- Studies Postings
|
|
|
|
2020 Facility Studies |
The following Generator Interconnection Studies have been requested.
|
Study Number |
Date Requested |
Purpose of Study |
Remarks |
Report |
GEN-2020-002 Interim |
April 07, 2021 |
Interconnect 81 MW to the OPPD Transmission System |
Posted 11/02/2021 |
Download |
GEN-2020-014 Interim |
February 17, 2021 |
Interconnect 45 MW to the BEPC Transmission System |
Posted 11/02/21 |
Download |
GEN-2020-025 Interim |
July 21, 2022 |
Interconnect 255 MW to the OPPD Transmission System |
Posted 09/07/2022 |
Download |
GEN-2020-028 Interim |
July 21, 2022 |
Interconnect 255 MW to the OPPD Transmission System |
Posted 09/07/2022 |
Download |
GEN-2020-043 Interim |
July 21, 2022 |
Interconnect 56.52 MW to the OPPD Transmission System |
Posted 09/07/2022 |
Download |
GEN-2020-044 Interim |
July 21, 2022 |
Interconnect 56.52 MW to the OPPD Transmission System |
Posted 09/07/2022 |
Download |
GEN-2020-045 Interim |
July 21, 2022 |
Interconnect 56.52 MW to the OPPD Transmission System |
Posted 09/07/2022 |
Download |
GEN-2020-056 Interim |
February 19, 2021 |
Interconnect 20 MW to the SUNC Transmission System |
Posted 03/29/2022 |
Download |
GEN-2020-071 Interim |
August 29, 2023 |
Interconnect 252 MW to the WERE Transmission System |
Posted 10/09/2023 |
Download |
GEN-2020-078 Interim |
July 27, 2020 |
Interconnect 100 MW to the OPPD Transmission System |
Posted 12/14/21 |
Download |