| 2020 Facility Studies | |
| The following Generator Interconnection Studies have been requested. | |
| Study Number | Date Requested | Purpose of Study | Remarks | Report |
|---|---|---|---|---|
| GEN-2020-002 | March 20, 2025 | Interconnect 81 MW to the OPPD Transmission System FINAL | Posted 5/27/2025 | Download |
| GEN-2020-002 Interim | April 07, 2021 | Interconnect 81 MW to the OPPD Transmission System | Posted 11/02/2021 | Download |
| GEN-2020-003 | March 20, 2025 | Interconnect 58 MW to the KPP Transmission System FINAL | Posted 6/20/2025 | Download |
| GEN-2020-007 | March 20, 2025 | Interconnect 650 MW to the Evergy Transmission System FINAL | Posted 5/22/2025 | Download |
| GEN-2020-008 | March 20, 2025 | Interconnect 250 MW to the SPS Transmission System FINAL | Posted 6/9/2025 | Download |
| GEN-2020-010 | March 20, 2025 | Interconnect 140 MW to the WFEC Transmission System FINAL | Posted 5/29/2025 | Download |
| GEN-2020-011 | March 20, 2025 | Interconnect 320 MW to the NPPD Transmission System FINAL | Posted 12/9/2025 | Download |
| GEN-2020-012 | March 20, 2025 | Interconnect 113 MW to the AEP Transmission System FINAL | Posted 10/24/2025 | Download |
| GEN-2020-013 | March 20, 2025 | Interconnect 215 MW to the NPPD Transmission System FINAL | Posted 12/9/2025 | Download |
| GEN-2020-014 | March 20, 2025 | Interconnect 45 MW to the BEPC Transmission System FINAL | Posted 5/29/2025 | Download |
| GEN-2020-014 Interim | February 17, 2021 | Interconnect 45 MW to the BEPC Transmission System | Posted 11/02/21 | Download |
| GEN-2020-020 | March 20, 2025 | Interconnect 201.6 MW to the AEP Transmission System FINAL | Posted 10/24/2025 | Download |
| GEN-2020-021 | March 20, 2025 | Interconnect 235 MW to the BEPC Transmission System FINAL | Posted 6/23/2025 | Download |
| GEN-2020-025 | March 20, 2025 | Interconnect 255 MW to the OPPD Transmission System FINAL | Posted 5/23/2025 | Download |
| GEN-2020-025 Interim | July 21, 2022 | Interconnect 255 MW to the OPPD Transmission System | Posted 09/07/2022 | Download |
| GEN-2020-028 | March 20, 2025 | Interconnect 255 MW to the OPPD Transmission System FINAL | Posted 5/23/2025 | Download |
| GEN-2020-028 Interim | July 21, 2022 | Interconnect 255 MW to the OPPD Transmission System | Posted 09/07/2022 | Download |
| GEN-2020-031 | March 20, 2025 | Interconnect 272.7 MW to the OPPD Transmission System FINAL | Posted 5/23/2025 | Download |
| GEN-2020-038 | March 20, 2025 | Interconnect 272.7 MW to the OPPD Transmission System FINAL | Posted 5/23/2025 | Download |
| GEN-2020-043 | March 20, 2025 | Interconnect 56.52 MW to the OPPD Transmission System FINAL | Posted 5/27/2025 | Download |
| GEN-2020-043 Interim | July 21, 2022 | Interconnect 56.52 MW to the OPPD Transmission System | Posted 09/07/2022 | Download |
| GEN-2020-044 | March 20, 2025 | Interconnect 56.52 MW to the OPPD Transmission System FINAL | Posted 5/27/2025 | Download |
| GEN-2020-044 Interim | July 21, 2022 | Interconnect 56.52 MW to the OPPD Transmission System | Posted 09/07/2022 | Download |
| GEN-2020-045 | March 20, 2025 | Interconnect 56.52 MW to the OPPD Transmission System FINAL | Posted 5/27/2025 | Download |
| GEN-2020-045 Interim | July 21, 2022 | Interconnect 56.52 MW to the OPPD Transmission System | Posted 09/07/2022 | Download |
| GEN-2020-054 | March 20, 2025 | Interconnect 298 MW to the AEP Transmission System FINAL | Reposted 8/27/2025 | Download |
| GEN-2020-056 | March 20, 2025 | Interconnect 20 MW to the SUNC Transmission System FINAL | Posted 6/5/2025 | Download |
| GEN-2020-056 Interim | February 19, 2021 | Interconnect 20 MW to the SUNC Transmission System | Posted 03/29/2022 | Download |
| GEN-2020-057 | March 20, 2025 | Interconnect 424.5 MW to the Evergy Transmission System FINAL | Posted 5/22/2025 | Download |
| GEN-2020-058 | March 20, 2025 | Interconnect 424.5 MW to the Evergy Transmission System FINAL | Posted 5/22/2025 | Download |
| GEN-2020-060 | March 20, 2025 | Interconnect 200 MW to the SPS Transmission System FINAL | Posted 9/9/2025 | Download |
| GEN-2020-061 | March 20, 2025 | Interconnect 29 MW to the Evergy Transmission System FINAL | Posted 5/22/2025 | Download |
| GEN-2020-064 | March 20, 2025 | Interconnect 64 MW to the EDE Transmission System FINAL | Posted 6/5/2025 | Download |
| GEN-2020-065 | March 20, 2025 | Interconnect 1003 MW to the SPS Transmission System FINAL | Posted 8/21/2025 | Download |
| GEN-2020-067 | March 20, 2025 | Interconnect 352.5 MW to the SPS Transmission System FINAL | Posted 8/21/2025 | Download |
| GEN-2020-068 | March 20, 2025 | Interconnect 400 MW to the SPS Transmission System FINAL | Posted 8/21/2025 | Download |
| GEN-2020-069 | March 20, 2025 | Interconnect 52.85 MW to the NPPD Transmission System FINAL | Posted 12/9/2025 | Download |
| GEN-2020-071 Interim | August 29, 2023 | Interconnect 252 MW to the WERE Transmission System | Posted 10/09/2023 | Download |
| GEN-2020-072 | March 20, 2025 | Interconnect 150 MW to the Evergy Transmission System FINAL | Posted 5/22/2025 | Download |
| GEN-2020-073 | March 20, 2025 | Interconnect 150 MW to the Evergy Transmission System FINAL | Posted 5/22/2025 | Download |
| GEN-2020-074 | March 20, 2025 | Interconnect 200 MW to the AEP Transmission System FINAL | Posted 8/28/2025 | Download |
| GEN-2020-078 | March 20, 2025 | Interconnect 100 MW to the OPPD Transmission System FINAL | Posted 5/28/2025 | Download |
| GEN-2020-078 Interim | July 27, 2020 | Interconnect 100 MW to the OPPD Transmission System | Posted 12/14/21 | Download |
| GEN-2020-079 | March 20, 2025 | Interconnect 225 MW to the EDE Transmission System FINAL | Posted 6/4/2025 | Download |
| GEN-2020-081 | March 20, 2025 | Interconnect 200 MW to the AEP Transmission System FINAL | Posted 9/23/2025 | Download |
| GEN-2020-083 | March 20, 2025 | Interconnect 74.5 MW to the WAPA Transmission System FINAL | Posted 6/4/2025 | Download |
| GEN-2020-084 | March 20, 2025 | Interconnect 350 MW to the OPPD Transmission System FINAL | Posted 5/28/2025 | Download |
| GEN-2020-085 | March 20, 2025 | Interconnect 500 MW to the AEP Transmission System FINAL | Posted 8/28/2025 | Download |
| GEN-2020-087 | March 20, 2025 | Interconnect 500 MW to the AEP Transmission System FINAL | Posted 10/24/2025 | Download |
| GEN-2020-088 | March 20, 2025 | Interconnect 150 MW to the EDE Transmission System FINAL | Posted 6/4/2025 | Download |
| GEN-2020-090 | March 20, 2025 | Interconnect 204.3 MW to the NEET Transmission System FINAL | Posted 6/16/2025 | Download |
| GEN-2020-091 | March 20, 2025 | Interconnect 150 MW to the BEPC Transmission System FINAL | Posted 6/16/2025 | Download |
| GEN-2020-092 | March 20, 2025 | Interconnect 100 MW to the AEP Transmission System FINAL | Posted 10/24/2025 | Download |
| GEN-2020-094 | March 20, 2025 | Interconnect 250 MW to the OPPD Transmission System FINAL | Posted 5/28/2025 | Download |
|