2021 Affected Systems
The following Generator Interconnection Studies have been requested.

Study Number Date Requested Purpose of Study Remarks Report
CIPCO IR24 & IR32 December 02, 2019 Affected System Impact Study Posted 4/15/2021 Download
DISIS-2021-001 April 30, 2021 AECI Affected System Impact Results v0 Posted 07/19/2024 Download
DISIS-2021-001 April 20, 2021 MISO Affected System Impact Results Re-Posted 08/09/2024 Download
DISIS-2021-001 April 30, 2021 MPC Affected System Impact Study Posted 09/24/2024 Download
FINAL SPP Affected System Impact Study for AECI Group 8, 12, and 13 May 24, 2018 FINAL SPP Affected System Impact Study for AECI Group 8, 12, and 13 Posted 05/11/2022 Download