| 2000 Impact Studies | |
| The following Generator Interconnection Studies have been requested. | |
| Study Number | Date Requested | Purpose of Study | Remarks | Report |
|---|---|---|---|---|
| GEN-2000-007 | September 25, 2000 | Request to interconnect 550MW on the AEP West transmission system | Withdrawn (Completed Impact Study March 2001) | Download |
| GEN-2000-008 | September 25, 2000 | Request to interconnect 550MW on the KCPL transmission system | Completed Impact Study March 2001 | Download |
| GEN-2000-015 | December 20, 2000 | Request to interconnect 180VW on the Western Farmers transmission system | Impact Study completed August 2001 | Download |
|
Please send your requests to GIStudies@spp.org If you have any questions, please submit a ticket on RMS. |
||||