2009 Impact Studies
The following Generator Interconnection Studies have been requested.

Study Number Date Requested Purpose of Study Remarks Report
January 01, 1900  
DISIS-2009-001 September 30, 2009 Definitive Interconnection System Impact Study Posted 1/31/2010 - Reposted 2/5/2010 Download
DISIS-2009-001 September 30, 2009 DISIS-2009-001 Appendices Posted 1/31/2010 Download
DISIS-2009-001 September 30, 2009 DISIS-2009-001 Appendices Posted 1/31/2010 - Reposted 2/5/2010 Download
DISIS-2009-001-1 March 01, 2010 Definitive Interconnection System Impact ReStudy Posted 6/4/2010 Download
DISIS-2009-001-2 November 01, 2010 Definitive Interconnection System Impact ReStudy Posted 1/18/2011 Download
DISIS-2009-001-3 November 01, 2010 Definitive Interconnection System Impact ReStudy Posted 4/14/2011 Download
DISIS-2009-001-4 March 01, 2010 Definitive Interconnection System Impact ReStudy Posted 1/22/2013 Download
DISIS-2009-001-6 November 01, 2010 Definitive Interconnection System Impact ReStudy Posted 11/18/2013 Download
GEN-2009-008 July 13, 2011 Limited Operation Impact Study for Generation Interconnection Request Posted 3/12/2013 Download
GEN-2009-008 November 12, 2012 Restudy to Interconnect 198.8MW to the MIDW transmission system Posted 2/19/2013 Download
GEN-2009-008 November 13, 2012 Impact Restudy for Generator Modification (Turbine change) Posted 2/17/2015 Download
GEN-2009-008 July 13, 2011 Limited Operation Impact Study for Generation Interconnection Request Posted 8/31/2011 Download
GEN-2009-008 August 31, 2010 Study to Interconnect 200.1MW to the MIDW transmission system Posted 4/4/2011 Download
GEN-2009-011 November 22, 2010 Restudy to Interconnect 49MW to the MKEC transmission system Posted 2/23/2011 Download
GEN-2009-011 November 22, 2010 Limited Operation Impact Study for Generation Interconnection Request Posted 4/21/2011 Download
GEN-2009-016 February 10, 2011 Restudy to Interconnect 100.8MW to the AEPW transmission system Posted 5/6/2011 Download
GEN-2009-016 March 08, 2013 Generator Modification Evaluation (Turbine Change) Posted 4/9/2013 Download
GEN-2009-017-DISIS September 30, 2009 DISIS for GEN-2009-017 Posted 3/1/2010 Download
GEN-2009-020 September 10, 2010 Limited Operation Impact Study for Generation Interconnection Request Posted 5/5/2011 Download
GEN-2009-020 September 10, 2010 Restudy to Interconnect 49.6MW to the OKGE transmission system Posted 2/16/2011 Download
GEN-2009-020 September 10, 2010 Re-Study to Interconnect 48.3 MW to the OGE transmission system Posted 3/1/2013 Download
GEN-2009-020 September 10, 2010 Limited Operation Impact Study for Generation Interconnection Request Posted 3/1/2013 Download
GEN-2009-020 November 20, 2012 Impact Restudy for Generator Modification (Turbine Change) Posted 2/27/2014 Download
GEN-2009-025 March 30, 2010 Restudy to Interconnect 60 MW on the OKGE transmission system Revised Posting 10/13/2011 Download
GEN-2009-025 March 30, 2010 Restudy to Interconnect 60 MW on the OKGE transmission system Posted 6/7/2010 Download
GEN-2009-040 August 05, 2014 Impact Restudy for Generator Modification (Turbine Change) Posted 8/27/2014 Download
GEN-2009-040 November 06, 2013 Impact Restudy for Generator Modification (Turbine Change) Posted 2/11/2014 Download
PISIS-2009-001 September 30, 2009 Preliminary Impact Study Appendix N-O Posted 3/30/2010 Download
PISIS-2009-001 September 30, 2009 Preliminary Impact Study Posted 2/26/2010 - Reposted 3/12/2010 Download