2002 Facility Studies
The following Generator Interconnection Studies have been requested.

Study Number Date Requested Purpose of Study Remarks Report
GEN-2002-006 April 30, 2002 Request to interconnect up to 150MW on the SWPS system. Facility Study completed February 2004 Download
GEN-2002-008 July 19, 2002 Request to interconnect up to 240 MW on the SWPS system Facility Study complete Sept. 16, 2004 Download
GEN-2002-008 July 19, 2002 Request to interconnect up to 240 MW on the SWPS system Addendum to Facility Study GEN-2002-008 Download
GEN-2002-008 July 19, 2002 Request to interconnect up to 240 MW on the SWPS system Final Facility Study Completed 4/6/2005 Download
GEN-2002-008 July 19, 2002 Request to interconnect up to 240 MW to the SWPS system Posted 11/17/2021 Download
GEN-2002-009 July 19, 2002 Request to interconnect up to 80MW on the SWPS system Facility Study completed 8/3/2004 Download
GEN-2002-019 September 12, 2002 Request to interconnect up to 160 MW on the SWPS system Facility Study Completed February 2005 Download
Gen-2002-022 September 12, 2002 Request to interconnect 240 MW on the SPWS System Facility Study completed October 2005 Download
Gen-2002-025A October 31, 2002 Request to interconnect 150 MW on the WPL System Facility Study completed November 2005 Download
GEN-2002-026 November 13, 2002 Request to interconnect up to 140 MW on the WERE system.(Reduced by Customer to 121 MW) Facility Study completed November 2003 Download