2019 Impact Studies
The following Generator Interconnection Studies have been requested.

Study Number Date Requested Purpose of Study Remarks Report
DISIS-2018-002/DISIS-2019-001 March 31, 2018 DISIS-2018-002/DISIS-2019-001 Phase 1 Powerflow and Short Circuit Final Report Reposted 11/16/2022 Download
DISIS-2018-002/DISIS-2019-001 March 31, 2018 DISIS-2018-002/DISIS-2019-001 Phase 2 Powerflow and Short Circuit Final Report Reposted 09/22/2023 Download
GEN-2019-001 November 27, 2018 Interim Availability Impact Study for Generation Interconnection Request Posted 12/21/2018 Download
GEN-2019-018 December 03, 2019 Interim Availability Impact Study for Generation Interconnection Request Posted 3/10/2021 Download
Group 15 Interim Operation Report December 03, 2019 Group 15 Interim Operation Posted 7/20/2021 Download

Please send your requests to GIStudies@spp.org