Study Number |
Date Requested |
Purpose of Study |
Remarks |
Report |
DISIS-2016-001 |
March 31, 2016 |
Definitive Interconnection System Impact Study DISIS-2016-001 |
Posted 2/28/2017 |
Download |
DISIS-2016-001-1 |
March 31, 2016 |
DISIS-2016-001 Restudy #1 (Revised) |
Posted 12/22/2017 |
Download |
DISIS-2016-001-2 |
March 31, 2016 |
DISIS-2016-001 Restudy #2 |
Posted 11/13/2018 Group 3, 6, & 8 Restudy |
Download |
DISIS-2016-001-3 |
March 31, 2016 |
DISIS-2016-001 Restudy #3 |
Re-posted 4/12/2019 Groups 3, 6 & 7 Restudy |
Download |
DISIS-2016-001-4 |
March 31, 2016 |
DISIS-2016-001 Restudy #4 |
Re-posted 4/24/2019 Groups 8 & 9 Restudy |
Download |
DISIS-2016-001-5 |
March 31, 2016 |
DISIS-2016-001 Restudy #5 (Power Flow) |
Updated 2/22/2022 Groups 3,6,7, and 8 |
Download |
DISIS-2016-001-5 |
March 31, 2016 |
DISIS-2016-001 Restudy #5 (Stability) |
Posted 2/19/2020 Groups 6 & 8 |
Download |
DISIS-2016-002 |
November 30, 2016 |
Definitive Interconnection System Impact Study DISIS-2016-002 |
Re-posted 8/20/2018 with Group 9,15,16 Results |
Download |
DISIS-2016-002 Appendix G-T |
November 30, 2016 |
DISIS-2016-002 Appendix G-T in Excel Format |
File Re-posted 8/20/2018 |
Download |
DISIS-2016-002 Group 6 |
October 25, 2022 |
DISIS-2016-02 Group 6 Border 345kV Capacitor Restudy |
Posted 3/3/2023 |
Download |
DISIS-2016-002-1 |
November 30, 2016 |
DISIS-2016-002 Restudy #1 |
Posted 4/26/2019 with Group 6 Results |
Download |
DISIS-2016-002-2 |
November 30, 2016 |
DISIS-2016-002 Restudy #2 (Stability) |
Posted 6/30/20 Group 6, 7, 8, 9, 15, 16 & 17 |
Download |
DISIS-2016-002-2 |
November 30, 2016 |
DISIS-2016-002 Restudy #2 (Power Flow) |
Revised 4/23/2021 Groups 4, 9,15 & 16 |
Download |
DISIS-2016-002-2 |
November 30, 2016 |
DISIS-2016-002-2 Sensitivity Restudy #2 (Stability) |
Posted 4/23/2021 Group 9 |
Download |
DISIS-2016-002-3 |
November 30, 2016 |
DISIS-2016-002 Restudy #3 (Power Flow) Draft Results |
Posted 06/18/21 Group 8 Results |
Download |
DISIS-2016-002-3 |
November 30, 2016 |
DISIS-2016-002 Restudy #3 (Power Flow) Final Results |
Posted 6/01/22 Group 8 Results |
Download |
DISIS-2016-002-4 |
November 30, 2016 |
DISIS-2016-002-4 Restudy Final Results |
Posted 10/18/2022 Group 8 Results |
Download |
GEN-2016-003 |
June 29, 2020 |
Modification Request Impact Study |
Posted 3/11/2021 |
Download |
GEN-2016-003 |
December 07, 2021 |
Modification Request Impact Study |
Posted 05/31/2022 |
Download |
GEN-2016-004 |
May 08, 2017 |
Impact Restudy for Generator Modification |
Posted 3/21/2018 |
Download |
GEN-2016-013 and GEN-2016-014 |
January 19, 2018 |
Modification Request Impact Study for GEN-2016-013 and GEN-2016-014 |
Posted 5/8/2018 |
Download |
GEN-2016-017 |
December 13, 2019 |
Modification Request Impact Study |
Posted 2/28/2020 |
Download |
GEN-2016-020 |
June 07, 2019 |
Modification Request Impact Study |
Posted 9/5/2019 |
Download |
GEN-2016-020 |
July 10, 2020 |
Limited Operation Impact Study for Generation Interconnection Request |
Posted 9/16/2020 |
Download |
GEN-2016-021 |
December 01, 2020 |
Modification Request Impact Study |
Posted 4/20/2021 |
Download |
GEN-2016-022 |
April 19, 2017 |
Impact Restudy for Generator Modification |
Posted 3/21/2018 |
Download |
GEN-2016-022 DISIS ILTCR |
June 30, 2020 |
DISIS-2016-001 ILTCR Study Report |
Posted 05/13/2021 |
Download |
GEN-2016-028 |
March 15, 2018 |
Impact Restudy for Generator Modification |
Posted 5/8/2018 |
Download |
GEN-2016-032 |
May 17, 2019 |
Modification Request Impact Study |
Posted 11/11/2019 |
Download |
GEN-2016-032 |
August 12, 2022 |
Modification Request Impact Study |
Posted 10/31/2022 |
Download |
GEN-2016-036 |
December 20, 2017 |
Interim Availability Impact Study for Generation Interconnection Request |
Posted 3/7/2018 |
Download |
GEN-2016-037 |
November 08, 2021 |
Modification Request Impact Study |
Posted 05/11/2022 |
Download |
GEN-2016-037 |
April 18, 2022 |
Limited Operation Impact Study |
Re-posted 2/17/2023 |
Download |
GEN-2016-037 |
February 09, 2024 |
Limited Impact Study |
Reposted 8/21/2024 |
Download |
GEN-2016-037 |
February 09, 2024 |
Limited Impact Study |
Posted 10/1/2024 |
Download |
GEN-2016-037 |
February 09, 2024 |
Limited Impact Study |
Posted 11/5/2024 |
Download |
GEN-2016-043 |
March 06, 2017 |
Impact Restudy for Generator Modification |
Posted 3/21/2018 |
Download |
GEN-2016-043 |
November 30, 2018 |
Limited Operation Impact Study for Generation Interconnection Request |
Re-Posted 4/8/2020 with Stability Analysis |
Download |
GEN-2016-043 |
May 16, 2019 |
Modification Request Impact Study |
Posted 10/25/2019 |
Download |
GEN-2016-045 and GEN-2016-057 |
April 10, 2019 |
Impact Restudy for Generator Modification (Turbine Change) |
Posted 1/31/2020 |
Download |
GEN-2016-045 and GEN-2016-057 |
December 21, 2020 |
Modification Request Impact Study |
Posted 5/10/2021 |
Download |
GEN-2016-046 |
October 20, 2020 |
Modification Request Impact Study |
Posted 3/23/2021 |
Download |
GEN-2016-050 |
May 12, 2020 |
Limited Operation Impact Study for Generation Interconnection Request |
Posted 5/3/2021 |
Download |
GEN-2016-050 |
July 02, 2021 |
Modification Request Impact Study |
Posted 10/28/2021 |
Download |
GEN-2016-061 |
January 30, 2020 |
Impact Restudy for Generator Modification |
Posted 6/17/2020 |
Download |
GEN-2016-068 |
June 02, 2020 |
Modification Request Impact Study |
Posted 9/18/2020 |
Download |
GEN-2016-071 |
January 06, 2022 |
Modification Request Impact Study |
Posted 05/02/2022 |
Download |
GEN-2016-071 |
May 24, 2019 |
Modification Request Impact Study |
Posted 3/3/2020 |
Download |
GEN-2016-071 |
September 19, 2017 |
Impact Restudy for Generator Modification |
Posted 3/21/2018 |
Download |
GEN-2016-071 |
December 19, 2017 |
Impact Restudy for Generator Modification |
Posted 10/30/2018 |
Download |
GEN-2016-071 |
November 08, 2018 |
Impact Restudy for Generator Modification |
11/27/2018 |
Download |
GEN-2016-074 |
May 13, 2022 |
Limited Operation Impact Study |
Re-posted 2/16/2023 |
Download |
GEN-2016-091 |
April 13, 2021 |
Modification Request Impact Study |
Posted 9/13/2021 |
Download |
GEN-2016-094 |
March 08, 2023 |
Modification Impact Study |
Posted 8/3/2023 |
Download |
GEN-2016-095 |
July 29, 2022 |
Modification Request Impact Study |
Posted 10/17/2022 |
Download |
GEN-2016-097 |
July 29, 2022 |
Modification Request Impact Study |
Posted 10/17/2022 |
Download |
GEN-2016-098 |
July 26, 2017 |
Interim Availability Impact Study for Generation Interconnection Request |
Posted 3/15/2018 |
Download |
GEN-2016-102 |
June 11, 2024 |
Modification Request Impact Study |
Posted 10/2/2024 |
Download |
GEN-2016-115 |
February 05, 2019 |
Impact Restudy for Generator Modification |
Posted 7/30/2019 |
Download |
GEN-2016-118 |
June 02, 2020 |
Modification Request Impact Study |
Posted 2/9/2021 |
Download |
GEN-2016-119 |
May 03, 2022 |
Modification Request Impact Study |
Posted 1/24/2023 |
Download |
GEN-2016-119 DISIS ILTCR |
June 30, 2020 |
DISIS-2016-002 ILTCR Study Report |
Posted 08/06/2021 |
Download |
GEN-2016-123 through 125 |
April 25, 2019 |
Limited Operation Impact Study for Generation Interconnection Request |
Reposted 8/13/2021 |
Download |
GEN-2016-126 |
May 21, 2018 |
Impact Restudy for Generator Modification (POI Change) |
Posted 12/19/2018 |
Download |
GEN-2016-128 |
July 13, 2018 |
Impact Restudy for Generator Modification |
Posted 2/7/2019 |
Download |
GEN-2016-130 |
May 06, 2024 |
Modification Impact Study |
Posted 10/17/24 |
Download |
GEN-2016-130 |
February 16, 2024 |
Limited Impact Study |
Posted 8/21/2024 |
Download |
GEN-2016-133 DISIS ILTCR |
June 30, 2020 |
DISIS-2016-002 ILTCR Study Report |
Posted 08/06/2021 |
Download |
GEN-2016-134 DISIS ILTCR |
June 30, 2020 |
DISIS-2016-002 ILTCR Study Report |
Posted 08/06/2021 |
Download |
GEN-2016-137 DISIS ILTCR |
June 30, 2020 |
DISIS-2016-002 ILTCR Study Report |
Posted 08/06/2021 |
Download |
GEN-2016-138 DISIS ILTCR |
June 30, 2020 |
DISIS-2016-002 ILTCR Study Report |
Posted 08/06/2021 |
Download |
GEN-2016-139 DISIS ILTCR |
June 30, 2020 |
DISIS-2016-002 ILTCR Study Report |
Posted 08/06/2021 |
Download |
GEN-2016-141 DISIS ILTCR |
June 30, 2020 |
DISIS-2016-002 ILTCR Study Report |
Posted 08/06/2021 |
Download |
GEN-2016-142 DISIS ILTCR |
June 30, 2020 |
DISIS-2016-002 ILTCR Study Report |
Posted 08/06/2021 |
Download |
GEN-2016-145 DISIS ILTCR |
June 30, 2020 |
DISIS-2016-002 ILTCR Study Report |
Posted 08/06/2021 |
Download |
GEN-2016-146 DISIS ILTCR |
June 30, 2020 |
DISIS-2016-002 ILTCR Study Report |
Posted 08/06/2021 |
Download |
GEN-2016-147 |
December 01, 2023 |
Limited Impact Study |
Reposted 6/28/2024 |
Download |
GEN-2016-149_GEN-2016-150 |
March 30, 2023 |
Modification Impact Study |
Posted 8/3/2023 |
Download |
GEN-2016-151 |
November 09, 2020 |
Modification Request Impact Study for GEN-2016-151 |
Posted 11/25/2020 |
Download |
GEN-2016-153 |
February 12, 2021 |
Limited Operation Impact Study for Generation Interconnection Request |
Posted 12/6/2021 |
Download |
GEN-2016-153 DISIS ILTCR |
June 30, 2020 |
DISIS-2016-002 ILTCR Study Report |
Posted 08/06/2021 |
Download |
GEN-2016-153_GEN-2017-086 |
June 02, 2023 |
Modification Impact Study |
Posted 9/1/2023 |
Download |
GEN-2016-174 |
May 06, 2020 |
Modification Request Impact Study for GEN-2016-174 |
Posted 9/16/2020 |
Download |
GEN-2016-176 |
April 01, 2021 |
Modification Request Impact Study |
Posted 10/28/2021 |
Download |
Group 9 Interim and Limited Operation |
February 14, 2019 |
Group 9 Interim and Limited Operation |
RePosted 7/15/2021 |
Download |
LOIS-2016-001 Group 8 |
June 06, 2019 |
Limited Operation Impact Study for Generation Interconnection Requests GEN-2016-022, GEN-2016-031, GEN-2016-061, GEN-2016-068, & GEN-2016-071 |
Posted 7/7/2020 |
Download |
PISIS-2016-001 |
March 31, 2016 |
Preliminary Interconnection System Impact Study PISIS-2016-001 |
Posted 10/31/2016 |
Download |
PISIS-2016-002 |
November 30, 2016 |
Preliminary Interconnection System Impact Study PISIS-2016-002 |
No requests were entered in this queue cluster |
|
Please send your requests to GIStudies@spp.org
If you have any questions, please submit a ticket on RMS.
|