Study Number |
Date Requested |
Purpose of Study |
Remarks |
Report |
Gen-2007-001 |
January 19, 2007 |
Request to interconnect 200MW on the SWPS system |
Impact Study completed December 2007 |
Download |
Gen-2007-002 |
January 29, 2007 |
Request to interconnect 160MW on the SWPS system |
Impact Study completed August 2007 |
Download |
GEN-2007-002 |
January 29, 2007 |
Request to interconnect 160MW on the SWPS system |
Impact ReStudy completed June 2008 |
Download |
Gen-2007-003 |
January 30, 2007 |
Request to interconnect 30MW on the SUNC system |
Impact Study completed May 2008 |
Download |
Gen-2007-004 |
February 01, 2007 |
Request to interconnect 150MW on the SWPS system |
Impact Study completed December 2007 |
Download |
Gen-2007-006 |
February 14, 2007 |
Request to interconnect 200MW on the OKGE system |
Impact Study completed January 2008 |
Download |
Gen-2007-006 |
February 14, 2007 |
Request to interconnect 200MW on the OKGE system |
Addendum to IS completed May 2008 |
Download |
Gen-2007-008 |
February 23, 2007 |
Request to interconnect 300MW on the SWPS system |
Impact Study completed August 2008 |
Download |
Gen-2007-011 |
March 09, 2007 |
Request to interconnect 135MW on the SUNC system |
Impact study completed May 2008 |
Download |
Gen-2007-013 |
March 23, 2007 |
Request to interconnect 99MW on the SUNC system |
Impact study completed August 2008 |
Download |
Gen-2007-015 |
March 27, 2007 |
Request to interconnect 135MW on the WERE system |
Impact study completed June 2008 |
Download |
Gen-2007-017 |
April 13, 2007 |
Request to interconnect 100.5 MW on the MIPU System |
Impact study completed August 2008 |
Download |
Gen-2007-018 |
April 13, 2007 |
Request to interconnect 315MW on the MIPU System |
Impact Study completed April 2008 |
Download |
GEN-2007-021 |
January 19, 2009 |
Restudy of Impact Study |
Restudy posted 12/6/2010 |
Download |
GEN-2007-021 |
July 20, 2013 |
Limited Operation Impact Study for Generation Interconnection Request |
Re-Posted 10/15/2013 |
Download |
GEN-2007-021 |
July 20, 2013 |
Limited Operation Impact Study for Generation Interconnection Request |
Posted 12/4/2013 |
Download |
GEN-2007-021 |
February 14, 2014 |
Generator Modification Evaluation (Turbine Change) |
Posted 3/7/2014 |
Download |
GEN-2007-025 |
June 15, 2011 |
Restudy to Interconnect 300MW to the WERE transmission system |
Restudy Posted 9/22/2011 |
Download |
GEN-2007-025 |
June 15, 2011 |
Restudy to Interconnect 300MW to the WERE transmission system |
Appendices Only Posted 9/22/2011 |
Download |
GEN-2007-040 |
September 10, 2010 |
Limited Operation Impact Study for Generation Interconnection Request |
Posted 4/20/2011 |
Download |
GEN-2007-040 |
September 10, 2010 |
Limited Operation Impact ReStudy for Generation Interconnection Request |
Posted 6/6/2011 |
Download |
GEN-2007-043 |
April 01, 2010 |
Interconnect 200MW to the OKGE transmission system |
Study Completed 5/28/2010 |
Download |
GEN-2007-043 and GEN-2016-131 |
November 10, 2020 |
Modification Request Impact Study |
Posted 11/30/2021 |
Download |
GEN-2007-044 |
February 14, 2014 |
Generator Modification Evaluation (Turbine Change) |
Posted 3/7/2014 |
Download |
GEN-2007-044 |
January 19, 2009 |
Restudy of Impact Study |
Restudy posted 12/6/2010 |
Download |
GEN-2007-046 |
July 22, 2011 |
Limited Operation Impact Study for Generation Interconnection Request |
Posted 8/30/2011 |
Download |
GEN-2007-046 |
October 17, 2013 |
Restudy of System Impact Study for turbine change |
Posted 2/7/2014 |
Download |
GEN-2007-050 |
October 22, 2007 |
Request to interconnect 171MW on the OKGE system |
Interim Operational Impact Study completed September 2009 |
Download |
GEN-2007-052 |
August 01, 2009 |
Interconnect 150 MW to the WFEC transmission system |
Posted 2/1/2010 |
Download |
Gen-2007-052 |
November 09, 2007 |
Request to interconnect 150MW on the WFEC system |
Interim Operational Impact Study completed June 2009 |
Download |
Gen-2007-053 |
November 19, 2009 |
Request to interconnect 150MW on the MIPU system |
Impact Study completed October 2009 |
Download |
GEN-2007-062 |
August 04, 2016 |
Generator Modification Evaluation (Turbine Change) |
Posted 9/29/2016 |
Download |
GEN-2007-062 |
December 01, 2017 |
Generator Modification Evaluation (Turbine Change) |
Posted 12/15/2017 |
Download |
Please send your requests to GIStudies@spp.org
If you have any questions, please submit a ticket on RMS.
|