| 2017 Facility Studies | |
| The following Generator Interconnection Studies have been requested. | |
| Study Number | Date Requested | Purpose of Study | Remarks | Report |
|---|---|---|---|---|
| GEN-2017-004 | April 13, 2017 | Interconnect 201.6 MW to the ITCGP Transmission System (queued as IFS-2016-001-05) | Posted 08/02/2022 | Download |
| GEN-2017-005 | January 25, 2018 | Interconnect 190 MW to the WERE Transmission System (queued as IFS-2017-001-11) | Posted 11/19/2021 | Download |
| GEN-2017-009 | April 12, 2017 | Interconnect 302 MW to the WERE Transmission System (queued as IFS-2017-001-39) | Posted 01/14/2022 | Download |
| GEN-2017-010 | April 18, 2017 | Interconnect 200.1 MW to the BEPC Transmission System (queued as IFS-2017-001-12) | Posted 07/29/2022 | Download |
| GEN-2017-011 | May 30, 2017 | Interconnect 151.8 MW to the OKGE Transmission System (queued as IFS-2017-001-06) | Reposted 08/01/2023 | Download |
| GEN-2017-014 | May 30, 2017 | Interconnect 300 MW to the WAPA Transmission System (queued as IFS-2017-001-29) | Posted 03/04/2022 | Download |
| GEN-2017-018 | May 30, 2017 | Interconnect 189 MW to the ITCGP Transmission System (queued as IFS-2017-001-27) | Posted 03/15/2022 | Download |
| GEN-2017-021 | May 31, 2017 | Interconnect 200 MW to the ITCGP Transmission System (queued as IFS-2017-001-21) | Posted 04/20/2022 | Download |
| GEN-2017-022 | May 31, 2017 | Interconnect 65 MW to the WERE Transmission System (queued as IFS-2017-001-21) | Posted 03/28/2022 | Download |
| GEN-2017-023 | May 31, 2017 | Interconnect 85 MW to the WFEC Transmission System (queued as IFS-2017-001-21) | Posted 03/29/2022 | Download |
| GEN-2017-027 | May 31, 2017 | Interconnect 140 MW to the OKGE Transmission System (queued as IFS-2017-001-33) | Posted 01/07/2022 | Download |
| GEN-2017-032 | May 30, 2017 | Interconnect 200 MW to the SPS Transmission System (queued as IFS-2017-001-38) | Posted 03/15/2022 | Download |
| GEN-2017-033 | May 30, 2017 | Interconnect 200 MW to the AEP Transmission System (queued as IFS-2017-001-28) | Posted 12/17/2021 | Download |
| GEN-2017-036 | May 31, 2017 | Interconnect 100 MW to the AEPW Transmission System (queued as IFS-2017-001-23) | Posted 12/29/2021 | Download |
| GEN-2017-040 | May 17, 2017 | Interconnect 200.1 MW to the OKGE Transmission System (queued as IFS-2017-001-03) | Posted 01/24/2022 | Download |
| GEN-2017-047 | May 26, 2017 | Interconnect 102 MW to the SWPS Transmission System (queued as IFS-2017-001-19) | Posted 03/29/2022 | Download |
| GEN-2017-048 | May 30, 2017 | Interconnect 300 MW to the BEPC Transmission System (queued as IFS-2017-001-34) | Posted 02/28/2023 | Download |
| GEN-2017-057 | October 16, 2018 | Interconnect 72.5 MW to the AEP Transmission System (queued as IFS-2017-001-13) | Posted 10/08/2021 | Download |
| GEN-2017-060 | May 30, 2017 | Interconnect 149.4 MW to the EMDE Transmission System (queued as IFS-2017-001-01) | Posted 10/08/2021 | Download |
| GEN-2017-061 | May 28, 2017 | Interconnect 101.5 MW to the GRDA Transmission System (queued as IFS-2017-001-25) | Posted 01/31/2022 | Download |
| GEN-2017-068 | May 30, 2017 | Interconnect 103.5 MW to the WERE Transmission System (queued as IFS-2017-001-26) | Posted 03/29/2022 | Download |
| GEN-2017-071 | May 28, 2017 | Interconnect 124.7 MW to the OKGE Transmission System (queued as IFS-2017-001-36) | Posted 01/25/2022 | Download |
| GEN-2017-072 | May 30, 2017 | Interconnect 52.2 MW to the OKGE Transmission System (queued as IFS-2017-001-37) | Posted 01/25/2022 | Download |
| GEN-2017-073 | May 30, 2017 | Interconnect 72.5 MW to the GRDA Transmission System (queued as IFS-2017-001-14) | Posted 01/28/2022 | Download |
| GEN-2017-074 | May 30, 2017 | Interconnect 72.5 MW to the AEP Transmission System (queued as IFS-2017-001-15) | Posted 02/28/2022 | Download |
| GEN-2017-075 | May 30, 2017 | Interconnect 200 MW to the OKGE Transmission System (queued as IFS-2017-001-16) | Posted 01/07/2022 | Download |
| GEN-2017-076 | October 16, 2018 | Interconnect 52.2 MW to the AEP Transmission System (queued as IFS-2017-001-17) | Posted 10/08/2021 | Download |
| GEN-2017-077 | May 28, 2017 | Interconnect 124.7 MW to the AEPW Transmission System (queued as IFS-2017-001-18) | Posted 02/08/2022 | Download |
| GEN-2017-082 | May 30, 2017 | Interconnect 149.4 MW to the EMDE Transmission System (queued as IFS-2017-001-02) | Posted 10/08/2021 | Download |
| GEN-2017-085 | May 10, 2017 | Interconnect .6 MW to the NPPD Transmission System (queued as IFS-2017-001-30) | Posted 12/01/2021 | Download |
| GEN-2017-086 | November 07, 2017 | Interconnect 150 MW to the WERE Transmission System (queued as IFS-2017-001-10) | Posted 03/29/2022 | Download |
| GEN-2017-090 | November 08, 2017 | Interconnect 150 MW to the KCPL Transmission System (queued as IFS-2017-001-35) | Posted 02/28/2022 | Download |
| GEN-2017-092 | May 30, 2017 | Interconnect 200 MW to the OKGE Transmission System (queued as IFS-2017-001-04) | Posted 01/24/2022 | Download |
| GEN-2017-094 | May 30, 2017 | Interconnect 200 MW to the WAPA Transmission System (queued as IFS-2017-001-31) | Posted 03/03/2022 | Download |
| GEN-2017-097 | May 31, 2017 | Interconnect 128 MW to the WAPA Transmission System (queued as IFS-2017-001-24) | Posted 02/14/2022 | Download |
| GEN-2017-099 | May 31, 2017 | Interconnect 150 MW to the ITCGP Transmission System (queued as IFS-2017-001-09) | Posted 04/20/2022 | Download |
| GEN-2017-100 | May 30, 2017 | Interconnect 102.6 MW to the SWPS Transmission System (queued as IFS-2017-001-20) | Posted 03/29/2022 | Download |
| GEN-2017-105 | October 13, 2022 | Interconnect 75 MW to the OPPD Transmission System (FINAL) | Posted 02/13/2023 | Download |
| GEN-2017-108 | December 29, 2022 | Interconnect 400 MW to KCPL transmission system FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-111 | December 29, 2022 | Interconnect 152 MW to KCPL transmission system FINAL | Posted 08/22/2023 | Download |
| GEN-2017-115 | December 29, 2022 | Interconnect 244 MW to KCPL transmission system FINAL | Reposted 07/25/2023 | Download |
| GEN-2017-117 | December 29, 2022 | Interconnect 19.8 MW to the WFECTransmission System FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-119 | December 29, 2022 | Interconnect 180 MW to SUNC transmission system FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-120 | December 29, 2022 | Interconnect 260 MW to WERE transmission system FINAL | Posted 07/25/2023 | Download |
| GEN-2017-121 | December 29, 2022 | Interconnect 200 MW to the WERE Transmission System FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-125 | December 29, 2022 | Interconnect 252 MW to the WERE Transmission System FINAL | Reposted 11/30/2023 | Download |
| GEN-2017-128 | December 29, 2022 | Interconnect 202 MW to the WERE Transmission System | Posted 07/25/2023 | Download |
| GEN-2017-131 | July 03, 2024 | Interconnect 29.6 MW to the WERE Transmission System FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-132 | December 29, 2022 | Interconnect 400 MW to the OGE Transmission System FINAL | Posted 07/26/2023 | Download |
| GEN-2017-133 | December 29, 2022 | Interconnect 200 MW to the OGE Transmission System FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-134 | December 29, 2022 | Interconnect 250 MW to the OGE Transmission System FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-137 | December 29, 2022 | Interconnect 295 MW to the OGE Transmission System FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-140 | December 29, 2022 | Interconnect 160 MW to the AEP Transmission System FINAL | Posted 06/05/2023 | Download |
| GEN-2017-141 | December 29, 2022 | Interconnect 241.7 MW to the AEP Transmission System FINAL | Posted 06/05/2023 | Download |
| GEN-2017-144 | October 13, 2022 | Interconnect 200 MW to the NPPD Transmission System (FINAL) | Posted 02/15/2023 | Download |
| GEN-2017-146 | December 29, 2022 | Interconnect 151.8 MW to SPS transmission system FINAL | Posted 05/15/2023 | Download |
| GEN-2017-148 | October 13, 2022 | Interconnect 202 MW to the EDE Transmission System FINAL | Reposted 08/24/2023 | Download |
| GEN-2017-149 | December 29, 2022 | Interconnect 258 MW to the OGE Transmission System FINAL | Reposted 08/06/2024 | Download |
| GEN-2017-150 | December 29, 2022 | Interconnect 250 MW to the OGE Transmission System FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-151 | December 29, 2022 | Interconnect 300 MW to SPS transmission system FINAL | Reposted 09/16/2025 | Download |
| GEN-2017-152 | December 29, 2022 | Interconnect 252 MW to the OGE Transmission System FINAL | Posted 06/05/2023 | Download |
| GEN-2017-154 | December 29, 2022 | Interconnect 255 MW to the OGE Transmission System FINAL | Reposted 08/06/2024 | Download |
| GEN-2017-155 | December 29, 2022 | Interconnect 300 MW to the OGE Transmission System FINAL | Reposted 07/25/2023 | Download |
| GEN-2017-158 | December 29, 2022 | Interconnect 265 MW to SPS transmission system FINAL | Posted 05/19/2023 | Download |
| GEN-2017-164 | December 29, 2022 | Interconnect 250 MW to the OGE Transmission System FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-166 | December 29, 2022 | Interconnect 250 MW to the OGE Transmission System FINAL | Posted 07/25/2023 | Download |
| GEN-2017-167 | December 29, 2022 | Interconnect 52 MW to the OGE Transmission System FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-168 | December 29, 2022 | Interconnect 250 MW to the OGE Transmission System FINAL | Posted 06/07/2023 | Download |
| GEN-2017-169 | December 29, 2022 | Interconnect 52 MW to the OGE Transmission System FINAL | Posted 06/05/2023 | Download |
| GEN-2017-171 | December 29, 2022 | Interconnect 150 MW to the AEP Transmission System FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-172 | December 29, 2022 | Interconnect 50 MW to the AEP Transmission System FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-173 | December 29, 2022 | Interconnect 50 MW to the AEP Transmission System FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-175 | December 29, 2022 | Interconnect 300 MW to WAPA transmission system FINAL | Reposted 08/14/2023 | Download |
| GEN-2017-178 | December 29, 2022 | Interconnect 52 MW to the OGE Transmission System FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-179 | December 29, 2022 | Interconnect 222 MW to the WERE Transmission System FINAL | Reposted 07/25/2023 | Download |
| GEN-2017-181 | October 13, 2022 | Interconnect 300 MW to the NPPD Transmission System (FINAL) | Reposted 07/03/2024 | Download |
| GEN-2017-182 | October 13, 2022 | Interconnect 128 MW to the NPPD Transmission System (FINAL) | Reposted 07/03/2024 | Download |
| GEN-2017-183 | December 29, 2022 | Interconnect 400 MW to KCPL transmission system FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-184 | December 29, 2022 | Interconnect 400 MW to KCPL transmission system FINAL | Reposted 07/05/2024 | Download |
| GEN-2017-187 | December 29, 2022 | Interconnect 150 MW to SPS transmission system FINAL | Posted 05/24/2023 | Download |
| GEN-2017-188 | October 13, 2022 | Interconnect 130 MW to the EDE Transmission System (FINAL) | Reposted 07/03/2024 | Download |
| GEN-2017-191 | December 29, 2022 | Interconnect 201.6 MW to the WERE Transmission System FINAL | Reposted 07/25/2023 | Download |
| GEN-2017-192 | December 29, 2022 | Interconnect 52 MW to the WERE Transmission System FINAL | Posted 07/07/2023 | Download |
| GEN-2017-194 | December 29, 2022 | Interconnect 52 MW to the WERE Transmission System | Posted 04/13/2023 | Download |
| GEN-2017-195 | December 29, 2022 | Interconnect 500.4 MW to the KCPL Transmission System FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-196 | March 07, 2024 | Interconnect 128 MW to KCPL transmission system FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-198 | October 13, 2022 | Interconnect 11.64 MW to the OPPD Transmission System (FINAL) | Posted 02/03/2023 | Download |
| GEN-2017-199 | December 29, 2022 | Interconnect 202 MW to the BEPC Transmission System | Posted 04/13/2023 | Download |
| GEN-2017-200 | December 29, 2022 | Interconnect 302 MW to the BEPC Transmission System | Posted 04/13/2023 | Download |
| GEN-2017-201 | October 13, 2022 | Interconnect 250 MW to the NPPD Transmission System (FINAL) | Reposted 07/03/2024 | Download |
| GEN-2017-202 | October 13, 2022 | Interconnect 200 MW to the SWPA Transmission System (FINAL) | Reposted 07/25/2023 | Download |
| GEN-2017-203 | December 29, 2022 | Interconnect 210 MW to the OGE Transmission System FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-209 | December 29, 2022 | Interconnect 300 MW to KCPL transmission system FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-210 | October 13, 2022 | Interconnect 310 MW to the NPPD Transmission System (FINAL) | Reposted 07/03/2024 | Download |
| GEN-2017-214 | December 29, 2022 | Interconnect 100 MW to the BEPC Transmission System FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-215 | December 29, 2022 | Interconnect 100 MW to the BEPC Transmission System FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-216 | December 29, 2022 | Interconnect 100 MW to the BEPC Transmission System FINAL | Posted 05/24/2023 | Download |
| GEN-2017-220 | December 29, 2022 | Interconnect 201.6 MW to the WERE Transmission System FINAL | Reposted 04/18/2025 | Download |
| GEN-2017-221 | December 29, 2022 | Interconnect 152 MW to the WERE Transmission System FINAL | Reposted 04/18/2025 | Download |
| GEN-2017-222 | October 13, 2022 | Interconnect 180 MW to the WAPA Transmission System (FINAL) | Reposted 11/20/2025 | Download |
| GEN-2017-225 | December 29, 2022 | Interconnect 76 MW to the KCPL Transmission System | Posted 04/13/2023 | Download |
| GEN-2017-226 | December 29, 2022 | Interconnect 201.6 MW to the WERE Transmission System FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-227 | December 29, 2022 | Interconnect 201.6 MW to the WERE Transmission System FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-229 | December 29, 2022 | Interconnect 76 MW to the WERE Transmission System FINAL | Posted 07/07/2023 | Download |
| GEN-2017-230 | December 29, 2022 | Interconnect 72.5 MW to the OGE Transmission System FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-231 | December 29, 2022 | Interconnect 72.5 MW to OGE transmission system FINAL | Posted 06/21/2023 | Download |
| GEN-2017-232 | December 29, 2022 | Interconnect 52.2 MW to the OGE Transmission System FINAL | Reposted 07/03/2024 | Download |
| GEN-2017-233 | December 29, 2022 | Interconnect 215 MW to the OGE Transmission System FINAL | Reposted 08/06/2024 | Download |
| GEN-2017-234 | October 13, 2022 | Interconnect115 MW to the NPPD Transmission System (FINAL) | Reposted 07/03/2024 | Download |
| GEN-2017-235 | December 29, 2022 | Interconnect 50 MW to BEPC transmission system | Posted on 04/25/2023 | Download |
| GEN-2017-236 | December 29, 2022 | Interconnect 50 MW to BEPC transmission system | Posted on 04/25/2023 | Download |
| GEN-2017-239 | December 29, 2022 | Interconnect 300 MW to SPS transmission system FINAL | Posted 05/16/2023 | Download |
| GEN-2017-240 | December 29, 2022 | Interconnect 202 MW to the OGE Transmission System | Posted 05/03/2023 | Download |
|
Please send your requests to GIStudies@spp.org If you have any questions, please submit a ticket on RMS. |
||||