2022 Facility Studies
The following Generator Interconnection Studies have been requested.

Study Number Date Requested Purpose of Study Remarks Report
GEN-2022-009 Interim April 16, 2024 Interconnect 125 MW to the BEPC Transmission System Posted 5/31/2024 Download
GEN-2022-010 Interim April 16, 2024 Interconnect 250 MW to the BEPC Transmission System Posted 5/31/2024 Download
GEN-2022-083 Interim April 16, 2024 Interconnect 250 MW to the BEPC Transmission System Posted 6/6/2024 Download
GEN-2022-147 Interim November 15, 2023 Interconnect 203 MW to the SPS Transmission System Posted 02/15/2024 Download
GEN-2022-GR1 April 27, 2023 Generator Replacement Facility Study Report for Pirkey 138 kV Posted 08/01/2023 Download