OASIS Apps

- Curtailment Viewer
- DC Tie Viewer
- Price Discounts
- Price Matrix
- Transmission Load Relief

- SPP OASIS Archive Map
    > SPP OASIS Archive Page
    > Market System Status
    > Member Related Postings
    > FERC890 Items

- Studies Postings
 
SPP Logo
 
2017 Facility Studies
The following Generator Interconnection Studies have been requested.

Study Number Date Requested Purpose of Study Remarks Report
GEN-2017-004 April 13, 2017 Interconnect 201.6 MW to the ITCGP Transmission System (queued as IFS-2016-001-05) Posted 08/02/2022 Download
GEN-2017-005 January 25, 2018 Interconnect 190 MW to the WERE Transmission System (queued as IFS-2017-001-11) Posted 11/19/2021 Download
GEN-2017-009 April 12, 2017 Interconnect 302 MW to the WERE Transmission System (queued as IFS-2017-001-39) Posted 01/14/2022 Download
GEN-2017-010 April 18, 2017 Interconnect 200.1 MW to the BEPC Transmission System (queued as IFS-2017-001-12) Posted 07/29/2022 Download
GEN-2017-011 May 30, 2017 Interconnect 151.8 MW to the OKGE Transmission System (queued as IFS-2017-001-06) Reposted 08/01/2023 Download
GEN-2017-014 May 30, 2017 Interconnect 300 MW to the WAPA Transmission System (queued as IFS-2017-001-29) Posted 03/04/2022 Download
GEN-2017-018 May 30, 2017 Interconnect 189 MW to the ITCGP Transmission System (queued as IFS-2017-001-27) Posted 03/15/2022 Download
GEN-2017-021 May 31, 2017 Interconnect 200 MW to the ITCGP Transmission System (queued as IFS-2017-001-21) Posted 04/20/2022 Download
GEN-2017-022 May 31, 2017 Interconnect 65 MW to the WERE Transmission System (queued as IFS-2017-001-21) Posted 03/28/2022 Download
GEN-2017-023 May 31, 2017 Interconnect 85 MW to the WFEC Transmission System (queued as IFS-2017-001-21) Posted 03/29/2022 Download
GEN-2017-027 May 31, 2017 Interconnect 140 MW to the OKGE Transmission System (queued as IFS-2017-001-33) Posted 01/07/2022 Download
GEN-2017-032 May 30, 2017 Interconnect 200 MW to the SPS Transmission System (queued as IFS-2017-001-38) Posted 03/15/2022 Download
GEN-2017-033 May 30, 2017 Interconnect 200 MW to the AEP Transmission System (queued as IFS-2017-001-28) Posted 12/17/2021 Download
GEN-2017-036 May 31, 2017 Interconnect 100 MW to the AEPW Transmission System (queued as IFS-2017-001-23) Posted 12/29/2021 Download
GEN-2017-040 May 17, 2017 Interconnect 200.1 MW to the OKGE Transmission System (queued as IFS-2017-001-03) Posted 01/24/2022 Download
GEN-2017-047 May 26, 2017 Interconnect 102 MW to the SWPS Transmission System (queued as IFS-2017-001-19) Posted 03/29/2022 Download
GEN-2017-048 May 30, 2017 Interconnect 300 MW to the BEPC Transmission System (queued as IFS-2017-001-34) Posted 02/28/2023 Download
GEN-2017-057 October 16, 2018 Interconnect 72.5 MW to the AEP Transmission System (queued as IFS-2017-001-13) Posted 10/08/2021 Download
GEN-2017-060 May 30, 2017 Interconnect 149.4 MW to the EMDE Transmission System (queued as IFS-2017-001-01) Posted 10/08/2021 Download
GEN-2017-061 May 28, 2017 Interconnect 101.5 MW to the GRDA Transmission System (queued as IFS-2017-001-25) Posted 01/31/2022 Download
GEN-2017-068 May 30, 2017 Interconnect 103.5 MW to the WERE Transmission System (queued as IFS-2017-001-26) Posted 03/29/2022 Download
GEN-2017-071 May 28, 2017 Interconnect 124.7 MW to the OKGE Transmission System (queued as IFS-2017-001-36) Posted 01/25/2022 Download
GEN-2017-072 May 30, 2017 Interconnect 52.2 MW to the OKGE Transmission System (queued as IFS-2017-001-37) Posted 01/25/2022 Download
GEN-2017-073 May 30, 2017 Interconnect 72.5 MW to the GRDA Transmission System (queued as IFS-2017-001-14) Posted 01/28/2022 Download
GEN-2017-074 May 30, 2017 Interconnect 72.5 MW to the AEP Transmission System (queued as IFS-2017-001-15) Posted 02/28/2022 Download
GEN-2017-075 May 30, 2017 Interconnect 200 MW to the OKGE Transmission System (queued as IFS-2017-001-16) Posted 01/07/2022 Download
GEN-2017-076 October 16, 2018 Interconnect 52.2 MW to the AEP Transmission System (queued as IFS-2017-001-17) Posted 10/08/2021 Download
GEN-2017-077 May 28, 2017 Interconnect 124.7 MW to the AEPW Transmission System (queued as IFS-2017-001-18) Posted 02/08/2022 Download
GEN-2017-082 May 30, 2017 Interconnect 149.4 MW to the EMDE Transmission System (queued as IFS-2017-001-02) Posted 10/08/2021 Download
GEN-2017-085 May 10, 2017 Interconnect .6 MW to the NPPD Transmission System (queued as IFS-2017-001-30) Posted 12/01/2021 Download
GEN-2017-086 November 07, 2017 Interconnect 150 MW to the WERE Transmission System (queued as IFS-2017-001-10) Posted 03/29/2022 Download
GEN-2017-090 November 08, 2017 Interconnect 150 MW to the KCPL Transmission System (queued as IFS-2017-001-35) Posted 02/28/2022 Download
GEN-2017-092 May 30, 2017 Interconnect 200 MW to the OKGE Transmission System (queued as IFS-2017-001-04) Posted 01/24/2022 Download
GEN-2017-094 May 30, 2017 Interconnect 200 MW to the WAPA Transmission System (queued as IFS-2017-001-31) Posted 03/03/2022 Download
GEN-2017-097 May 31, 2017 Interconnect 128 MW to the WAPA Transmission System (queued as IFS-2017-001-24) Posted 02/14/2022 Download
GEN-2017-099 May 31, 2017 Interconnect 150 MW to the ITCGP Transmission System (queued as IFS-2017-001-09) Posted 04/20/2022 Download
GEN-2017-100 May 30, 2017 Interconnect 102.6 MW to the SWPS Transmission System (queued as IFS-2017-001-20) Posted 03/29/2022 Download
GEN-2017-105 October 13, 2022 Interconnect 75 MW to the OPPD Transmission System (FINAL) Posted 02/13/2023 Download
GEN-2017-108 December 29, 2022 Interconnect 400 MW to KCPL transmission system FINAL Reposted 07/03/2024 Download
GEN-2017-111 December 29, 2022 Interconnect 152 MW to KCPL transmission system FINAL Posted 08/22/2023 Download
GEN-2017-115 December 29, 2022 Interconnect 244 MW to KCPL transmission system FINAL Reposted 07/25/2023 Download
GEN-2017-117 December 29, 2022 Interconnect 19.8 MW to the WFECTransmission System FINAL Reposted 07/03/2024 Download
GEN-2017-119 December 29, 2022 Interconnect 180 MW to SUNC transmission system FINAL Reposted 07/03/2024 Download
GEN-2017-120 December 29, 2022 Interconnect 260 MW to WERE transmission system FINAL Posted 07/25/2023 Download
GEN-2017-121 December 29, 2022 Interconnect 200 MW to the WERE Transmission System FINAL Reposted 07/03/2024 Download
GEN-2017-125 December 29, 2022 Interconnect 252 MW to the WERE Transmission System FINAL Reposted 11/30/2023 Download
GEN-2017-128 December 29, 2022 Interconnect 202 MW to the WERE Transmission System Posted 07/25/2023 Download
GEN-2017-131 July 03, 2024 Interconnect 29.6 MW to the WERE Transmission System FINAL Reposted 07/03/2024 Download
GEN-2017-132 December 29, 2022 Interconnect 400 MW to the OGE Transmission System FINAL Posted 07/26/2023 Download
GEN-2017-133 December 29, 2022 Interconnect 200 MW to the OGE Transmission System FINAL Reposted 07/03/2024 Download
GEN-2017-134 December 29, 2022 Interconnect 250 MW to the OGE Transmission System FINAL Reposted 07/03/2024 Download
GEN-2017-137 December 29, 2022 Interconnect 295 MW to the OGE Transmission System FINAL Reposted 07/03/2024 Download
GEN-2017-140 December 29, 2022 Interconnect 160 MW to the AEP Transmission System FINAL Posted 06/05/2023 Download
GEN-2017-141 December 29, 2022 Interconnect 241.7 MW to the AEP Transmission System FINAL Posted 06/05/2023 Download
GEN-2017-144 October 13, 2022 Interconnect 200 MW to the NPPD Transmission System (FINAL) Posted 02/15/2023 Download
GEN-2017-146 December 29, 2022 Interconnect 151.8 MW to SPS transmission system FINAL Posted 05/15/2023 Download
GEN-2017-148 October 13, 2022 Interconnect 202 MW to the EDE Transmission System FINAL Reposted 08/24/2023 Download
GEN-2017-149 December 29, 2022 Interconnect 258 MW to the OGE Transmission System FINAL Reposted 08/06/2024 Download
GEN-2017-150 December 29, 2022 Interconnect 250 MW to the OGE Transmission System FINAL Reposted 07/03/2024 Download
GEN-2017-151 December 29, 2022 Interconnect 300 MW to SPS transmission system FINAL Posted 05/15/2023 Download
GEN-2017-152 December 29, 2022 Interconnect 252 MW to the OGE Transmission System FINAL Posted 06/05/2023 Download
GEN-2017-154 December 29, 2022 Interconnect 255 MW to the OGE Transmission System FINAL Reposted 08/06/2024 Download
GEN-2017-155 December 29, 2022 Interconnect 300 MW to the OGE Transmission System FINAL Reposted 07/25/2023 Download
GEN-2017-158 December 29, 2022 Interconnect 265 MW to SPS transmission system FINAL Posted 05/19/2023 Download
GEN-2017-164 December 29, 2022 Interconnect 250 MW to the OGE Transmission System FINAL Reposted 07/03/2024 Download
GEN-2017-166 December 29, 2022 Interconnect 250 MW to the OGE Transmission System FINAL Posted 07/25/2023 Download
GEN-2017-167 December 29, 2022 Interconnect 52 MW to the OGE Transmission System FINAL Reposted 07/03/2024 Download
GEN-2017-168 December 29, 2022 Interconnect 250 MW to the OGE Transmission System FINAL Posted 06/07/2023 Download
GEN-2017-169 December 29, 2022 Interconnect 52 MW to the OGE Transmission System FINAL Posted 06/05/2023 Download
GEN-2017-171 December 29, 2022 Interconnect 150 MW to the AEP Transmission System FINAL Reposted 07/03/2024 Download
GEN-2017-172 December 29, 2022 Interconnect 50 MW to the AEP Transmission System FINAL Reposted 07/03/2024 Download
GEN-2017-173 December 29, 2022 Interconnect 50 MW to the AEP Transmission System FINAL Reposted 07/03/2024 Download
GEN-2017-175 December 29, 2022 Interconnect 300 MW to WAPA transmission system FINAL Reposted 08/14/2023 Download
GEN-2017-178 December 29, 2022 Interconnect 52 MW to the OGE Transmission System FINAL Reposted 07/03/2024 Download
GEN-2017-179 December 29, 2022 Interconnect 222 MW to the WERE Transmission System FINAL Reposted 07/25/2023 Download
GEN-2017-181 October 13, 2022 Interconnect 300 MW to the NPPD Transmission System (FINAL) Reposted 07/03/2024 Download
GEN-2017-182 October 13, 2022 Interconnect 128 MW to the NPPD Transmission System (FINAL) Reposted 07/03/2024 Download
GEN-2017-183 December 29, 2022 Interconnect 400 MW to KCPL transmission system FINAL Reposted 07/03/2024 Download
GEN-2017-184 December 29, 2022 Interconnect 400 MW to KCPL transmission system FINAL Reposted 07/05/2024 Download
GEN-2017-187 December 29, 2022 Interconnect 150 MW to SPS transmission system FINAL Posted 05/24/2023 Download
GEN-2017-188 October 13, 2022 Interconnect 130 MW to the EDE Transmission System (FINAL) Reposted 07/03/2024 Download
GEN-2017-191 December 29, 2022 Interconnect 201.6 MW to the WERE Transmission System FINAL Reposted 07/25/2023 Download
GEN-2017-192 December 29, 2022 Interconnect 52 MW to the WERE Transmission System FINAL Posted 07/07/2023 Download
GEN-2017-194 December 29, 2022 Interconnect 52 MW to the WERE Transmission System Posted 04/13/2023 Download
GEN-2017-195 December 29, 2022 Interconnect 500.4 MW to the KCPL Transmission System FINAL Reposted 07/03/2024 Download
GEN-2017-196 March 07, 2024 Interconnect 128 MW to KCPL transmission system FINAL Reposted 07/03/2024 Download
GEN-2017-198 October 13, 2022 Interconnect 11.64 MW to the OPPD Transmission System (FINAL) Posted 02/03/2023 Download
GEN-2017-199 December 29, 2022 Interconnect 202 MW to the BEPC Transmission System Posted 04/13/2023 Download
GEN-2017-200 December 29, 2022 Interconnect 302 MW to the BEPC Transmission System Posted 04/13/2023 Download
GEN-2017-201 October 13, 2022 Interconnect 250 MW to the NPPD Transmission System (FINAL) Reposted 07/03/2024 Download
GEN-2017-202 October 13, 2022 Interconnect 200 MW to the SWPA Transmission System (FINAL) Reposted 07/25/2023 Download
GEN-2017-203 December 29, 2022 Interconnect 210 MW to the OGE Transmission System FINAL Reposted 07/03/2024 Download
GEN-2017-209 December 29, 2022 Interconnect 300 MW to KCPL transmission system FINAL Reposted 07/03/2024 Download
GEN-2017-210 October 13, 2022 Interconnect 310 MW to the NPPD Transmission System (FINAL) Reposted 07/03/2024 Download
GEN-2017-214 December 29, 2022 Interconnect 100 MW to the BEPC Transmission System FINAL Reposted 07/03/2024 Download
GEN-2017-215 December 29, 2022 Interconnect 100 MW to the BEPC Transmission System FINAL Reposted 07/03/2024 Download
GEN-2017-216 December 29, 2022 Interconnect 100 MW to the BEPC Transmission System FINAL Posted 05/24/2023 Download
GEN-2017-220 December 29, 2022 Interconnect 201.6 MW to the WERE Transmission System FINAL Reposted 07/03/2024 Download
GEN-2017-221 December 29, 2022 Interconnect 152 MW to the WERE Transmission System FINAL Reposted 07/03/2024 Download
GEN-2017-222 October 13, 2022 Interconnect 180 MW to the WAPA Transmission System (FINAL) Reposted 7/25/2023 Download
GEN-2017-225 December 29, 2022 Interconnect 76 MW to the KCPL Transmission System Posted 04/13/2023 Download
GEN-2017-226 December 29, 2022 Interconnect 201.6 MW to the WERE Transmission System FINAL Reposted 07/03/2024 Download
GEN-2017-227 December 29, 2022 Interconnect 201.6 MW to the WERE Transmission System FINAL Reposted 07/03/2024 Download
GEN-2017-229 December 29, 2022 Interconnect 76 MW to the WERE Transmission System FINAL Posted 07/07/2023 Download
GEN-2017-230 December 29, 2022 Interconnect 72.5 MW to the OGE Transmission System FINAL Reposted 07/03/2024 Download
GEN-2017-231 December 29, 2022 Interconnect 72.5 MW to OGE transmission system FINAL Posted 06/21/2023 Download
GEN-2017-232 December 29, 2022 Interconnect 52.2 MW to the OGE Transmission System FINAL Reposted 07/03/2024 Download
GEN-2017-233 December 29, 2022 Interconnect 215 MW to the OGE Transmission System FINAL Reposted 08/06/2024 Download
GEN-2017-234 October 13, 2022 Interconnect115 MW to the NPPD Transmission System (FINAL) Reposted 07/03/2024 Download
GEN-2017-235 December 29, 2022 Interconnect 50 MW to BEPC transmission system Posted on 04/25/2023 Download
GEN-2017-236 December 29, 2022 Interconnect 50 MW to BEPC transmission system Posted on 04/25/2023 Download
GEN-2017-239 December 29, 2022 Interconnect 300 MW to SPS transmission system FINAL Posted 05/16/2023 Download
GEN-2017-240 December 29, 2022 Interconnect 202 MW to the OGE Transmission System Posted 05/03/2023 Download

Please send your requests to GIStudies@spp.org

If you have any questions, please submit a ticket on RMS.