Study Number |
Date Requested |
Purpose of Study |
Remarks |
Report |
GEN-2003-002 |
March 11, 2003 |
Request to interconnect up to 200 MW on the WERE system |
Impact Study completed Sept. 28, 2004 |
Download |
GEN-2003-004 |
June 05, 2003 |
Request to interconnect up to 100 MW on the WFEC system |
Impact Study (Re-Study) Completed January 2005 |
Download |
GEN-2003-004 |
June 05, 2003 |
Request to interconnect up to 100MW on the WFEC system |
Impact Study completed April 2004 |
Download |
GEN-2003-004, GEN-2004-023, GEN-2005-003 |
July 06, 2020 |
Modification Request Impact Study |
Posted 6/23/2021 |
Download |
Gen-2003-005 |
June 05, 2003 |
Request to interconnect 100MW on the WFEC system |
Impact Re-Study completed March 2009 |
Download |
Gen-2003-005 |
June 15, 2003 |
Request to interconnect 100MW on the WFEC system |
Impact Re-Study completed September 2008 |
Download |
GEN-2003-005 |
June 05, 2003 |
Request to interconnect up to 120 MW on the WFEC system |
Impact Study completed August 2004 |
Download |
GEN-2003-005 |
June 05, 2003 |
Request to interconnect 100 MW on the WFEC System (Customer reduced to 100 MW) |
Impact Study (Re-Study) completed September 2005 |
Download |
Gen-2003-006A |
July 09, 2003 |
Request to interconnect 200MW on the WPEK system |
Impact Study completed September 2007 |
Download |
GEN-2003-006A |
November 05, 2019 |
Modification Request Impact Study |
Posted 5/29/2020 |
Download |
GEN-2003-009 |
July 16, 2003 |
Request to interconnect 81MW on the SWPS system |
Impact Study Completed February 2004 *****WITHDRAWN***** |
Download |
GEN-2003-013 |
July 29, 2003 |
Request to interconnect 198MW on the SWPS system |
Impact Study completed March 2004 |
Download |
GEN-2003-013 |
July 29, 2003 |
Request to interconnect 198 MW in the SWPS System |
Addendum to Impact Study GEN-2003-013 (Revised 8/26/05) |
Download |
GEN-2003-013-2 |
July 29, 2003 |
Request to interconnect up to 198MW on the SWPS system |
Impact Study revised 6/25/2004 |
Download |
GEN-2003-018 |
October 22, 2003 |
Request to interconnect up to 298.5 MW to the SPS System |
Impact Study Completed 12/2004 ***WITHDRAWN*** |
Download |
Gen-2003-019 |
November 24, 2003 |
Request to interconnect 250MW on the MIDW System |
Impact Study completed February 2007 |
Download |
GEN-2003-019 |
November 24, 2003 |
Request to interconnect up to 250MW on the MIDW system |
Impact Study completed 7-23-2004 ~7.0 MB |
Download |
GEN-2003-019 |
January 21, 2020 |
Impact Restudy for Generator Modification |
Reposted 7/14/2020 |
Download |
Gen-2003-019 |
November 24, 2003 |
Request to interconnect 250MW on the MIDW system |
Impact Re-Study completed November 2007 |
Download |
GEN-2003-019-2 |
November 24, 2003 |
Request to interconnect up to 250 MW on the MIDW system |
Revised Impact Study completed 6/7/2005 |
Download |
GEN-2003-020 |
December 29, 2003 |
Request to interconnect up to 240 MW on the SWPS system. (Customer reduced to 160 MW.) |
Impact Study completed December 2004 |
Download |
GEN-2003-020 |
December 29, 2003 |
Request to interconnect up to 240 MW on the SWPS System (customer reduced to 120 MW) |
Impact Study Re-Study completed May 2, 2006 |
Download |
Gen-2003-020 |
December 29, 2003 |
Request to interconnect 160MW on the SWPS system |
Impact Re-Study completed January 2009 |
Download |
GEN-2003-022 |
December 31, 2003 |
Request to Interconnect 130 MW on the AEPW system |
Impact Study completed June 2004 |
Download |
GEN-2003-022-2 |
December 31, 2003 |
Request to interconnect 130 MW on the AEPW System |
Impact Study Revised 7/2004 |
Download |
Please send your requests to GIStudies@spp.org
If you have any questions, please submit a ticket on RMS.
|