GEN-2002-006 |
April 30, 2002 |
Request to interconnect up to 150MW on the SWPS system. |
Facility Study completed February 2004 |
Download |
GEN-2002-008 |
July 19, 2002 |
Request to interconnect up to 240 MW on the SWPS system |
Facility Study complete Sept. 16, 2004 |
Download |
GEN-2002-008 |
July 19, 2002 |
Request to interconnect up to 240 MW on the SWPS system |
Addendum to Facility Study GEN-2002-008 |
Download |
GEN-2002-008 |
July 19, 2002 |
Request to interconnect up to 240 MW on the SWPS system |
Final Facility Study Completed 4/6/2005 |
Download |
GEN-2002-008 |
July 19, 2002 |
Request to interconnect up to 240 MW to the SWPS system |
Posted 11/17/2021 |
Download |
GEN-2002-009 |
July 19, 2002 |
Request to interconnect up to 80MW on the SWPS system |
Facility Study completed 8/3/2004 |
Download |
GEN-2002-019 |
September 12, 2002 |
Request to interconnect up to 160 MW on the SWPS system |
Facility Study Completed February 2005 |
Download |
Gen-2002-022 |
September 12, 2002 |
Request to interconnect 240 MW on the SPWS System |
Facility Study completed October 2005 |
Download |
Gen-2002-025A |
October 31, 2002 |
Request to interconnect 150 MW on the WPL System |
Facility Study completed November 2005 |
Download |
GEN-2002-026 |
November 13, 2002 |
Request to interconnect up to 140 MW on the WERE system.(Reduced by Customer to 121 MW) |
Facility Study completed November 2003 |
Download |