2018 Feasibility Studies
The following Generator Interconnection Studies have been requested.

Study Number Date Requested Purpose of Study Remarks Report
FCS-2018-001 February 28, 2018 Feasibility Cluster Study Posted 5/29/2018 Download
FCS-2018-002 May 29, 2018 Feasibility Cluster Study Posted 8/27/2018 Download
FCS-2018-003 August 27, 2018 Feasibility Cluster Study No requests were entered in this queue cluster Download
FCS-2018-004 November 25, 2018 Feasibility Cluster Study Posted 3/5/2019 Download