhart 230kV Substation11/21/2018 DISIS STAGE   
GEN-2018-088DISIS-2018-00204 SOUTHEASTBowieTXAEP12/31/202312/15/2027  130130130ERSolarLydia 345kV substation11/21/2018 DISIS STAGE   
GEN-2018-083DISIS-2018-00202 NEBRASKAMadisonNENPPD12/31/202312/31/2027  250250250ERWindShell Creek-Hoskins 345kv Line Break11/16/2018 DISIS STAGE   
GEN-2018-082DISIS-2018-00204 SOUTHEASTPittsburgOKAEP12/31/202312/31/2027  215215215ERWindPittsburg 345kV Substation11/18/2018 DISIS STAGE   
GEN-2018-079DISIS-2018-00204 SOUTHEASTCraig/NovataOKAEP12/31/202312/31/2027  148148148ERSolarFarmland-Delaware 138kV line11/18/2018 DISIS STAGE   
GEN-2018-074DISIS-2018-00201 NORTHCrawford and Carrol IAWAPA5/10/202210/31/2026  727272ERWindDenison 230kV Substation10/31/2018 DISIS STAGE   
GEN-2018-072DISIS-2018-00204 SOUTHEASTKayOKOGE11/30/202111/30/2025  151151151ER/NRBattery/StorageInterconnecting into OG&E's Ranch Road 345kV substation by tapping a 0.1 gen tie line into the existing Frontier II gen-tie line10/26/2018 DISIS STAGE   
GEN-2018-071DISIS-2018-00204 SOUTHEASTKayOKOGE11/30/202111/30/2025  151151151ER/NRBattery/StorageInterconnecting into OG&E's Ranch Road 345kV substation by tapping a 0.1 gen tie line into the existing Frontier II gen-tie line10/25/2018 DISIS STAGE   
GEN-2018-069DISIS-2018-00201 NORTHWibauxMTWAPA12/31/20206/1/2025  125125125ER/NRWindWAPA-UGP Mingusville 230kV10/26/2018 DISIS STAGE   
GEN-2018-068DISIS-2018-00202 NEBRASKAMadisonNENPPD9/1/202212/1/2027  302.4302.4302.4ER/NRWindAntelope - Hoskins 345 kV Substation10/26/2018 DISIS STAGE   
GEN-2018-067DISIS-2018-00201 NORTHWilliamsNDMWEC10/30/202010/30/2026  255255255ERWind115kV Strandahl sub 10/25/2018 DISIS STAGE   
GEN-2018-065DISIS-2018-00202 NEBRASKAMadisonNENPPD7/1/202012/1/2027  19.819.819.8ER/NRWindAntelope - Hoskins 345 kV Substation10/24/2018 DISIS STAGE   
GEN-2018-064DISIS-2018-00204 SOUTHEASTBenton CountyARGRDA6/30/202112/31/2025  808080ER/NRSolarTonnece Substation 69kV10/24/2018 DISIS STAGE   
GEN-2018-063DISIS-2018-00203 CENTRALGreeneMOEDE6/30/202112/31/2026  575757ERSolarSedalia Marshfield Springfield Nichols Street 69kV circuit10/23/2018 DISIS STAGE   
GEN-2018-060DISIS-2018-00102 NEBRASKAWebsterNENPPD12/1/202012/31/2026  505050ER/NRWindAxtell-Post Rock 345 kV5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-057DISIS-2018-00103 CENTRALSedgwickKSWERE5/15/20295/15/2029  203.4203.4203.4ER/NRSolarGordon Evans 138kV5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-055DISIS-2018-00104 SOUTHEASTGradyOKAEP12/31/202012/31/2026  252252252ER/NRSolarTerry Road 345kV station (shared with Rush Springs Windfarm on a common gentie) 5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-052DISIS-2018-00105 SOUTHWESTLeaNMSPS12/31/202112/31/2026  707070ERBattery/StorageRoadrunner 115kV Substation5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-050DISIS-2018-00104 SOUTHEASTCaddoLAAEP12/31/20214/15/2027  200200200ERSolarLongwood 345kV Substation5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-049DISIS-2018-00103 CENTRALSumnerKSITCGP12/31/20214/1/2027  120120120ERSolarThistle 345kV Substation5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-048DISIS-2018-00104 SOUTHEASTCaddoOKOGE12/31/202112/15/2027  300300300ERSolarPecan Creek 345kV Substation5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-043DISIS-2018-00102 NEBRASKABurtNEOPPD12/31/202112/15/2028  500500500ERSolarFt. Calhoun - Raun 345 kV Line Break5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-037DISIS-2018-00102 NEBRASKADouglasNEOPPD12/31/20245/31/2030  100100100ERBattery/StorageLooping in OPPD (S1211) (S1220) (S1211) (S1299) 161kV5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-033DISIS-2018-00102 NEBRASKACassNEOPPD12/31/202311/30/2029  200200200ERBattery/StorageCass County 345kV Substation5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-032DISIS-2018-00103 CENTRALMcPhearsonKSWERE12/1/20215/1/2029  310310310ERWindNeosho 345kV Substation5/29/2018 IA FULLY EXECUTED/ON SUSPENSION   
GEN-2018-031DISIS-2018-00103 CENTRALJacksonMOINDN12/31/20245/31/2028  505050ERBattery/StorageBlue Valley 161kV Substation5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-029DISIS-2018-00104 SOUTHEASTOklahomaOKOGE10/15/20235/31/2028  100100100ERBattery/StorageHorseshoe Lake 138kV Substation5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-028DISIS-2018-00104 SOUTHEASTTulsaOKAEP10/15/20235/31/2028  200200200ERBattery/StorageTulsa North 138kV Substation5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-027DISIS-2018-00104 SOUTHEASTTulsaOKAEP12/31/20245/31/2028  100100100ERBattery/StorageTulsa Power Station 138kV Substation5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-026DISIS-2018-00104 SOUTHEASTCanadianOKOGE10/15/20235/31/2026  100100100ERBattery/StorageMustang 138kV Substation5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-025DISIS-2018-00102 NEBRASKAWashington NEOPPD10/15/202311/30/2028  200200200ERBattery/StorageFort Calhoun 345kV Substation5/29/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-024DISIS-2018-00104 SOUTHEASTMuskogeeOKOGE10/15/202312/31/2028  100100100ERBattery/StorageCanadian River-Muskogee and Muskogee-Seminole 345kV5/28/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-021DISIS-2018-00104 SOUTHEASTWashitaOKAEP12/1/202312/31/2024  74.174.174.1ER/NRSolarChisholm-Gracemont 345kV Line5/24/2018 IA PENDING   
GEN-2018-015DISIS-2018-00105 SOUTHWESTPaducahTXSPS10/31/202111/1/2027  252252252ER/NRSolarTuco-Oklaunion 345kV Line4/27/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-013DISIS-2018-00103 CENTRALDickinsonKSWERE12/30/202412/31/2026  74.174.174.1ERWindAbilene Energy Center-Northview 115kV Line4/27/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-011DISIS-2018-00104 SOUTHEASTKingfisherOKWFEC12/1/202012/31/2027  74.174.174.1ER/NRBattery/StorageDover 138 kV Switching Station4/27/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-010DISIS-2018-00101 NORTHMontrailNDBEPC12/1/202112/31/2026  74.174.174.1ER/NRBattery/StorageNeset 230kV Substation4/27/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-009DISIS-2018-00103 CENTRALSeward/MeadeKSSUNC7/15/202512/31/2028  150150150ERWindCimarron 115kV Substation4/27/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-004DISIS-2018-00105 SOUTHWESTLeaNMSPS12/31/20193/1/2027  74.9974.9974.99ERSolarT14 Circuit 115kV line4/26/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2018-003DISIS-2018-00104 SOUTHEASTBowieTXAEP12/31/20216/1/2027  150150150ER/NRSolarNorth Boston-Bann 138kV Line4/25/2018 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-239IFS-2017-002-76DISIS-2017-00205 SOUTHWESTYoakumTXSPS6/1/20235/1/2026  300300300ERSolarMahoney 230kV Substation11/30/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-234IFS-2017-002-73DISIS-2017-00202 NEBRASKAGreeleyNENPPD12/31/201912/31/2024  115115115ERWindSpalding to North Loup 115kV11/6/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-233IFS-2017-002-72DISIS-2017-00204 SOUTHEASTGradyOKOGE12/1/202012/31/2027  215215215ER/NRWindMinco 345kV11/28/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-232IFS-2017-002-71DISIS-2017-00204 SOUTHEASTBryan CountyOKOGE6/1/20203/31/2026  52.252.252.2ER/NRSolarBrown 138kV Substation11/28/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-231IFS-2017-002-70DISIS-2017-00204 SOUTHEASTFranklin CountyAROGE6/1/20206/1/2026  72.572.572.5ER/NRSolarBranch 161kV Substation11/28/2017 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-230IFS-2017-002-69DISIS-2017-00204 SOUTHEASTLincoln CountyOKOGE6/1/20205/1/2026  72.572.572.5ER/NRSolarTryon 138kV Substation11/28/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-227IFS-2017-002-67DISIS-2017-00203 CENTRALSedwick CountyKSWERE12/31/20205/15/2029  201.6201.6201.6ER/NRBattery/StorageGordon Evans 138kV Substation11/30/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-226IFS-2017-002-66DISIS-2017-00203 CENTRALSedgwick CountyKSWERE12/1/20205/15/2029  201.6201.6201.6ER/NRSolarGordon Evans 138kV Substation11/30/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-222IFS-2017-002-64DISIS-2017-00201 NORTHDenisonIAWAPA10/6/20202/2/2027  180180180ERWindDenison 230kV Substation11/30/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-221IFS-2017-002-63DISIS-2017-00203 CENTRALSedgwickKSWERE12/31/20203/30/2029  152152152ER/NRBattery/StorageBuffalo Flats 345kV Substation11/30/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-220IFS-2017-002-62DISIS-2017-00203 CENTRALSedgwickKSWERE12/1/202012/31/2029  201.6201.6201.6ER/NRSolarBuffalo Flats 345kV Substation11/30/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-215IFS-2017-002-60DISIS-2017-00201 NORTHWardNDBEPC12/1/202012/31/2030  100100100ER/NRWindLogan 230kV Substation11/30/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-214IFS-2017-002-59DISIS-2017-00201 NORTHWardNDBEPC12/1/202012/31/2030  100100100ER/NRWindLogan 230kV Substation11/30/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-210IFS-2017-002-57DISIS-2017-00202 NEBRASKACedarNENPPD12/1/202112/1/2026  310310310ERHybridSolarMcCool 345kV Substation11/30/2017 IA FULLY EXECUTED/ON SUSPENSION View 
GEN-2017-203IFS-2017-002-55DISIS-2017-00204 SOUTHEASTGrant/KayOKOGE7/1/202312/31/2026  210210210ERHybridSolarRenfrow 345kV Substation11/30/2017 IA FULLY EXECUTED/ON SUSPENSION View 
GEN-2017-201IFS-2017-002-53DISIS-2017-00202 NEBRASKAWayne CountyNENPPD12/1/202212/31/2028  250250250ER/NRWindHoskins 345kV Substation11/30/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-198IFS-2017-002-50DISIS-2017-00202 NEBRASKAOmahaNEOPPD12/1/20225/31/2026  11.6411.6411.64ERBattery/StorageJones St. No 1201 69kV substation11/30/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-196IFS-2017-002-49DISIS-2017-00203 CENTRALJohnsonKSKCPL12/1/202012/1/2030  128128128ER/NRBattery/StorageWest Gardner 345kV11/30/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-195IFS-2017-002-48DISIS-2017-00203 CENTRALJohnsonKSKCPL12/1/202012/1/2030  500.4500.4500.4ER/NRSolarWest Gardner 345kV11/30/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-188IFS-2017-002-44DISIS-2017-00203 CENTRALBarryMOEDE12/31/20206/15/2026  130130130ERSolarAsbury 161 kV11/30/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-187IFS-2017-002-43DISIS-2017-00205 SOUTHWESTTerryTXSPS12/31/20206/1/2026  150150150ERSolarFlatland 115 kV Substation11/30/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-184IFS-2017-002-42DISIS-2017-00203 CENTRALHodgeman/FordKSKCPL12/1/20216/1/2029  400400400ER/NRSolarNashua-St. Joe 345kV11/29/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-183IFS-2017-002-41DISIS-2017-00203 CENTRALHodgeman/FordKSKCPL12/1/20216/1/2029  400400400ER/NRWindNashua-St. Joe 345kV11/29/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-182IFS-2017-002-40DISIS-2017-00202 NEBRASKALancasterNENPPD12/1/20202/4/2025  128128128ER/NRWindTobias 345kV Substation11/29/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-181IFS-2017-002-39DISIS-2017-00202 NEBRASKALancasterNENPPD12/1/202012/8/2024  300300300ER/NRWindTobias 345kV Substation11/29/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-178IFS-2017-002-37DISIS-2017-00204 SOUTHEASTGarfieldOKOGE12/31/202012/1/2025  525252ER/NRBattery/StorageWoodring 345kV Substation11/29/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-175IFS-2017-002-36DISIS-2017-00201 NORTHTurnerSDWAPA9/30/202312/1/2026  300300300ERWindVfodnes-Utica Jct. 230kV11/29/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-173IFS-2017-002-35DISIS-2017-00204 SOUTHEASTStephenOKAEP12/1/202012/31/2027  505050ER/NRSolarLawton Eastside - Terry Road 345kV11/29/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-172IFS-2017-002-34DISIS-2017-00204 SOUTHEASTStephenOKAEP12/1/202012/31/2027  505050ER/NRSolarLawton Eastside - Terry Road 345kV11/29/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-171IFS-2017-002-33DISIS-2017-00204 SOUTHEASTStephenOKAEP12/1/202012/31/2027  150150150ER/NRSolarLawton Eastside - Terry Road 345kV11/29/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-164IFS-2017-002-28DISIS-2017-00204 SOUTHEASTGarfieldOKOGE12/1/202012/31/2025  250250250ER/NRSolarWoodring 345kV Substation11/29/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-158IFS-2017-002-27DISIS-2017-00205 SOUTHWESTParmer/CastroTXSPS12/31/20208/30/2026  265265265ERWindTolk 230kV Substation11/29/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-151IFS-2017-002-23DISIS-2017-00205 SOUTHWESTCrosbyTXSPS10/31/202010/15/2026  300300300ERWindTUCO-Oklaunion 345kV11/28/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-150IFS-2017-002-22DISIS-2017-00204 SOUTHEASTGradyOKOGE12/1/202012/31/2026  250250250ER/NRSolarMinco 345kV11/28/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-149IFS-2017-002-21DISIS-2017-00204 SOUTHEASTJohnstonOKOGE12/1/202012/31/2027  258258258ER/NRWindJohnson County 345kV Substation11/27/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-146IFS-2017-002-19DISIS-2017-00205 SOUTHWESTCastroTXSPS10/31/202010/15/2026  151.8151.8151.8ERWindDeaf Smith-Plant X 230kV11/27/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-144IFS-2017-002-18DISIS-2017-00202 NEBRASKAHolt, Antelope, WheelerNENPPD12/31/202112/31/2025  200200200ERWindHolt County 345kV11/27/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-141IFS-2017-002-17DISIS-2017-00204 SOUTHEASTWagonerOKAEP12/1/202012/31/2027  241.7241.7241.7ER/NRSolarClarksville 345kV Switching Station11/22/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-140IFS-2017-002-16DISIS-2017-00204 SOUTHEASTWagonerOKAEP12/1/202012/31/2027  160160160ER/NRSolarClarksville 345kV Switching Station11/22/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-137IFS-2017-002-15DISIS-2017-00204 SOUTHEASTOklahomaOKOGE12/1/202012/31/2028  295295295ER/NRWindArcadia 345kV11/22/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-134IFS-2017-002-14DISIS-2017-00204 SOUTHEASTOklahomaOKOGE12/1/202012/31/2028  250250250ER/NRWindArcadia 345kV11/22/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-133IFS-2017-002-13DISIS-2017-00204 SOUTHEASTOklahomaOKOGE12/1/202012/31/2028  200200200ER/NRWindArcadia 345kV11/22/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-131IFS-2017-002-11DISIS-2017-00203 CENTRALWilsonKSWERE12/1/20202/1/2026  29.629.629.6ER/NRBattery/StorageAltoona- NE Parson 138kV11/22/2017 IA FULLY EXECUTED/ON SUSPENSION View 
GEN-2017-121IFS-2017-002-08DISIS-2017-00203 CENTRALSumnerKSWERE12/1/202112/1/2026  200200200ER/NRWindSumner 138kV11/17/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-120IFS-2017-002-07DISIS-2017-00203 CENTRALDickinson/MarionKSWERE5/1/202712/31/2027  260260260ERWindAbilene Energy Center-Northview 115kV11/17/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-119IFS-2017-002-06DISIS-2017-00203 CENTRALCloud/MitchellKSSUNC5/1/202412/31/2027  180180180ERWindElm Creek 345kV substation11/17/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-117IFS-2017-002-05DISIS-2017-00204 SOUTHEASTCanadianOKWFEC12/1/202012/1/2026  19.819.819.8ER/NRBattery/StorageEl Reno SW 138kV11/17/2017 IA FULLY EXECUTED/ON SUSPENSION View 
GEN-2017-115IFS-2017-002-04DISIS-2017-00203 CENTRALAtchinson/NodawayMOKCPL5/1/202712/31/2026  244244244ERWindHolt County 345 kV11/10/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-108IFS-2017-002-02DISIS-2017-00203 CENTRALHenry CountyMOKCPL12/1/20223/1/2027  400400400ER/NRSolarStillwell - Clinton 161kV Line8/26/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-105IFS-2017-002-01DISIS-2017-00202 NEBRASKABurt CountyNEOPPD12/15/201812/20/2026  757575ER/NRWindTekamah - Raun 161 kV Line7/12/2017 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2017-100IFS-2017-001-20DISIS-2017-00105 SOUTHWESTTexas CountyOKSPS12/31/201912/1/2025  102.6102.6102.6ER/NRSolarTexas County 115kV5/31/2017 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2017-097IFS-2017-001-24DISIS-2017-00101 NORTHPennington CountySDWAPA1/9/20226/29/2024  128128128ERSolarUnderwood 115 kV Sub5/31/2017 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2017-094IFS-2017-001-31DISIS-2017-00101 NORTHWessington/Hand CountiesSDWAPA10/6/202011/1/2023  200200200ERWindFort Thompson-Huron 230 kV5/24/2017 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2017-092IFS-2017-001-04DISIS-2017-00104 SOUTHEASTMuskogee CountyOKOGE6/1/202312/31/2025  200200200ERSolarCanadian River-Muskogee and Muskogee-Seminole 345kV5/30/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-086IFS-2017-001-10DISIS-2017-00103 CENTRALHarper CountyKSWERE12/1/20213/1/2025  150150150ERWindViola 345kV5/25/2017 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2017-082IFS-2017-001-02DISIS-2017-00103 CENTRALBarton/Jasper CountiesMOEDE7/1/202012/31/2020  149.4149.4149.4ERWindAsbury Plant 161 kV5/31/2017 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2017-077IFS-2017-001-18DISIS-2017-00104 SOUTHEASTMayes CountyOKAEP12/1/20218/8/2025  124.7124.7124.7ERSolarExplorer Claremore Tap EXCLART45/28/2017 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2017-076IFS-2017-001-17DISIS-2017-00104 SOUTHEASTBenton CountyARAEP12/1/202112/1/2024  52.252.252.2ERSolarChamber Springs 161kV sub5/28/2017 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2017-075IFS-2017-001-16DISIS-2017-00104 SOUTHEASTJohnston CountyOKOGE12/1/202112/1/2026  200200200ERSolarHugo-Sunnyside 345 kV5/28/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-074IFS-2017-001-15DISIS-2017-00104 SOUTHEASTMayes CountyOKAEP12/1/20218/8/2025  72.572.572.5ERSolarPryor Junction 138kV sub5/28/2017 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2017-073IFS-2017-001-14DISIS-2017-00104 SOUTHEASTMayes CountyOKGRDA12/1/20219/1/2025  72.572.572.5ERSolarDry Gulch 161kV sub5/28/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-072IFS-2017-001-37DISIS-2017-00104 SOUTHEASTPayne CountyOKOGE12/1/202112/1/2025  52.252.252.2ERSolarGreenwood 138kV sub5/28/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-071IFS-2017-001-36DISIS-2017-00104 SOUTHEASTPayne CountyOKOGE12/1/202112/1/2025  124.7124.7124.7ERSolarGreenwood 138kV sub5/28/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-068IFS-2017-001-26DISIS-2017-00103 CENTRALSumner CountyKSWERE12/31/202012/15/2028  103.5103.5103.5ER/NRSolarGordon Evans 138kV Substation5/30/2017 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2017-061IFS-2017-001-25DISIS-2017-00104 SOUTHEASTMayes CountyOKGRDA12/1/20219/1/2025  101.5101.5101.5ERSolarGRDA1 to CLARMR 5 161kV line5/28/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-060IFS-2017-001-01DISIS-2017-00103 CENTRALBarton CountyMOEDE9/1/20204/21/2021  149.4149.4149.4ERWindLaRussell Energy Center 161kV5/30/2017 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2017-057IFS-2017-001-13DISIS-2017-00104 SOUTHEASTCaddo ParishLAAEP12/1/20212/28/2025  72.572.572.5ERSolarHosston 69kV5/30/2017 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2017-048IFS-2017-001-34DISIS-2017-00101 NORTHWilliams CountyNDBEPC8/30/202412/31/2026  300300300ERWindNeset 230 kV Substation5/31/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-047IFS-2017-001-19DISIS-2017-00105 SOUTHWESTBeaver CountyOKSPS12/31/201912/31/2024  102102102ER/NRWindBull Creek 115 kV substation5/18/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-040IFS-2017-001-03DISIS-2017-00104 SOUTHEASTOchiltree CountyTXOGE6/1/202012/31/2025  200.1200.1200.1ERSolarCanadian River-Muskogee and Muskogee-Seminole 345kV5/31/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-036IFS-2017-001-23DISIS-2017-00104 SOUTHEASTKiowa CountyOKAEP12/1/202212/1/2024  100100100ERSolarSnyder - Cache 138 kV5/31/2017 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2017-033IFS-2017-001-28DISIS-2017-00105 SOUTHWESTBaylor CountyTXAEP12/31/202012/31/2024  200200200ERWindOklaunion 345 kV sub5/31/2017 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2017-027IFS-2017-001-33DISIS-2017-00104 SOUTHEASTCarter CountyOKOGE11/1/202112/21/2021  140140140ERWindPooleville-Ratliff (Carter County) 138kV5/31/2017 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2017-023IFS-2017-001-22DISIS-2017-00104 SOUTHEASTChoctaw CountyOKWFEC 6/1/2026  858585ER/NRSolarHugo Power Plant 138 kV Sub5/31/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-022IFS-2017-001-21DISIS-2017-00103 CENTRALWilson CountyKSWERE12/1/20196/1/2025  656565ER/NRSolarAltoona- NE Parson 138kV5/31/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-018IFS-2017-001-27DISIS-2017-00103 CENTRALBarber CountyKSITCGP12/31/20204/30/2025  189189189ER/NRSolarThistle 345 kV sub5/30/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-014IFS-2017-001-29DISIS-2017-00101 NORTHHaakon CountySDWAPA12/1/202012/1/2027  300300300ERWindPhilip Tap 230 kV5/22/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-011IFS-2017-001-06DISIS-2017-00104 SOUTHEASTEllis CountyOKOGE12/31/201912/31/2026  151.8151.8151.8ERSolarBadger-Woodward EHV Dbl Ckt 345kV5/17/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-010IFS-2017-001-12DISIS-2017-00101 NORTHBowman CountyNDBEPC10/31/202212/12/2025  200.1200.1200.1ERWindRhame 230 kV Sub4/14/2017 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2017-009IFS-2017-001-39DISIS-2017-00103 CENTRALNeoshoe CountyKSWERE10/31/20205/1/2021  302302302ERWindNeosho - Caney River 345 kV4/14/2017 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2017-005IFS-2017-001-11DISIS-2017-00103 CENTRALBourbon and Crawford CountiesOKWERE12/31/202012/13/2021  190190190ERWindMarmaton - Litchfield 161 kV4/14/2017 IA FULLY EXECUTED/COMMERCIAL OPERATIONInterim IGIA effective 3/3/2021 - AB View 
GEN-2017-004IFS-2017-001-05DISIS-2017-00103 CENTRALCloud CountyKSITCGP12/31/202111/30/2027  201.6201.6201.6ERWindElm Creek - Summit 345 kV4/14/2017 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2016-177IFS-2016-002-60DISIS-2016-002-105 SOUTHWESTGainesTXSPS 7/28/2021  1714.417ERThermalGas TurbineXTO-Cornell 115 kV station1/23/2017 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-176IFS-2016-002-67DISIS-2016-002-103 CENTRALNemaha CountyKSWERE12/31/201912/6/2021  302302302ERWindStranger Creek 345kV12/15/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-174IFS-2016-002-19DISIS-2016-002-103 CENTRALNemahaKSWERE9/15/201911/18/2020  302302302ERWindStranger Creek 345kV11/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-167IFS-2016-002-02DISIS-2016-002-104 SOUTHEASTCaddo ParishLAAEP9/1/202312/1/2024  73.573.573.5ER/NRSolarLieberman - North Benton 138 kV Line11/29/2016 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2016-160IFS-2016-002-04DISIS-2016-002-103 CENTRALEllisKSMIDW10/2/202312/31/2026  202020ER/NRBattery/StoragePost Rock 230kV11/21/2016 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2016-153IFS-2016-002-11DISIS-2016-002-103 CENTRALHarper CountyKSWERE10/30/201912/31/2024  134134134ERWindViola 345kV11/30/2016 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2016-151IFS-2016-002-62DISIS-2016-002-101 NORTHBurkeNDBEPC9/15/201912/22/2020  202202202ERWindTande 345kV11/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-150IFS-2016-002-15DISIS-2016-002-103 CENTRALNemahaKSWERE9/22/202212/7/2023  302302302ERWindStranger Creek 345kV11/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-149IFS-2016-002-14DISIS-2016-002-103 CENTRALWashingtonKSWERE9/15/201912/7/2023  302302302ERWindStranger Creek 345kV11/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-147IFS-2016-002-33DISIS-2016-002-102 NEBRASKACheyenneNETri-State9/15/20196/28/2024  404040ERSolarSidney 115 kV Sub11/30/2016 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2016-146IFS-2016-002-56DISIS-2016-002-104 SOUTHEASTTexasOKAEP9/1/202012/31/2025  175175175ERWindRiverside 345kV Substation11/29/2016 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2016-145IFS-2016-002-55DISIS-2016-002-104 SOUTHEASTTexasOKAEP9/1/202012/31/2025  175175175ERWindRiverside 345kV Substation11/29/2016 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2016-142IFS-2016-002-52DISIS-2016-002-104 SOUTHEASTTexasOKAEP9/1/202012/31/2025  350350350ERWindRiverside 345kV Substation11/29/2016 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2016-141IFS-2016-002-51DISIS-2016-002-104 SOUTHEASTTexasOKAEP9/1/202012/31/2025  350350350ERWindRiverside 345kV Substation11/29/2016 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2016-139IFS-2016-002-49DISIS-2016-002-104 SOUTHEASTTexasOKAEP9/1/202012/31/2025  100100100ERWindRiverside 345kV Substation11/29/2016 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2016-138IFS-2016-002-48DISIS-2016-002-104 SOUTHEASTTexasOKAEP9/1/202012/31/2025  187.5187.5187.5ERWindRiverside 345kV Substation11/29/2016 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2016-137IFS-2016-002-47DISIS-2016-002-104 SOUTHEASTTexasOKAEP9/1/202012/31/2025  187.5187.5187.5ERWindRiverside 345kV Substation11/29/2016 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2016-134IFS-2016-002-44DISIS-2016-002-104 SOUTHEAST TexasOKAEP9/1/202012/31/2025  187.5187.5187.5ERWindRiverside 345kV Substation11/29/2016 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2016-133IFS-2016-002-43DISIS-2016-002-104 SOUTHEASTTexasOKAEP9/1/202012/31/2025  187.5187.1187.5ERWindRiverside 345kV Substation11/29/2016 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2016-132IFS-2016-002-61DISIS-2016-002-104 SOUTHEASTRoger MillsOKAEP12/31/20176/5/2020  6.16.16.1ERWindSweetwater 230kV11/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-131IFS-2016-002-37DISIS-2016-002-104 SOUTHEASTGradyOKOGE12/31/201710/25/2021  2.52.52.5ERWindMinco 345kV11/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-130IFS-2016-002-21DISIS-2016-002-101 NORTHMercerNDBEPC9/15/201912/31/2024  202202202ERWindLeland Olds 345 kV11/30/2016 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2016-128IFS-2016-002-36DISIS-2016-002-104 SOUTHEASTAlfalfaOKOGE9/15/201912/31/2026  176176176ERWindWoodring 345kV11/30/2016 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2016-126IFS-2016-002-06DISIS-2016-002-104 SOUTHEASTMurrayOKOGE12/31/201911/24/2021  172.5172.5172.5ER/NRWindArbuckle 138kV substation11/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-125IFS-2016-002-29DISIS-2016-002-105 SOUTHWESTRooseveltNMSPS12/31/201912/31/2020  747474ERWindEddy County-Tolk (Crossroads) 345kV11/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-124IFS-2016-002-28DISIS-2016-002-105 SOUTHWESTRooseveltNMSPS12/31/201912/31/2020  150150150ERWindEddy County-Tolk (Crossroads) 345kV11/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-123IFS-2016-002-27DISIS-2016-002-105 SOUTHWESTRooseveltNMSPS12/31/201912/31/2020  298298298ERWindEddy County-Tolk (Crossroads) 345kV11/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-121IFS-2016-002-26DISIS-2016-002-105 SOUTHWESTLeaNMSPS10/1/202212/31/2024  110110110ERSolarRoadrunner 115kV11/22/2016 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2016-119IFS-2016-002-10DISIS-2016-002-104 SOUTHEASTKingfisherOKOGE5/15/202012/31/2025  600600600ERWindSpring Creek-Sooner 345kV11/30/2016 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2016-118IFS-2016-002-05DISIS-2016-002-104 SOUTHEASTKingfisherOKWFEC5/15/20219/10/2021  288288288ERWindDover Switchyard 138 kV Line11/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-115IFS-2016-002-24DISIS-2016-002-103 CENTRALAtchisonMOGMO11/16/20203/2/2021  300300300ERWindNebraska City-Mullen Creek (Holt County MO) 345kV11/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION  View 
GEN-2016-111IFS-2016-002-18DISIS-2016-002-103 CENTRALMcPhersonKSEvergy9/15/20191/15/2027  302302302ERWindReno - Summit 345kV11/30/2016 IA FULLY EXECUTED/ON SCHEDULESuspension Start Date of 3/24/2021 View 
GEN-2016-102IFS-2016-002-01DISIS-2016-002-104 SOUTHEASTPontotocOKOGE11/1/202312/1/2024  150.9150.9150.9ER/NRWindBlue River 138kV11/7/2016 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2016-097IFS-2016-002-31DISIS-2016-002-104 SOUTHEASTCaddoOKAEP9/1/20201/1/2024  100100100ER/NRWindTap Southwestern-Fletcher Tap 138kV10/19/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-095IFS-2016-002-32DISIS-2016-002-104 SOUTHEASTCaddoOKAEP9/1/20204/22/2024  200200200ER/NRWindGracemont-Lawton East Side 345kV12/1/2020 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-094IFS-2016-002-25DISIS-2016-002-101 NORTHHydeSDWAPA10/1/20201/24/2024  200200200ERWindTap Ft Thompson - Oahe 230kV Line (Single Circuit)10/31/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-091IFS-2016-002-22DISIS-2016-002-104 SOUTHEASTCaddoOKAEP5/6/20201/8/2022  303.6303.6303.6ERWindGracemont-Lawton East Side 345kV10/3/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-087IFS-2016-002-59DISIS-2016-002-101 NORTHCampbellSDWAPA11/15/201912/31/2026  98.998.998.9ERWindBismark-Glenham 230 kV line7/25/2016 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2016-075IFS-2016-001-21DISIS-2016-001-302 NEBRASKAHoltNEWAPA12/31/201712/31/2024  505050ERWindFort Thompson-Grand Island (Grand Prairie) 345kV3/31/2016 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2016-074IFS-2016-002-57DISIS-2016-002-102 NEBRASKACusterNENPPD10/30/20207/1/2027  200200200ERWindSweetwater 345kV4/14/2016 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2016-071IFS-2016-001-19DISIS-2016-001-304 SOUTHEASTKayOKOGE9/30/20182/27/2027  200.1200.1200.1ERWindMiddleton Tap 138kV Substation3/30/2016 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2016-070IFS-2016-001-18DISIS-2016-001-305 SOUTHWESTCarsonTXSPS11/1/201612/11/2020  5.35.35.3ERWindMartin 115 kV Substation3/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-068IFS-2016-001-40DISIS-2016-001-304 SOUTHEASTGarfieldOKOGE9/18/202012/15/2020  250250250ERWindWoodring 345kV3/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-067IFS-2016-001-33DISIS-2016-001-303 CENTRALThomasKSSUNC11/1/20177/24/2019  73.673.673.6ERWindMingo 345kV3/31/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-061IFS-2016-001-15DISIS-2016-001-304 SOUTHEASTGarfield/NobleOKOGE12/1/201711/21/2020  250.7250.7250.7ERWindSooner-Woodring 345 kV line3/29/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-057IFS-2016-001-35DISIS-2016-001-304 SOUTHEASTCimarron, Texas CountyOKOGE8/31/20183/18/2022  499.1499.1499.1ERWindMathewson 345kV3/31/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-051IFS-2016-001-13DISIS-2016-001-304 SOUTHEASTCusterOKAEP 12/18/2020  9.89.89.8ERWindClinton Junction-Weatherford Southeast 138kV3/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-050IFS-2016-001-42DISIS-2016-001-302 NEBRASKAWebster CoNENPPD12/1/201712/9/2021  250.7250.7250.7ERWindAxtell – Post Rock 345 kV3/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-047IFS-2016-001-22DISIS-2016-001-304 SOUTHEASTCanadianOKOGE12/31/20173/24/2018  24824ERThermalCTMustang 69kV3/31/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-046IFS-2016-001-12DISIS-2016-001-303 CENTRALFord CountyKSSUNC12/1/201812/23/2021  299299299ERWindClark County-Ironwood 345kV3/31/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-045IFS-2016-001-34DISIS-2016-001-304 SOUTHEASTCimarron, Texas CountyOKOGE8/31/20183/18/2022  499.1499.1499.1ERWindMathewson 345kV3/31/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-043IFS-2016-001-36DISIS-2016-001-302 NEBRASKAWayne CountyNENPPD9/1/20186/27/2020  230230230ERWindHoskins 345kV3/31/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-037IFS-2017-001-32DISIS-2017-00104 SOUTHEASTWashita CountyOKAEP6/1/20213/21/2023  300300300ERWindChisholm-Gracemont 345kV3/31/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-036IFS-2016-002-42DISIS-2016-002-101 NORTHChippewa CountyMNWAPA11/17/201812/30/2018  44.644.644.6ERWindGranite Falls 115kV substation3/28/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-032IFS-2016-001-11DISIS-2016-001-304 SOUTHEASTKingfisher CoOKOGE2/1/20234/11/2024  200200200ER/NRWindCrescent Substation 138 kV3/30/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-031IFS-2016-001-10DISIS-2016-001-304 SOUTHEASTKay CountyOKOGE11/30/201612/17/2016  1.51.51.5ERWindRose Hill (Open Sky)-Sooner (Ranch Road) 345kV3/25/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-030IFS-2016-001-26DISIS-2016-001-304 SOUTHEASTJohnston CoOKOGE8/28/20213/31/2026  100100100ER/NRSolarBrown 138kV3/30/2016 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2016-028IFS-2016-001-38DISIS-2016-001-304 SOUTHEASTLe Flore CoOKAEP12/31/201812/27/2019  100100100ERWindClayton 138 kV Sub3/29/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-022IFS-2016-001-29DISIS-2016-001-304 SOUTHEASTNewkirk, Kay CountyOKOGE12/31/201712/10/2020  151.8151.8151.8ERWindRose Hill (Open Sky)-Sooner (Ranch Road) 345kV3/31/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-021IFS-2016-001-31DISIS-2016-001-302 NEBRASKADixon CountyNENPPD12/1/20183/9/2022  298.47298.47298.47ERWindHoskins 345kV3/31/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-020IFS-2016-001-27DISIS-2016-001-304 SOUTHEASTWoodward CountyOKWFEC12/31/201812/18/2020  148.4148.4148.4ERWindMoreland 138kV Substation4/1/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-017IFS-2016-001-08DISIS-2016-001-301 NORTHHyde CountySDBEPC12/1/201711/23/2020  250.24250.24250.24ERWindChappelle Creek 345kV3/29/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-014IFS-2016-001-04DISIS-2016-001-303 CENTRALJoplinMOEDE4/25/20034/30/2020  101010ERThermalCTLaRussell Energy Center 161kV3/29/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-013IFS-2016-001-03DISIS-2016-001-303 CENTRALJoplinMOEDE4/25/20034/30/2020  101010ERThermalCTLaRussell Energy Center 161kV3/29/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2016-009IFS-2016-001-02DISIS-2016-001-303 CENTRALPonca CityOKOGE9/30/201811/18/2020  292929ERThermalSteam TurbineOsage 69 kV Sub3/24/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2016-004IFS-2016-001-25DISIS-2016-001-301 NORTHOliverNDBEPC10/5/202212/31/2025  202202202ER/NRWindBasin Electric 230 kV3/10/2016 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2016-003IFS-2016-001-45DISIS-2016-001-304 SOUTHEASTEllisOKOGE12/31/201712/21/2022  250.4250.4250.4ERWindBadger-Woodward EHV Dbl Ckt 345kV3/15/2016 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-096IFS-2015-002-43DISIS-2015-002-701 NORTHHettinger CountyNDBEPC12/31/201712/29/2016  150150150ERWindBrady 230kV substation10/19/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-090IFS-2015-002-21DISIS-2015-002-703 CENTRALPrattKSWERE12/1/201712/14/2018  220220220ERWindThistle-Wichita Dbl Ckt (Buffalo Flats) 345kV9/29/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-089IFS-2016-001-05DISIS-2016-001-301 NORTHBon HommeSDWAPA6/30/20174/22/2020  200200200ERWindUtica 230 kV Substation10/13/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-088IFS-2015-002-32DISIS-2015-002-702 NEBRASKASalineNENPPD1/1/201912/29/2020  300300300ER/NRWindTobias 345kV Substation9/30/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2015-082IFS-2016-001-28DISIS-2016-001-305 SOUTHWESTBeaverOKOGE12/1/201711/25/2020  200200200ERWindBeaver County - Woodward EHV Dbl Ckt (Badger) 345kV9/28/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-073IFS-2015-002-20DISIS-2015-002-703 CENTRALLyon CountyKSWERE12/31/201812/19/2019  200.1200.1200.1ER/NRWindEmporia 345kV9/28/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-069IFS-2015-002-06DISIS-2015-002-703 CENTRALDickenson / Marion CountiesKSWERE12/1/201712/17/2018  300300300ERWindUnion Ridge 230kV9/21/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-066IFS-2015-002-38DISIS-2015-002-704 SOUTHEASTPawneeOKOGE12/1/201712/31/2025  248.4248.4248.4ERWindSooner - Cleveland 345kV10/7/2015 IA FULLY EXECUTED/ON SCHEDULE View 
GEN-2015-065IFS-2015-002-19DISIS-2015-002-703 CENTRALThomas CountyKSSUNC11/1/20177/1/2019  202.4202.4202.4ERWindMingo 345kV10/7/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-064IFS-2015-002-18DISIS-2015-002-703 CENTRALThomas CountyKSSUNC11/1/20173/26/2020  197.8197.8197.8ERWindMingo 115kV10/7/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-063IFS-2015-002-16DISIS-2015-002-704 SOUTHEASTKingfisher CountyOKOGE12/1/20171/1/2018  300300300ERWindWoodring-Matthewson 345kV10/6/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-062IFS-2015-002-15DISIS-2015-002-704 SOUTHEASTGarfield CountyOKOGE3/1/20168/27/2024  4.54.54.5ERWindBreckinridge 138kV10/6/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-057IFS-2015-002-33DISIS-2015-002-704 SOUTHEASTGrady CountyOKOGE12/1/201612/22/2018  100100100ERWindMinco 345kV10/6/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-052IFS-2015-002-03DISIS-2015-002-703 CENTRALSumnerKSWERE12/1/20176/1/2025  300300300ERWindOpen Sky-Rose Hill 345kV10/5/2015 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2015-048IFS-2015-002-11DISIS-2015-002-704 SOUTHEASTMajor County, OKOKOGE12/1/20174/14/2021  200200200ERWindCleo Corner 138kV10/5/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-047IFS-2015-002-02DISIS-2015-002-704 SOUTHEASTNoble CountyOKOGE12/1/20171/1/2018  300300300ERWindSooner 345kV10/5/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-046IFS-2015-002-46DISIS-2015-002-701 NORTHWilliams CountyNDBEPC12/1/20175/27/2021  300300300ERWindTande 345kV10/5/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-045IFS-2015-002-10DISIS-2015-002-704 SOUTHEASTGrady CountyOKAEP12/1/20172/2/2020  202020ERBattery/StorageLawton East Side-Sunnyside (Terry Road) 345kV10/5/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-041IFS-2015-002-41DISIS-2016-00105 SOUTHWESTHale CountyTXSPS7/1/201510/19/2019  550ERThermalCTTUCO 345kV9/30/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-036IFS-2016-001-44DISIS-2016-001-304 SOUTHEASTJohnston CountyOKOGE12/31/201712/13/2020  303.6303.6303.6ERWindJohnston County 345kV9/10/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-034IFS-2015-002-08DISIS-2015-002-704 SOUTHEASTKay CountyOKOGE10/31/201712/10/2020  200200200ERWindRose Hill (Open Sky)-Sooner (Ranch Road) 345kV8/28/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-025IFS-2015-001-03DISIS-2015-001-403 CENTRALPrattKSWERE12/31/201612/19/2016  220220220ERWindTap Thistle – Wichita 345kV Dbl CKT3/26/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-024IFS-2015-001-02DISIS-2015-001-403 CENTRALPratt CountyKSWERE12/31/201612/9/2016  220220220ERWindThistle-Wichita Dbl Ckt (Buffalo Flats) 345kV3/26/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-023IFS-2015-001-08DISIS-2015-001-402 NEBRASKAAntelope & Wheeler CountyNENPPD12/31/201911/16/2022  300.7300.7300.7ER/NRWindGrand Prairie-Grand Island (Holt County NE) 345kV3/31/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2015-021IFS-2015-001-16DISIS-2015-001-403 CENTRALStantonKSSUNC12/31/20164/7/2020  202020ER/NRSolarJohnson Corner 115kV4/1/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-016IFS-2015-001-05DISIS-2015-001-403 CENTRALAllen CountyKSKCPL12/31/20179/11/2019  200200200ER/NRWindTap Marmaton - Centerville 161kV3/20/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-015IFS-2015-001-14DISIS-2015-001-404 SOUTHEASTGrant CountyOKOGE7/31/201612/8/2017  154.56154.56154.56ER/NRWindTap Medford Tap – Coyote 138kV3/27/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-014IFS-2015-001-20DISIS-2015-001-405 SOUTHWESTCochran CountyTXSPS12/1/201612/15/2018  150150150ERWindTap Cochran - Lehman 115kV substation3/31/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-013IFS-2015-001-18DISIS-2015-001-404 SOUTHEASTKiowa CountyOKWFEC12/1/20165/23/2024  120120120ER/NRSolarSnyder 138kV3/31/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-007IFS-2015-001-01DISIS-2015-001-402 NEBRASKAWayne CountyNENPPD11/8/201912/31/2019  160160160ERWindHoskins 345kV3/25/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2015-005IFS-2015-001-04DISIS-2015-001-403 CENTRALDeKalb CountyMOGMO12/31/201712/16/2016  200.1200.1200.1ERWindMullen Creek-Sibley (Ketchum) 345kV3/25/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2015-001IFS-2015-001-15DISIS-2015-001-404 SOUTHEASTKayOKOGE12/31/201612/17/2016  200200200ERWindRose Hill (Open Sky)-Sooner (Ranch Road) 345kV3/4/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2014-064IFS-2014-002-24 DISIS-2014-002-604 SOUTHEASTGarfieldOKOGE12/1/201612/21/2018  248.4248.4248.4ERWindOtter 138kV9/30/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-057IFS-2014-002-22DISIS-2014-002-604 SOUTHEASTGradyOKAEP12/31/201612/1/2016  249.9249.9249.9ERWindLawton East Side-Sunnyside (Terry Road) 345kV9/29/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-056IFS-2014-002-21DISIS-2014-002-604 SOUTHEASTCanadianOKOGE12/31/201612/22/2018  250250250ERWindMinco 345kV9/29/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-040IFS-2014-002-14DISIS-2014-002-605 SOUTHWESTCastroTXSPS9/1/201612/30/2016  320320320ERWindCastro 115kV9/26/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-035IFS-2014-002-12 DISIS-2014-002-605 SOUTHWESTChavesNMSPS12/31/20164/24/2023  303030ERSolarChaves County 115kV9/29/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-034IFS-2014-002-11DISIS-2014-002-605 SOUTHWESTChavesNMSPS12/31/201610/21/2016  707070ERSolarChaves County 115kV9/29/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-033IFS-2014-002-10DISIS-2014-002-605 SOUTHWESTChavesNMSPS12/31/20168/25/2016  707070ERSolarChaves County 115kV9/29/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-032IFS-2014-002-09DISIS-2014-002-602 NEBRASKAAntelope NENPPD10/1/20155/1/2014  10.210.210.2ER/NRWindMeadow Grove 230kV9/29/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2014-031IFS-2014-002-08 DISIS-2014-002-602 NEBRASKAAntelope CountyNENPPD10/1/20153/30/2016  35.835.835.8ER/NRWindMeadow Grove 230kV9/26/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION View 
GEN-2014-028IFS-2014-002-07 DISIS-2014-002-603 CENTRALCherokee CountyKSEDE1/1/20164/1/2016  50050ERThermalCCRiverton 161kV9/25/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-025IFS-2014-002-05 DISIS-2014-002-603 CENTRALRush KSMIDW10/15/201512/1/2015  2.422.422.42ERWindTap Nekoma - Bazine (Walnut Creek) 69kV9/25/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-021IFS-2014-002-04DISIS-2014-002-603 CENTRALAtchison MOGMO12/1/201611/7/2017  300300300ER/NRWindNebraska City-Mullen Creek (Holt County MO) 345kV9/2/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-020IFS-2014-002-03 DISIS-2014-002-604 SOUTHEASTGrady OKAEP12/31/201410/10/2017  100100100ER/NRWindTuttle 138kV7/14/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-013IFS-2014-001-07 DISIS-2014-001-102 NEBRASKAAntelope / BooneNENPPD12/31/201412/18/2015  73.573.573.5ER/NRWindMeadow Grove 230kV3/31/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-005IFS-2014-001-05 DISIS-2014-001-104 SOUTHEASTCaddoOKOGE 6/1/2015  5.75.75.7ERWindMinco 345kV2/19/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-004IFS-2014-001-04 DISIS-2014-001-102 NEBRASKAJeffersonNENPPD 10/29/2013  3.963.963.96ERWindSteele City 115kV2/19/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-002IFS-2014-001-02DISIS-2014-001-104 SOUTHEASTDeweyOKOGE12/31/20144/8/2015  10.510.510.5ERWindTatonga 345kV2/18/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-001ISIFS-2015-001-21DISIS-2015-002 Prior Queued01 NORTHButteSDWAPA12/15/20159/24/2020  103.24103.24103.24ERWindSulphur 115kV11/24/2015 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2014-001IFS-2014-001-08DISIS-2014-001-103 CENTRALMarionKSWERE7/15/20148/11/2023  200.6200.6200.6ERWindTap Wichita - Emporia Energy Center 345kV1/15/2014 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2013-033IFS-2013-002-07DISIS-2013-002-203 CENTRALEllisKSMIDW12/31/20152/27/2016  282828ER/NRThermalGasGoodman Energy Center 115kV9/30/2013 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2013-032IFS-2013-002-06DISIS-2013-002-202 NEBRASKAAntelopeNENPPD12/31/201612/20/2018  202.5202.5202.5ERWindAntelope 115kV9/30/2013 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2013-029IFS-2013-002-04 DISIS-2013-002-204 SOUTHEASTGrantOKOGE12/15/20154/8/2016  299299299ERWindRenfrow 345kV9/30/2013 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2013-028IFS-2013-002-03DISIS-2013-002-204 SOUTHEASTMayesOKGRDA4/16/201612/23/2017  538495538ERThermalGasTap N Tulsa - GRDA 1 345kV9/30/2013 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2013-027IFS-2014-002-02DISIS-2014-002-605 SOUTHWESTBaileyTXSPS3/31/201612/10/2018  148.4148.4148.4ER/NRWindTolk - Yoakum 230kV9/30/2013 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2013-022IFS-2013-002-02DISIS-2013-002-205 SOUTHWESTQuayNMSPS5/1/201512/7/2016  252525ER/NRSolarNorton 115kV Switching Station9/5/2013 IA FULLY EXECUTED/COMMERCIAL OPERATION  View
GEN-2013-019IFS-2013-002-01DISIS-2013-002-202 NEBRASKALancasterNENPPD6/30/201412/1/2026  73.673.673.6ER/NRHybridWind/SolarMonolith 115kV4/17/2013 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2013-016IFS-2013-001-03DISIS-2013-001-405 SOUTHWESTHaleTXSPS12/1/201610/19/2019  203191203ERThermalCTTUCO 345kV3/29/2013 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2013-012DISIS-2013-001-404 SOUTHEASTLogan CountyOKOGE11/30/20148/11/2014  14768147ERThermalGasRedbud 345kV3/28/2013 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2013-011IFS-2013-001-02DISIS-2013-001-404 SOUTHEASTHempsteadARAEP 12/18/2012  304030ERThermalCoalTurk 138kV3/28/2013 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2013-008DISIS-2013-001-402 NEBRASKAJeffersonNENPPD12/31/201312/31/2013  1.21.21.2ERWindSteele City 115kV3/27/2013 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2013-007DISIS-2013-001-404 SOUTHEASTMurrayOKOGE12/31/201411/23/2015  100100100ER/NRWindTap Prices Falls - Carter 138kV3/25/2013 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2013-002IFS-2013-001-01DISIS-2013-001-402 NEBRASKALancasterNENPPD12/31/201312/1/2026  50.650.650.6ER/NRHybridWind/SolarMonolith 115kV3/1/2013 IA FULLY EXECUTED/ON SCHEDULE ViewView
GEN-2012-044CrawfordKSWERE11/30/201311/1/2013  222ERThermalGasSheffield 69kV12/5/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-041DISIS-2012-002-604 SOUTHEASTKayOKOGE4/15/20154/15/2015  121.585.3121.5ERThermalCTRose Hill (Open Sky)-Sooner (Ranch Road) 345kV9/30/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-037DISIS-2012-002-605 SOUTHWESTHaleTXSPS3/1/20153/1/2015  203196203ERThermalCTTUCO 345kV9/30/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-036DISIS-2012-002-605 SOUTHWESTYoakumTXSPS6/1/20133/1/2013  777ERThermalCTMustang 230kV9/30/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-035DISIS-2012-002-605 SOUTHWESTYoakumTXSPS6/1/20134/1/2015  777ERThermalCTMustang 230kV9/30/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-034DISIS-2012-002-605 SOUTHWESTYoakumTXSPS6/1/20134/1/2015  777ERThermalCTMustang 230kV9/30/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-033DISIS-2012-002-604 SOUTHEASTGarfieldOKOGE12/1/20149/1/2015  98.8298.8298.82ERWindBreckinridge 138kV9/28/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2012-032DISIS-2012-002-604 SOUTHEASTKayOKOGE11/30/20146/30/2015  299299299ERWindRose Hill-(Ranch Road) Sooner (Open Sky) 345kV9/28/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-028DISIS-2012-002-604 SOUTHEASTWashitaOKWFEC12/1/201412/22/2015  747474ERWindGotebo 69kV9/28/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-024IFS-2012-002-01DISIS-2012-002-603 CENTRALFordKSSUNC12/31/20156/1/2017  180180180ERWindClark County 345kV9/28/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-021DISIS-2012-002-602 NEBRASKALincolnNELES8/1/201312/1/2013  4.84.84.8ERThermalGasTerry Bundy Generating Station 115kV9/26/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-020DISIS-2012-002-605 SOUTHWESTAbernathy CountyTXSPS9/30/20156/28/2019  478478478ERWindTUCO 230kV9/26/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-007DISIS-2012-001-403 CENTRALGrant CountyKSSUNC4/1/20144/15/2014  120120120ER/NRThermalGasRubart 115kV3/29/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-004DISIS-2012-001-404 SOUTHEASTCarter CountyOKOGE12/31/201311/21/2014  40.840.840.8ER/NRWindPooleville-Ratliff (Carter County) 138kV3/27/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2012-001DISIS-2012-001-405 SOUTHWESTLynn County TexasTXSPS11/30/201212/21/2012  61.261.261.2ERWindTap Grassland - Borden County 230 kv3/8/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-057DISIS-2011-002-603 CENTRALSumner CountyKSWERE12/31/201312/30/2015  150150150ERWindCreswell 138kV9/30/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-056BDISIS-2011-002-602 NEBRASKANorth Platte - LexingtonNENPPD6/30/201210/31/2012  4.54.54.5ERHydroJohn 2 115kV3/8/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-056ADISIS-2011-002-602 NEBRASKANorth Platte - LexingtonNENPPD6/30/201210/31/2012  3.63.63.6ERHydroJohn 1 115kV3/8/2012 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-056DISIS-2011-002-602 NEBRASKANorth Platte - LexingtonNENPPD6/30/201210/31/2012  3.63.63.6ERHydroJeffrey 115kV9/30/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-054DISIS-2011-002-604 SOUTHEASTCanadian CountyOKOGE11/30/201312/31/2014  300300300ERWindCimarron 345kV9/30/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2011-050DISIS-2011-002-604 SOUTHEASTGrady CountyOKAEP12/31/201312/13/2016  108108108ERWindTap Rush Springs - Marlow 138kV9/30/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-048DISIS-2011-002-605 SOUTHWESTDenver CityTXSPS3/1/20133/1/2013  175165175ER/NRThermalCTMustang 230kV9/30/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-046DISIS-2011-002-605 SOUTHWESTQuay CountyNMSPS6/1/20139/5/2013  232323ERThermalCTTucumcari 115kV9/29/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-045DISIS-2011-002-605 SOUTHWESTLubbockTXSPS6/1/20135/1/2013  205180205ERThermalNG/CTJones 230kV9/29/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-040DISIS-2011-002-604 SOUTHEASTMurray CountyOKOGE12/31/201211/21/2014  111111111ER/NRWindPooleville-Ratliff (Carter County) 138kV9/16/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-037DISIS-2011-002-604 SOUTHEASTApacheOKWFEC1/1/20122/5/2013  6.66.66.6ERWindBlue Canyon 5 138kV7/1/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-027DISIS-2011-001-802 NEBRASKAWinsideNENPPD12/31/201212/17/2018  120120120ER/NRWindWakefield 230kV3/31/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2011-025DISIS-2011-001-805 SOUTHWESTLorenzoTXSPS6/30/201212/15/2018  79.9679.9679.96ERWindTap Floyd County - Crosby County 115kV3/31/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-022DISIS-2011-001-805 SOUTHWESTHansfordTXSPS12/31/20129/8/2022  299299299ERWindHitchland 345kV3/31/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-020DISIS-2011-001-804 SOUTHEASTEllisOKOGE12/31/201210/31/2027  165.6165.6165.6ER/NRWindWoodward EHV 345kV3/31/2011 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2011-019DISIS-2011-001-804 SOUTHEASTWoodward CountyOKOGE12/31/201212/31/2020  175175175ER/NRWindWoodward EHV 345kV3/31/2011 IA FULLY EXECUTED/ON SCHEDULE   
GEN-2011-018DISIS-2011-001-802 NEBRASKAJefferson CountyNENPPD12/1/201312/31/2013  73.673.673.6ER/NRWindSteele City 115kV3/31/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-014DISIS-2011-001-805 SOUTHWESTBeaver CountyOKOGE12/31/201312/20/2016  198198198ERWindBeaver County-Woodward EHV Dbl Ckt (Badger) 345kV3/31/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-011DISIS-2011-001-803 CENTRALWestonMOKCPL12/31/20106/5/2012  505050ERThermalCoalIatan 345kV3/31/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-010DISIS-2011-001-804 SOUTHEASTCaddo CountyOKOGE12/1/201210/1/2012  100.8100.8100.8ERWindMinco 345kV3/30/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2011-008DISIS-2011-001-803 CENTRALClark CountyKSSUNC12/1/201512/21/2016  600600600ERWindClark County 345kV3/29/2011 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-057DISIS-2011-001-803 CENTRALLincoln CountyKSMIDW8/1/20129/28/2012  201201201ER/NRWindRice County 230kV10/27/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-055DISIS-2011-001-804 SOUTHEASTSand SpringsOKAEP12/31/20112/27/2013  4.54.54.5ERThermalGasWekiwa 138kV9/30/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-051DISIS-2010-002-602 NEBRASKADixon CountyNENPPD12/15/201212/17/2018  200200200ERWindWakefield 230kV9/30/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-040DISIS-2010-002-604 SOUTHEASTCanadian CountyOKOGE11/30/201111/23/2012  300300300ERWindCimarron 345kV8/19/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-036DISIS-2010-002-603 CENTRALDouglas CountyKSWERE8/1/20128/1/2012  4.64.64.6ERHydro6th Street 115kV6/30/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-014DISIS-2010-001-805 SOUTHWESTHansford CountyTXSPS12/31/201312/31/2022  358.8358.8358.8ERWindHitchland 345kV3/31/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-011DISIS-2010-001-804 SOUTHEASTDewey CountyOKOGE12/31/20112/28/2012  29.729.729.7ERWindTatonga 345kV3/31/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-009DISIS-2010-001-803 CENTRALGray CountyKSSUNC12/1/201112/31/2012  165.6165.6165.6ERWindBuckner 345kV3/29/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-006DISIS-2010-001-805 SOUTHWESTLubbockTXSPS6/1/20126/30/2011  205180205ERThermalGasJones 230kV3/24/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-005DISIS-2010-001-803 CENTRALHarper CountyKSWERE12/1/201212/31/2021  299.2299.2299.2ERWindViola 345kV3/15/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-003DISIS-2010-001-803 CENTRALCoffey CountyKSWERE12/31/20117/31/2014  99.599.599.5ERWindWaverly 345kV3/8/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2010-001DISIS-2010-002-605 SOUTHWESTBeaver CountyOKOGE1/1/20125/15/2015  300300300ERWindHitchland-Woodward EHV Dbl Ckt (Beaver County) 345kV3/3/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2009-040DISIS-2010-001-803 CENTRALMarshall CountyKSWERE12/31/20129/3/2016  727272ERWindTap Smittyville - Knob Hill 115KV8/31/2009 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2009-025DISIS-2009-001-604 SOUTHEASTKay CountyOKOGE12/31/201111/1/2012  59.859.859.8ERWindTAP Deer Creek – Sinclair 69kV6/19/2009 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2009-020DISIS-2010-001-803 CENTRALRush CountyKSMIDW12/31/201110/15/2015  48.348.348.3ERWindTap Nekoma - Bazine (Walnut Creek) 69kV4/15/2009 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2009-008DISIS-2010-001-803 CENTRALNess CountyKSMIDW9/1/201112/1/2015  198.69198.69198.69ERWindSouth Hays 230kV3/10/2009 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-129DISIS-2009-001-603 CENTRALCass CountyMOMIPU5/1/20092/15/2002  72643675ERThermalCTPleasant Hill 161kV12/12/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-124DISIS-2009-001-603 CENTRALFord CountyKSSUNC1/1/20162/28/2017  200.1200.1200.1ERWindClark County-Spearville Ckt 1 (Ironwood) 345kV11/14/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-123NDISIS-2010-001-802 NEBRASKAWebster CountyNENPPD12/31/201611/16/2017  89.6689.6689.66ERWindTap Pauline - Hildreth (Rosemont) 115kV11/12/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-119OICS-2008-001 Prior Queued02 NEBRASKARichardson CountyNEOPPD12/31/2009   606060ERWindS1399 161kV10/8/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-098DISIS-2010-001-803 CENTRALCoffey CountyKSWERE12/31/201111/30/2015  99.599.599.5ERWindWaverly 345kV8/22/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2008-092DISIS-2009-001-603 CENTRALEllis CountyKSMIDW12/1/201111/30/2015  200.5200.5200.5ERWindPost Rock 230kV8/18/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-086N02DISIS-2009-001-602 NEBRASKAAntelope CountyNENPPD 12/31/2014  201201201ERWindMeadow Grove 230kV8/8/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-079DISIS-2009-001-603 CENTRALGray CountyKSMKEC12/1/201011/2/2011  98.998.998.9ERWindCrooked Creek 115kV7/29/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-051DISIS-2009-001-605 SOUTHWESTOldham CountyTXSPS12/31/201012/31/2014  161161161ERWindPotter County 345kV5/30/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-047DISIS-2010-001-805 SOUTHWESTBeaver CountyOKOGE12/31/201212/31/2014  263.13263.13263.13ERWindHitchland-Woodward EHV Dbl Ckt (Beaver County) 345kV5/16/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-044DISIS-2010-001-804 SOUTHEASTDewey CountyOKOGE12/1/20112/28/2012  197.8197.8197.8ERWindTatonga 345kV5/15/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-037DISIS-2010-001-804 SOUTHEASTCommanche CountyOKWFEC11/30/201112/17/2011  999999ERWindTap Washita - Blue Canyon Wind 138kV5/12/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-023DISIS-2009-001-604 SOUTHEASTWashita CountyOKAEP12/1/201011/30/2012  150150150ERWindHobart Junction 138kV3/28/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-022DISIS-2010-001-805 SOUTHWESTChaves CountyNMSPS9/1/201111/15/2015  299.65299.65299.65ERWindEddy County-Tolk (Crossroads) 345kV3/28/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-021Coffey CountyKSWERE5/16/20115/16/2011  424242ERThermalNuclearWolf Creek 345kV3/24/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-018ICS-2008-001-603 CENTRALFinney CountyKSSPS12/31/201212/13/2013  250250250ERWindFinney 345kV3/17/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-013ICS-2008-001-604 SOUTHEASTGarfield CountyOKOGE10/1/201012/7/2012  300300300ERWindHunter 345kV2/19/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-006Caddo ParishLAAEP6/1/20106/16/2010  302030ERThermalGasArsenal Hill 138kV1/31/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-005Mayes CountyOKGRDA1/9/20099/2/2009  161616ERHydro1/28/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-003ICS-2008-001-604 SOUTHEASTWoodwardOKOGE8/31/200912/14/2009  101.2101.2101.2ERWindWoodward EHV 138kV1/25/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2008-002Platte CountyMOKACP1/1/20094/12/2009  656565ERThermalCoal1/22/2008 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-062ICS-2008-001-604 SOUTHEASTHarper CountyOKOGE12/31/201112/21/2016  424424424ERWindWoodward EHV 345kV12/27/2007 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-052ICS-2008-001-604 SOUTHEASTCaddo CountyOKWFEC5/1/20097/1/2009  150150150ERThermalGasAnadarko 138kV11/9/2007 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-050ICS-2008-001-604 SOUTHEASTWoodward CountyOKOGE10/1/200912/23/2010  151.8151.8151.8ERWindWoodward EHV 138kV10/22/2007 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-046ICS-2008-001-605 SOUTHWESTTexas CountyOKSPS12/31/201112/15/2015  200200200ERWindHitchland 115kV10/15/2007 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-044ICS-2008-001-604 SOUTHEASTBlaine CountyOKOGE12/1/200912/31/2014  299.2299.2299.2ERWindTatonga 345kV10/2/2007 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-043ICS-2008-001-604 SOUTHEASTGrady CountyOKOGE12/1/200911/1/2010  200200200ERWindMinco 345kV10/2/2007 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-040DISIS-2009-001-603 CENTRALGray CountyKSSUNC12/15/20106/9/2012  131.1131.1131.1ERWindBuckner 345kV9/25/2007 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2007-025ICS-2008-001-603 CENTRALBarber CountyKSWERE12/31/200910/1/2012  299.2299.2299.2ERWindViola 345kV5/24/2007 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-021ICS-2008-001-604 SOUTHEASTDewey CountyOKOGE8/1/200912/31/2014  198.9198.9198.9ERWindTatonga 345kV5/9/2007 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2007-011N08ICS-2008-001 Prior Queued02 NEBRASKAKnox CountyNENPPD1/1/2009   818181ERWindBloomfield 115kV3/19/2007 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-046ICS-2008-001 Prior Queued04 SOUTHEASTDeweyOKOGE12/31/20096/6/2011  129.6129.6129.6ERWindDewey 138kV12/5/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-044NDISIS-2009-001-602 NEBRASKAPetersburgNENPPD1/1/201012/31/2011  40.540.540.5ERWindNorth Petersburg 115kV12/4/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-044ICS-2008-001 Prior Queued05 SOUTHWESTHansfordTXSPS10/1/201012/31/2022  370370370ERWindHitchland 345kV12/4/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-043ICS-2008-001 Prior Queued04 SOUTHEASTBeckham CountyOKAEP8/1/200812/15/2009  999999ERWindSweetwater 230kV11/17/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-038N019ICS-2008-001 Prior Queued02 NEBRASKABoone CountyNENPPD5/1/201110/31/2011  808080ERWindPetersburg North 115kV10/26/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-038N005ICS-2008-001 Prior Queued02 NEBRASKACuster CountyNENPPD12/1/201012/31/2012  808080ERWindBroken Bow 115kV10/17/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-037N1DISIS-2009-001-602 NEBRASKACuster CountyNENPPD1/1/201012/31/2014  757575ERWindBroken Bow 115kV10/3/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-035ICS-2008-001 Prior Queued04 SOUTHEASTBeckham CountyOKAEP12/1/20084/27/2012  132132132ERWindSweetwater 230kV8/29/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-03103 CENTRALEllis CountyKSMIDW6/1/20086/1/2008  75.675.675.6ERThermalGasKnoll 115kV8/16/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-028LyonKSWERE5/1/20096/1/2009  360300360ERThermalGasEmporia 345kV8/11/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-027LyonKSWERE5/1/20086/1/2008  380310380ERThermalGasEmporia 345kV8/11/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-026ICS-2008-001 Prior Queued05 SOUTHWESTLeaNMSPS6/1/20086/1/2008  604604604ERThermalGasHobbs 230kV & Hobbs 115kV7/26/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-024SICS-2008-001 Prior Queued04 SOUTHEASTHarperOKWFEC12/31/200712/31/2008  18.918.918.9ERWindBuffalo Bear Tap 69kV7/7/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-021ICS-2008-001 Prior Queued03 CENTRALBarber CountyKSITCGP5/31/200812/1/2008  949494ERWindFlat Ridge Tap 138kV6/21/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-020SICS-2008-001 Prior Queued05 SOUTHWESTHansfordTXSPS9/1/20073/1/2012  202020ERWindDWS Frisco 115kV12/31/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-020NICS-2008-001 Prior Queued02 NEBRASKABloomfieldNENPPD1/1/2009   424242ERWindBloomfield 115kV6/20/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-019GreeneMOSPRM6/1/20101/1/2011  275275275ERThermalCoal6/19/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-018ICS-2008-001 Prior Queued05 SOUTHWESTHaleTXSPS6/1/20073/22/2011  168.1168.1168.1ERThermalCTTUCO 230kV6/1/2010 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-01505 SOUTHWESTDenver CityTXSPS4/1/20076/1/2007  150150150ERThermalGasMustang 230kV4/24/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-01004 SOUTHEASTHempstead Co.ARAEP6/1/201112/20/2012  620610620ERThermalCoalTurk 138kV2/27/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-008Caddo Prsh.LAAEP6/1/20086/26/2010  550490550ERThermalGasArsenal Hill 138kV2/27/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2006-002ICS-2008-001 Prior Queued04 SOUTHEASTBeckham OKAEP12/31/200612/28/2010  100.8100.8100.8ERWindSweetwater 230kV1/9/2006 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2005-024Tulsa CountyOKAEP6/1/20073/22/2007  181172181ERThermalGas12/13/2005 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2005-022Caddo CountyOKAEP6/1/200712/27/2007  177168177ERThermalGas12/13/2005 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2005-013ICS-2008-001 Prior Queued03 CENTRALElk CountyKSWERE11/1/20077/5/2011  199.8199.8199.8ERWindCaney River 345kV8/22/2005 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2005-012ICS-2008-001 Prior Queued03 CENTRALFord CountyKSSUNC12/31/20159/1/2012  248.4248.4248.4ERWindClark County-Spearville Ckt 1 (Ironwood) 345kV8/8/2005 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2005-008ICS-2008-001 Prior Queued04 SOUTHEASTHarper CountyOKOGE7/31/20076/30/2007  120120120ERWindWoodward 138kV4/1/2005 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2005-003ICS-2008-001 Prior Queued04 SOUTHEASTCaddo & Kiowa CountiesOKWFEC12/1/200512/15/2005  30.630.630.6ERWindWashita 138kV1/21/2005 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-023NICS-2008-001 Prior Queued02 NEBRASKAColumbusNENPPD1/1/2009   757575ERThermalCoalColumbus Co 115kV11/29/2004 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-023ICS-2008-001 Prior Queued04 SOUTHEASTApacheOKWFEC12/1/200512/15/2005  20.620.620.6ERWindWashita 138kV10/26/2004 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-022NHastingsNENPPD1/1/2005   111111ERThermal10/20/2004 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-020ICS-2008-001 Prior Queued04 SOUTHEASTCuster CountyOKAEP12/31/20051/1/2006  272727ERWindClinton Junction-Weatherford Southeast 138kV10/8/2004 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-019NColfax CountyNENPPD1/1/2005   0.10.10.1ERThermalGas10/4/2004 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-018N1BrownsvilleNENPPD1/1/2005   222222ERThermalNuclear9/20/2004 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-017NColumbusNENPPD1/1/2007   555ERHydro9/13/2004 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-01703 CENTRALRiverton SE Cherokee CntyKSEDE1/1/2007   250250250ER/NRThermalCT/STRiverton 161kV8/23/2004 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-01505 SOUTHWESTDenver City/YoakumTXSPS4/1/20064/1/2006  150150150ERThermalCT7/12/2004 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-014ICS-2008-001 Prior Queued03 CENTRALEdwardsKSMKEC11/15/200512/31/2012  152152152ERWindSpearville 230kV4/22/2004 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-00803 CENTRALPlatte CountyMOKCPL6/1/20096/5/2012  850850850ERThermalCoal3/26/2004 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2004-002OWashington CountyNEOPPD1/1/2007   484848ERThermalNuclear1/21/2004 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2003-022ICS-2008-001 Prior Queued04 SOUTHEASTCuster/WasitaOKAEP12/31/20041/1/2006  120120120ERWindClinton Junction-Weatherford Southeast 138kV12/31/2003 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2003-021NICS-2008-001 Prior Queued02 NEBRASKAAinsworthNENPPD10/1/2005   757575ERWindAinsworth Wind Tap 115kV12/29/2003 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2003-020ICS-2008-001 Prior Queued05 SOUTHWESTCarson CountyTXSPS6/1/20078/1/2012  159.1159.1159.1ERWindMartin 115kV12/29/2003 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2003-019ICS-2008-001 Prior Queued03 CENTRALSalina NC Ellsworth CntyKSMIDW11/1/200611/1/2006  249.3249.3249.3ERWindSmoky Hills Tap 230kV11/24/2003 IA FULLY EXECUTED/COMMERCIAL OPERATION ViewView
GEN-2003-017NBrownsvilleNENPPD1/1/2007   505050ERThermalNuclear10/15/2003 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2003-008OOtoe CountyNEOPPD5/1/2009   700700700ERThermalCoal7/15/2003 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2003-006AICS-2008-001 Prior Queued03 CENTRALCloud CountyKSMKEC    201201201ERWindElm Creek 230kV7/9/2003 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2003-005ICS-2008-001 Prior Queued04 SOUTHEASTApacheOKWFEC12/1/2006   999999ERWindAnadarko - Paradise (Blue Canyon) 138kV6/5/2003 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2003-004ICS-2008-001 Prior Queued04 SOUTHEASTApacheOKWFEC12/1/200512/15/2005  100100100ERWindWashita 138kV6/5/2003 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2002-025AICS-2008-001 Prior Queued03 CENTRALSpearvilleKSMKEC6/1/2006   100.5100.5100.5ERWindSpearville 230kV10/31/2002 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2002-023NHarmonyNENPPD    0.80.80.8ERWindHarmony 115kV9/28/2002 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2002-022ICS-2008-001 Prior Queued05 SOUTHWESTOldham County (Wildorado)TXSPS12/15/2006   239.2239.2239.2ERWindBushland 230kV9/12/2002 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2002-009ICS-2008-001 Prior Queued05 SOUTHWESTHansford CountyTXSPS9/30/20069/30/2006  67.267.267.2ERWindHansford 115kV7/19/2002 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2002-008ICS-2008-001 Prior Queued05 SOUTHWESTHansford CountyTXSPS11/1/200712/30/2008  240240240ERWindHitchland 345kV7/19/2002 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2002-005ICS-2008-001 Prior Queued04 SOUTHEASTHammonOKWFEC12/31/200612/31/2008  123123123ERWindRed Hills Tap 138kV4/28/2002 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2002-004NGrand IslandNENPPD12/1/2003   808080ERThermalGas4/16/2002 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2002-004ICS-2008-001 Prior Queued03 CENTRALBeaumont SE Butler CntyKSWERE9/30/200312/15/2005  153153153ERWindLatham 345kV4/12/2002 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-04003 CENTRALLaRussell Energy Ctr.MOEDE6/1/20034/24/2003  505050ERThermalCTLaRussell Energy Center 161kV11/27/2001 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-039MICS-2008-001 Prior Queued03 CENTRALWichita CountyKSSUNC12/1/2008   100100100ERWindCentral Plains Tap 115kV11/1/2001 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-039AICS-2008-001 Prior Queued03 CENTRALKiowa CountyKSMKEC    104104104ERWindShooting Star Tap 115kV10/30/2001 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-037ICS-2008-001 Prior Queued04 SOUTHEASTWoodwardOKOGE10/1/200211/12/2003  102102102ERWindFPL Moreland Tap 138kV10/18/2001 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-033ICS-2008-001 Prior Queued05 SOUTHWESTChaves County (Melrose)NMSPS10/1/200212/22/2005  120120120ERWindSan Juan Tap 230kV9/17/2001 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-03003 CENTRALLaRussell Energy CenterMOEDE6/1/20034/25/2003  505050ERThermalCTLaRussell Energy Center 161kV9/4/2001 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-029NBeatriceNENPPD1/1/20051/1/2005  250250250ERThermalGas8/15/2001 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-026ICS-2008-001 Prior Queued04 SOUTHEASTMeersOKWFEC10/1/200310/1/2003  74.2574.2574.25ERWindWashita 138kV7/24/2001 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-024Washington CountyARAEP5/1/20077/1/2007  630580630ERThermalCTSWEPCO Tontitown 161kV Substation7/9/2001 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-018Neosho CountyKSWERE1/1/20021/1/2002  474747ERThermalGasChanute NW Neosho Cnty By Tioga Sub5/15/2001 IA FULLY EXECUTED/COMMERCIAL OPERATION   
GEN-2001-014ICS-2008-001 Prior Queued04 SOUTHEASTSleeping BearOKWFEC6/30/20074/15/2007  94.594.594.5ERWindFt Supply 138kV4/24/2001 IA FULLY EXECUTED/COMMERCIAL OPERATION   

Download data as CSV