Study Number |
Date Requested |
Purpose of Study |
Remarks |
Report |
Gen-2008-002 |
January 22, 2008 |
Request to interconnect 75MW on the KACP system |
Impact Study completed August 2008 |
Download |
Gen-2008-003 |
January 25, 2008 |
Request to interconnect 120MW on the OKGE system |
Interim Impact Study completed May 2009 |
Download |
Gen-2008-005 |
January 28, 2008 |
Request to interconnect 16MW on the GRDA system |
Impact study completed August 2008 |
Download |
Gen-2008-006 |
January 31, 2008 |
Request to interconnect 30MW on the AEPW system |
Impact Study completed May 2008 |
Download |
GEN-2008-008 |
September 10, 2010 |
Limited Operation Impact Study for Generation Interconnection Request |
Posted 4/20/2011 |
Download |
GEN-2008-013 |
February 28, 2012 |
Restudy to Interconnect 299.04 MW to the OGE transmission system |
Restudy Posted 5/24/2012 |
Download |
GEN-2008-013 |
August 25, 2016 |
Impact Restudy for Generator Modification (Turbine Change) |
Posted 9/26/2016 |
Download |
GEN-2008-014 |
September 10, 2010 |
Limited Operation Impact Study for Generation Interconnection Request |
Posted 4/20/2011 |
Download |
GEN-2008-016 |
March 01, 2008 |
Interconnect 248 MW into SWPS (Restudy new turbine) |
Posted 9/14/2010 |
Download |
Gen-2008-016 |
March 01, 2008 |
Interconnect 248 MW into SWPS (Restudy) |
Posted 10/19/2011 |
Download |
GEN-2008-017 |
March 01, 2013 |
Limited Operation Impact Study for Generation Interconnection Request |
Posted 5/13/2013 |
Download |
GEN-2008-018 |
March 19, 2013 |
Impact Restudy for Generator Modification (Turbine Change) |
Posted 6/11/2013 |
Download |
GEN-2008-018 |
July 08, 2011 |
Limited Operation Impact Study for Generation Interconnection Request |
Posted 2/1/2013 |
Download |
GEN-2008-018 |
July 08, 2011 |
Limited Operation Impact Study for Generation Interconnection Request |
Posted 8/23/2011 |
Download |
GEN-2008-018 |
July 08, 2011 |
Revised Limited Operation Impact Study for Generation Interconnection Request |
Posted 9/7/2011 |
Download |
GEN-2008-018 |
June 12, 2013 |
Limited Operation Impact Study for Generation Interconnection Request |
Posted 9/27/2013 |
Download |
GEN-2008-022 |
April 25, 2014 |
Impact Restudy for Generator Modification (Turbine change) |
Posted 7/7/2014 |
Download |
GEN-2008-022 |
April 25, 2014 |
Impact Restudy for Generator Modification (Turbine change) |
Re-Posted 9/2/2014 |
Download |
GEN-2008-023 |
May 20, 2011 |
Interconnect 150MW to the AEP transmission system |
Posted 7/29/2011 |
Download |
GEN-2008-037 |
September 01, 2010 |
Interim Impact Study for 100MW on WFEC transmission system |
Posted 10/19/2010 |
Download |
GEN-2008-038 |
July 15, 2010 |
Restudy of Definitive Interconnection System Impact |
Posted 12/9/2010 |
Download |
GEN-2008-044 |
July 15, 2010 |
Interim Operational Study for 227MW on OKGE transmission system |
Posted 12/30/2010 |
Download |
GEN-2008-047 |
March 03, 2014 |
Impact Restudy for Generator Modification (Turbine change) |
Posted 5/30/2014 |
Download |
GEN-2008-051 |
March 29, 2011 |
Limited Operation Impact Study for Generation Interconnection Request |
Posted 5/24/2011 |
Download |
GEN-2008-051 |
March 01, 2010 |
Limited Operation Impact Study for Generation Interconnection Request |
Posted 1/2/2013 |
Download |
GEN-2008-079 |
April 20, 2011 |
Limited Operation Impact Study for Generation Interconnection Request |
Posted 5/7/2012 |
Download |
GEN-2008-079 |
October 20, 2010 |
Limited Operation Impact Study for Generation Interconnection Request |
Posted 4/20/2011 |
Download |
GEN-2008-079 |
July 29, 2010 |
Interim Impact Study for 100MW on SUNC transmission system |
Posted 10/20/2010 |
Download |
GEN-2008-079 |
November 11, 2020 |
Modification Request Impact Study |
Posted 10/26/2021 |
Download |
GEN-2008-079 |
April 20, 2011 |
Limited Operation Impact Study for Generation Interconnection Request |
Posted 5/5/2014 |
Download |
GEN-2008-086N02 |
July 31, 2009 |
Limited Operation Impact Study for Generation Interconnection Request |
Posted 1/3/2013 |
Download |
GEN-2008-086N02 |
July 31, 2009 |
Limited Operation Impact Study for Generation Interconnection Request |
Posted 2/7/2013 |
Download |
GEN-2008-086N02 and GEN-2014-032 |
February 12, 2021 |
Modification Request Impact Study |
Posted 12/2/2021 |
Download |
GEN-2008-088 |
July 28, 2011 |
Limited Operation Impact ReStudy for Generation Interconnection Request |
Posted 9/7/2011 |
Download |
GEN-2008-088 |
September 10, 2010 |
Limited Operation Impact Study for Generation Interconnection Request |
Posted 4/20/2011 |
Download |
GEN-2008-092 |
February 13, 2015 |
Impact Restudy for Generator Modification (Turbine Change) |
Posted 2/27/2015 |
Download |
GEN-2008-098 |
May 29, 2015 |
Impact Restudy for Generator Modification (Turbine Change) |
Posted 7/13/2015 |
Download |
GEN-2008-098 |
February 27, 2014 |
Impact Restudy for Generator Modification (Turbine change) |
Posted 4/1/2014 |
Download |
GEN-2008-098 |
September 07, 2010 |
Restudy to Interconnect 100.8MW to the WR transmission system |
Restudy Posted 1/27/2012 |
Download |
GEN-2008-098 |
September 27, 2010 |
Second restudy to Interconnect 100.8MW to the WR transmission system |
Posted 4/24/2012 |
Download |
GEN-2008-123N |
July 25, 2013 |
Impact Restudy for Generator Modification (Turbine change) |
Posted 8/19/2013 |
Download |
GEN-2008-123N |
July 25, 2013 |
Impact Restudy for Generator Modification (Turbine change) |
Posted 9/12/2014 |
Download |
GEN-2008-123N |
July 25, 2013 |
Impact Restudy for Generator Modification (Turbine change) |
Posted 5/1/2017 |
Download |
GEN-2008-124 |
November 10, 2010 |
Limited Operation Impact Study for Generation Interconnection Request |
Posted 1/7/2011 |
Download |
ICS-2008-001 |
January 19, 2009 |
Cluster 1 Impact Study |
Posted 7/1/2009 |
Download |
ICS-2008-001-1 |
August 13, 2009 |
Cluster 1 Impact Study (Restudy) |
Posted 1/13/2010 |
Download |
ICS-2008-001-2 |
April 01, 2010 |
Cluster 1 Impact Study (2nd Restudy) |
Posted 5/12/2010 |
Download |
ICS-2008-001-3 |
July 28, 2010 |
Cluster 1 Impact Study (3rd Restudy) |
Posted 8/23/2010 |
Download |
ICS-2008-001-4 |
October 28, 2010 |
Cluster 1 Impact ReStudy |
Posted 12/21/2010 |
Download |
ICS-2008-001-5 |
January 19, 2009 |
Cluster 1 Impact Re-Study |
Posted 1/22/13 |
Download |
ICS-2008-001-6 |
January 19, 2009 |
Cluster 1 Impact Re-Study |
Posted 11/18/2013 |
Download |
Please send your requests to GIStudies@spp.org
If you have any questions, please submit a ticket on RMS.
|