| 2018 Affected Systems | |
| The following Generator Interconnection Studies have been requested. | |
| Study Number | Date Requested | Purpose of Study | Remarks | Report |
|---|---|---|---|---|
| AECI AFS DISIS 2018-002/2019-001 Phase II v0 | March 31, 2018 | Affected System Impact Study DISIS 2018-002/2019-001 Phase II | Posted 10/24/2023 | Download |
| AECI AFS of DISIS 2018-002/2019-001 Phase II v1 | March 31, 2018 | Affected System Impact Study DISIS 2018-002/2019-001 Phase II v1 | Posted 7/18/2025 | Download |
| ASGI-2018-001 | November 01, 2018 | Network Upgrade Facility Study for ASGI-2018-001 | Posted 08/15/2022 | Download |
| ASGI-2018-001 | February 02, 2018 | Affected System Impact Study | Posted 3/25/2021 | Download |
| ASGI-2018-001 | February 02, 2018 | Limited Operation Impact Study Report of Affected System ASGI-2018-001 | Reposted 8/7/2019 | Download |
| ASGI-2018-001 | February 02, 2018 | Affected System Impact Restudy | Posted 05/12/2022 | Download |
| DISIS-2018-001 | February 02, 2018 | AECI Affected System Impact Results v0 | Posted 07/18/2023 | Download |
| DISIS-2018-001 | February 02, 2018 | AECI Affected System Impact Results v1 | Posted 07/18/2024 | Download |
| DISIS-2018-001 | February 02, 2018 | AECI Affected System Impact Results v2 | Posted 02/19/2025 | Download |
| DISIS-2018-001 | February 02, 2018 | AECI Affected System Impact Results v3 | Posted 12/02/2025 | Download |
| MISO AFS DISIS 2018-002/2019-001 Phase II Final | March 31, 2018 | Affected System Impact Study DISIS 2018-002/2019-001 Phase II | Re-Posted 09/11/2023 | Download |
| MISO AFS DISIS 2018-002/2019-001 Phase III | March 31, 2018 | Affected System Impact Study DISIS 2018-002/2019-001 Phase III Final | Posted 03/22/2024 | Download |
| MISO AFS DISIS-2018-002/2019-001 Phase III | March 31, 2018 | Affected System Impact Study DISIS 2018-002/2019-001 Phase III Draft | Posted 03/01/2024 | Download |
| MISO AFS of DISIS 2018-001 Phase III | February 02, 2018 | Affected System Impact Study of DISIS 2018-001 Phase III | Posted 09/15/2023 | Download |
| MISO AFS of DISIS-2018-001 Phase II | February 02, 2018 | Affected System Impact Study of DISIS-2018-001 Phase II | Posted 03/13/2023 | Download |
| MISO AFS of DISIS-2018-001 Restudy 2 | February 02, 2018 | Affected System Impact Restudy 2 of DISIS-2018-001 Phase II Final | Reposted 1/16/2026 | Download |
| MPC AFS of DISIS-2018-001 Phase II | February 02, 2018 | Affected System Impact Study of DISIS-2018 Phase II | Re-Posted 02/05/2023 | Download |
| MPC03600-03700 | April 25, 2019 | SPP Affected System Impact Study for MPC 03600-03700 Restudy Final | Posted 07/22/2025 | Download |
|
Please send your requests to GIStudies@spp.org If you have any questions, please submit a ticket on RMS. |
||||