2006 Impact Studies
The following Generator Interconnection Studies have been requested.

Study Number Date Requested Purpose of Study Remarks Report
Gen-2006-002 January 09, 2006 Request to interconnect 150MW on the AEPW System Impact Study Completed December 2006 Download
GEN-2006-002 August 25, 2010 Interconnect 101 MW to AEPW transmission system Study Posted 9/29/2010 Download
Gen-2006-003 February 07, 2006 Request to interconnect 50MW on the MIPU System (Reduced to 30MW) Impact Study completed January 2007 Download
Gen-2006-006 February 16, 2006 Request to interconnect 205.5MW on the WPEK system Impact Study completed February 2008 Download
Gen-2006-008 February 27, 2006 Request to interconnect 550MW on the AEPW system Impact Study completed December 2006 Download
Gen-2006-010 February 27, 2006 Request to interconnect 620MW on the AEPW System Impact Study completed January 2007 Download
Gen-2006-010 February 27, 2006 Request to interconnect 620 MW on the AEPW system Impact Study reposted on January 25, 2007 Download
Gen-2006-014 March 02, 2006 Request to interconnect 300MW on the MIPU System Impact Study completed February 2007 Download
Gen-2006-014 March 02, 2006 Request to interconnect 300MW on the MIPU system Impact Re-Study completed January 2008 Download
Gen-2006-015 April 24, 2006 Request to interconnect 170MW on the SWPS system Expedited Impact Study completed June 2006 Download
Gen-2006-017 June 02, 2006 Request to interconnect 300 MW on the MIPU system Impact Study completed May 2007 Download
Gen-2006-017 June 02, 2006 Request to interconnect 300MW on the MIPU system Impact Re-Study completed January 2008 Download
Gen-2006-018 June 14, 2006 Request to interconnect 170MW on the SWPS system Impact Study completed December 2006 Download
GEN-2006-018 June 14, 2006 Interconnect 170MW on the SWPS transmission system Impact Restudy reposted 3/24/2010 Download
Gen-2006-019 June 19, 2006 Request to interconnect 275MW on the SPRM system Impact study posted February 2007 Download
Gen-2006-020S June 20, 2006 Request to interconnect 18.9MW on the SW PS System Impact Study posted January 17, 2007 Download
Gen-2006-020S June 20, 2006 Request to interconnect 18.9 MW on the SWPS system Impact Re-Study completed November 2007 Download
GEN-2006-020S October 01, 2010 Interconnect 20MW on the SWPS transmission system Posted 12/8/2010 Download
Gen-2006-020S June 20, 2006 Request to interconnect 18.9MW on the SWPS system Impact Re-Study completed May 2009 Download
GEN-2006-021 December 15, 2017 Generator Modification Evaluation (Turbine Change) Posted 1/31/2018 Download
Gen-2006-021 June 21, 2007 Request to interconnect 250MW on the WPEK system Impact Study completed June 2007 Download
Gen-2006-021 (Re-Study) June 21, 2006 Request to interconnect 250MW on the WPEK system Re-Study posted October 2007 Download
Gen-2006-022 June 21, 2007 Request to interconnect 150MW on the WPEK system Impact Study completed August 2007 Download
Gen-2006-024S July 07, 2006 Request to interconnect 19.8MW on the WFEC system Impact Study completed February 2007 Download
Gen-2006-025 July 07, 2006 Request to interconnect 150MW on the SWPS system Impact Study completed July 2007 Download
Gen-2006-026 July 26, 2006 Request to interconnect 502MW on the SWPS System Impact Study completed November 2006 Download
Gen-2006-027 August 11, 2006 Request to interconnect 320MW on the WERE system Impact Study completed February 2006 Download
Gen-2006-028 August 11, 2006 Request to interconnect 300MW on the WERE system Impact Study completed April 2007 Download
Gen-2006-031 August 16, 2006 Request to interconnect 75MW on the MIDW system Impact Study completed April 2007 Download
Gen-2006-032 August 21, 2006 Request to interconnect 210 MW on the MIDW system Impact Study completed April 2007 Download
GEN-2006-032 August 21, 2006 Request to interconnect 210MW on the MIDW system Re-Study completed January 2008 Download
Gen-2006-033 August 22, 2006 Request to interconnect 150MW on the WERE system Impact Study completed June 2007 Download
Gen-2006-034 August 23, 2006 Request to interconnect 81MW on the SUNC system Impact Study completed June 2007 Download
Gen-2006-035 August 29, 2006 Request to interconnect 225MW on the AEPW system Impact Study completed July 2007 Download
Gen-2006-035 August 29, 2006 Request to interconnect 225MW on the AEPW system Impact Re-Study completed May 2008 Download
Gen-2006-037 September 15, 2006 Request to interconnect 900 MW on the OKGE system Impact Study completed April 2007 Download
GEN-2006-037N1 April 15, 2011 Restudy to Interconnect 75MW to the NPPD transmission system Posted 7/25/2011 Download
GEN-2006-037N1 September 30, 2009 Generator Modification Evaluation (Turbine Change) Posted 2/3/2014 Download
Gen-2006-038 October 16, 2006 Request to interconnect 750MW on the WFEC system Impact Study completed September 2007 Download
Gen-2006-039 October 30, 2006 Request to interconnect 400MW on the SWPS system Impact Study completed August 2007 Download
Gen-2006-040 November 07, 2006 Request to interconnect 108MW on the SUNC system Impact Study posted October 2007 Download
Gen-2006-040 November 07, 2006 Request to interconnect 108 MW on the SUNC System Impact Re-Study completed November 2008 Download
Gen-2006-043 November 17, 2006 Request to interconnect 126MW on the AEPW system Impact Re-Study completed March 2009 Download
Gen-2006-043 November 17, 2007 Request to interconnect 300MW on the AEPW system Impact Study completed October 2007 Download
Gen-2006-044 December 04, 2006 Request to interconnect 400MW on the SWPS system Impact Study completed February 2008 Download
Gen-2006-044 December 04, 2006 Request to interconnect 400MW on the SWPS System Impact Re-Study completed August 2008 Download
GEN-2006-044 October 15, 2010 Interconnect 370MW on the SPS transmission system Study posted 2-23/2012 Download
GEN-2006-044 October 29, 2010 Interconnect 370MW on the SWPS transmission system Restudy posted 12/16/2010 Download
GEN-2006-044 March 16, 2022 Modification Request Impact Study Posted 08/15/2022 Download
GEN-2006-044N August 09, 2010 Request to interconnect 40.5MW on the NPPD system Interim Impact Study posted August 2010 Download
GEN-2006-044N02 November 22, 2010 Restudy to Interconnect 99.2MW to the NPPD transmission system Posted 2/23/2011 Download
GEN-2006-045 December 05, 2006 Request to Interconnect 240MW on the SWPS system using different wind turbine technology Restudy posted 9/22/2011 Download
Gen-2006-045 December 05, 2006 Request to interconnect 240MW on the SWPS system Impact Study completed October 2007 Download
Gen-2006-046 December 05, 2006 Request to interconnect 130MW on the OKGE system Impact Study completed November 2007 Download
GEN-2006-046 September 01, 2010 Interconnect 130MW to the OKGE transmission system Posted 10/13/2010 Download
Gen-2006-046 December 05, 2006 Request to interconnect 130.2MW on the OKGE system Impact Re-Study #2 completed August 2008 Download
Gen-2006-046 December 05, 2006 Request to interconnect 130MW on the OKGE system Impact Re-Study completed April 2008 Download
GEN-2006-047 June 11, 2013 Limited Operation Impact Study for Generation Interconnection Request Posted 10/4/2013 Download
Gen-2006-047 December 05, 2006 Request to interconnect 240MW on the SWPS system Impact Study completed January 2008 Download
Gen-2006-048 December 08, 2006 Request to interconnect 150MW on the SW PS system Impact Study completed December 2007 Download
Gen-2006-049 December 18, 2006 Request to interconnect 400MW on the SWPS system Impact Study completed May 2008 Download
Gen-2006-049 December 18, 2006 Request to interconnect 400MW on the SWPS system Impact Re-Study completed April 2009 Download
GEN-2006-049 October 24, 2008 Interconnect 400MW to the SPS transmission system Posted 2/27/2012 Download