OASIS Apps

- Curtailment Viewer
- DC Tie Viewer
- Price Discounts
- Price Matrix
- Transmission Load Relief

- SPP OASIS Archive Map
    > SPP OASIS Archive Page
    > Market System Status
    > Member Related Postings
    > FERC890 Items

- Studies Postings
 
SPP Logo
 
2007 Impact Studies
The following Generator Interconnection Studies have been requested.

Study Number Date Requested Purpose of Study Remarks Report
Gen-2007-001 January 19, 2007 Request to interconnect 200MW on the SWPS system Impact Study completed December 2007 Download
Gen-2007-002 January 29, 2007 Request to interconnect 160MW on the SWPS system Impact Study completed August 2007 Download
GEN-2007-002 January 29, 2007 Request to interconnect 160MW on the SWPS system Impact ReStudy completed June 2008 Download
Gen-2007-003 January 30, 2007 Request to interconnect 30MW on the SUNC system Impact Study completed May 2008 Download
Gen-2007-004 February 01, 2007 Request to interconnect 150MW on the SWPS system Impact Study completed December 2007 Download
Gen-2007-006 February 14, 2007 Request to interconnect 200MW on the OKGE system Impact Study completed January 2008 Download
Gen-2007-006 February 14, 2007 Request to interconnect 200MW on the OKGE system Addendum to IS completed May 2008 Download
Gen-2007-008 February 23, 2007 Request to interconnect 300MW on the SWPS system Impact Study completed August 2008 Download
Gen-2007-011 March 09, 2007 Request to interconnect 135MW on the SUNC system Impact study completed May 2008 Download
Gen-2007-013 March 23, 2007 Request to interconnect 99MW on the SUNC system Impact study completed August 2008 Download
Gen-2007-015 March 27, 2007 Request to interconnect 135MW on the WERE system Impact study completed June 2008 Download
Gen-2007-017 April 13, 2007 Request to interconnect 100.5 MW on the MIPU System Impact study completed August 2008 Download
Gen-2007-018 April 13, 2007 Request to interconnect 315MW on the MIPU System Impact Study completed April 2008 Download
GEN-2007-021 January 19, 2009 Restudy of Impact Study Restudy posted 12/6/2010 Download
GEN-2007-021 July 20, 2013 Limited Operation Impact Study for Generation Interconnection Request Re-Posted 10/15/2013 Download
GEN-2007-021 July 20, 2013 Limited Operation Impact Study for Generation Interconnection Request Posted 12/4/2013 Download
GEN-2007-021 February 14, 2014 Generator Modification Evaluation (Turbine Change) Posted 3/7/2014 Download
GEN-2007-025 June 15, 2011 Restudy to Interconnect 300MW to the WERE transmission system Restudy Posted 9/22/2011 Download
GEN-2007-025 June 15, 2011 Restudy to Interconnect 300MW to the WERE transmission system Appendices Only Posted 9/22/2011 Download
GEN-2007-040 September 10, 2010 Limited Operation Impact Study for Generation Interconnection Request Posted 4/20/2011 Download
GEN-2007-040 September 10, 2010 Limited Operation Impact ReStudy for Generation Interconnection Request Posted 6/6/2011 Download
GEN-2007-043 April 01, 2010 Interconnect 200MW to the OKGE transmission system Study Completed 5/28/2010 Download
GEN-2007-043 and GEN-2016-131 November 10, 2020 Modification Request Impact Study Posted 11/30/2021 Download
GEN-2007-044 February 14, 2014 Generator Modification Evaluation (Turbine Change) Posted 3/7/2014 Download
GEN-2007-044 January 19, 2009 Restudy of Impact Study Restudy posted 12/6/2010 Download
GEN-2007-046 July 22, 2011 Limited Operation Impact Study for Generation Interconnection Request Posted 8/30/2011 Download
GEN-2007-046 October 17, 2013 Restudy of System Impact Study for turbine change Posted 2/7/2014 Download
GEN-2007-050 October 22, 2007 Request to interconnect 171MW on the OKGE system Interim Operational Impact Study completed September 2009 Download
GEN-2007-052 August 01, 2009 Interconnect 150 MW to the WFEC transmission system Posted 2/1/2010 Download
Gen-2007-052 November 09, 2007 Request to interconnect 150MW on the WFEC system Interim Operational Impact Study completed June 2009 Download
Gen-2007-053 November 19, 2009 Request to interconnect 150MW on the MIPU system Impact Study completed October 2009 Download
GEN-2007-062 August 04, 2016 Generator Modification Evaluation (Turbine Change) Posted 9/29/2016 Download
GEN-2007-062 December 01, 2017 Generator Modification Evaluation (Turbine Change) Posted 12/15/2017 Download

Please send your requests to GIStudies@spp.org

If you have any questions, please submit a ticket on RMS.