2016 Impact Studies
The following Generator Interconnection Studies have been requested.

Study Number Date Requested Purpose of Study Remarks Report
DISIS-2016-001 March 31, 2016 Definitive Interconnection System Impact Study DISIS-2016-001 Posted 2/28/2017 Download
DISIS-2016-001-1 March 31, 2016 DISIS-2016-001 Restudy #1 (Revised) Posted 12/22/2017 Download
DISIS-2016-001-2 March 31, 2016 DISIS-2016-001 Restudy #2 Posted 11/13/2018 Group 3, 6, & 8 Restudy Download
DISIS-2016-001-3 March 31, 2016 DISIS-2016-001 Restudy #3 Re-posted 4/12/2019 Groups 3, 6 & 7 Restudy Download
DISIS-2016-001-4 March 31, 2016 DISIS-2016-001 Restudy #4 Re-posted 4/24/2019 Groups 8 & 9 Restudy Download
DISIS-2016-001-5 March 31, 2016 DISIS-2016-001 Restudy #5 (Power Flow) Updated 2/22/2022 Groups 3,6,7, and 8 Download
DISIS-2016-001-5 March 31, 2016 DISIS-2016-001 Restudy #5 (Stability) Posted 2/19/2020 Groups 6 & 8 Download
DISIS-2016-002 November 30, 2016 Definitive Interconnection System Impact Study DISIS-2016-002 Re-posted 8/20/2018 with Group 9,15,16 Results Download
DISIS-2016-002 Appendix G-T November 30, 2016 DISIS-2016-002 Appendix G-T in Excel Format File Re-posted 8/20/2018 Download
DISIS-2016-002 Group 6 October 25, 2022 DISIS-2016-02 Group 6 Border 345kV Capacitor Restudy Posted 3/3/2023 Download
DISIS-2016-002-1 November 30, 2016 DISIS-2016-002 Restudy #1 Posted 4/26/2019 with Group 6 Results Download
DISIS-2016-002-2 November 30, 2016 DISIS-2016-002 Restudy #2 (Stability) Posted 6/30/20 Group 6, 7, 8, 9, 15, 16 & 17 Download
DISIS-2016-002-2 November 30, 2016 DISIS-2016-002 Restudy #2 (Power Flow) Revised 4/23/2021 Groups 4, 9,15 & 16 Download
DISIS-2016-002-2 November 30, 2016 DISIS-2016-002-2 Sensitivity Restudy #2 (Stability) Posted 4/23/2021 Group 9 Download
DISIS-2016-002-3 November 30, 2016 DISIS-2016-002 Restudy #3 (Power Flow) Draft Results Posted 06/18/21 Group 8 Results Download
DISIS-2016-002-3 November 30, 2016 DISIS-2016-002 Restudy #3 (Power Flow) Final Results Posted 6/01/22 Group 8 Results Download
DISIS-2016-002-4 November 30, 2016 DISIS-2016-002-4 Restudy Final Results Posted 10/18/2022 Group 8 Results Download
GEN-2016-003 June 29, 2020 Modification Request Impact Study Posted 3/11/2021 Download
GEN-2016-003 December 07, 2021 Modification Request Impact Study Posted 05/31/2022 Download
GEN-2016-004 May 08, 2017 Impact Restudy for Generator Modification Posted 3/21/2018 Download
GEN-2016-013 and GEN-2016-014 January 19, 2018 Modification Request Impact Study for GEN-2016-013 and GEN-2016-014 Posted 5/8/2018 Download
GEN-2016-017 December 13, 2019 Modification Request Impact Study Posted 2/28/2020 Download
GEN-2016-020 June 07, 2019 Modification Request Impact Study Posted 9/5/2019 Download
GEN-2016-020 July 10, 2020 Limited Operation Impact Study for Generation Interconnection Request Posted 9/16/2020 Download
GEN-2016-021 December 01, 2020 Modification Request Impact Study Posted 4/20/2021 Download
GEN-2016-022 April 19, 2017 Impact Restudy for Generator Modification Posted 3/21/2018 Download
GEN-2016-022 DISIS ILTCR June 30, 2020 DISIS-2016-001 ILTCR Study Report Posted 05/13/2021 Download
GEN-2016-028 March 15, 2018 Impact Restudy for Generator Modification Posted 5/8/2018 Download
GEN-2016-032 May 17, 2019 Modification Request Impact Study Posted 11/11/2019 Download
GEN-2016-032 August 12, 2022 Modification Request Impact Study Posted 10/31/2022 Download
GEN-2016-036 December 20, 2017 Interim Availability Impact Study for Generation Interconnection Request Posted 3/7/2018 Download
GEN-2016-037 November 08, 2021 Modification Request Impact Study Posted 05/11/2022 Download
GEN-2016-037 April 18, 2022 Limited Operation Impact Study Re-posted 2/17/2023 Download
GEN-2016-037 February 09, 2024 Limited Impact Study Reposted 8/21/2024 Download
GEN-2016-037 February 09, 2024 Limited Impact Study Posted 10/1/2024 Download
GEN-2016-037 February 09, 2024 Limited Impact Study Posted 11/5/2024 Download
GEN-2016-043 March 06, 2017 Impact Restudy for Generator Modification Posted 3/21/2018 Download
GEN-2016-043 November 30, 2018 Limited Operation Impact Study for Generation Interconnection Request Re-Posted 4/8/2020 with Stability Analysis Download
GEN-2016-043 May 16, 2019 Modification Request Impact Study Posted 10/25/2019 Download
GEN-2016-045 and GEN-2016-057 April 10, 2019 Impact Restudy for Generator Modification (Turbine Change) Posted 1/31/2020 Download
GEN-2016-045 and GEN-2016-057 December 21, 2020 Modification Request Impact Study Posted 5/10/2021 Download
GEN-2016-046 October 20, 2020 Modification Request Impact Study Posted 3/23/2021 Download
GEN-2016-050 May 12, 2020 Limited Operation Impact Study for Generation Interconnection Request Posted 5/3/2021 Download
GEN-2016-050 July 02, 2021 Modification Request Impact Study Posted 10/28/2021 Download
GEN-2016-061 January 30, 2020 Impact Restudy for Generator Modification Posted 6/17/2020 Download
GEN-2016-068 June 02, 2020 Modification Request Impact Study Posted 9/18/2020 Download
GEN-2016-071 January 06, 2022 Modification Request Impact Study Posted 05/02/2022 Download
GEN-2016-071 May 24, 2019 Modification Request Impact Study Posted 3/3/2020 Download
GEN-2016-071 September 19, 2017 Impact Restudy for Generator Modification Posted 3/21/2018 Download
GEN-2016-071 December 19, 2017 Impact Restudy for Generator Modification Posted 10/30/2018 Download
GEN-2016-071 November 08, 2018 Impact Restudy for Generator Modification 11/27/2018 Download
GEN-2016-074 May 13, 2022 Limited Operation Impact Study Re-posted 2/16/2023 Download
GEN-2016-091 April 13, 2021 Modification Request Impact Study Posted 9/13/2021 Download
GEN-2016-094 March 08, 2023 Modification Impact Study Posted 8/3/2023 Download
GEN-2016-095 July 29, 2022 Modification Request Impact Study Posted 10/17/2022 Download
GEN-2016-097 July 29, 2022 Modification Request Impact Study Posted 10/17/2022 Download
GEN-2016-098 July 26, 2017 Interim Availability Impact Study for Generation Interconnection Request Posted 3/15/2018 Download
GEN-2016-102 June 11, 2024 Modification Request Impact Study Posted 10/2/2024 Download
GEN-2016-115 February 05, 2019 Impact Restudy for Generator Modification Posted 7/30/2019 Download
GEN-2016-118 June 02, 2020 Modification Request Impact Study Posted 2/9/2021 Download
GEN-2016-119 May 03, 2022 Modification Request Impact Study Posted 1/24/2023 Download
GEN-2016-119 DISIS ILTCR June 30, 2020 DISIS-2016-002 ILTCR Study Report Posted 08/06/2021 Download
GEN-2016-123 through 125 April 25, 2019 Limited Operation Impact Study for Generation Interconnection Request Reposted 8/13/2021 Download
GEN-2016-126 May 21, 2018 Impact Restudy for Generator Modification (POI Change) Posted 12/19/2018 Download
GEN-2016-128 July 13, 2018 Impact Restudy for Generator Modification Posted 2/7/2019 Download
GEN-2016-130 May 06, 2024 Modification Impact Study Posted 10/17/24 Download
GEN-2016-130 February 16, 2024 Limited Impact Study Posted 8/21/2024 Download
GEN-2016-133 DISIS ILTCR June 30, 2020 DISIS-2016-002 ILTCR Study Report Posted 08/06/2021 Download
GEN-2016-134 DISIS ILTCR June 30, 2020 DISIS-2016-002 ILTCR Study Report Posted 08/06/2021 Download
GEN-2016-137 DISIS ILTCR June 30, 2020 DISIS-2016-002 ILTCR Study Report Posted 08/06/2021 Download
GEN-2016-138 DISIS ILTCR June 30, 2020 DISIS-2016-002 ILTCR Study Report Posted 08/06/2021 Download
GEN-2016-139 DISIS ILTCR June 30, 2020 DISIS-2016-002 ILTCR Study Report Posted 08/06/2021 Download
GEN-2016-141 DISIS ILTCR June 30, 2020 DISIS-2016-002 ILTCR Study Report Posted 08/06/2021 Download
GEN-2016-142 DISIS ILTCR June 30, 2020 DISIS-2016-002 ILTCR Study Report Posted 08/06/2021 Download
GEN-2016-145 DISIS ILTCR June 30, 2020 DISIS-2016-002 ILTCR Study Report Posted 08/06/2021 Download
GEN-2016-146 DISIS ILTCR June 30, 2020 DISIS-2016-002 ILTCR Study Report Posted 08/06/2021 Download
GEN-2016-147 December 01, 2023 Limited Impact Study Reposted 6/28/2024 Download
GEN-2016-149_GEN-2016-150 March 30, 2023 Modification Impact Study Posted 8/3/2023 Download
GEN-2016-151 November 09, 2020 Modification Request Impact Study for GEN-2016-151 Posted 11/25/2020 Download
GEN-2016-153 February 12, 2021 Limited Operation Impact Study for Generation Interconnection Request Posted 12/6/2021 Download
GEN-2016-153 DISIS ILTCR June 30, 2020 DISIS-2016-002 ILTCR Study Report Posted 08/06/2021 Download
GEN-2016-153_GEN-2017-086 June 02, 2023 Modification Impact Study Posted 9/1/2023 Download
GEN-2016-174 May 06, 2020 Modification Request Impact Study for GEN-2016-174 Posted 9/16/2020 Download
GEN-2016-176 April 01, 2021 Modification Request Impact Study Posted 10/28/2021 Download
Group 9 Interim and Limited Operation February 14, 2019 Group 9 Interim and Limited Operation RePosted 7/15/2021 Download
LOIS-2016-001 Group 8 June 06, 2019 Limited Operation Impact Study for Generation Interconnection Requests GEN-2016-022, GEN-2016-031, GEN-2016-061, GEN-2016-068, & GEN-2016-071 Posted 7/7/2020 Download
PISIS-2016-001 March 31, 2016 Preliminary Interconnection System Impact Study PISIS-2016-001 Posted 10/31/2016 Download
PISIS-2016-002 November 30, 2016 Preliminary Interconnection System Impact Study PISIS-2016-002 No requests were entered in this queue cluster  

Please send your requests to GIStudies@spp.org