OASIS Apps

- Curtailment Viewer
- DC Tie Viewer
- Price Discounts
- Price Matrix
- Transmission Load Relief

- SPP OASIS Archive Map
    > SPP OASIS Archive Page
    > Market System Status
    > Member Related Postings
    > FERC890 Items

- Studies Postings
 
SPP Logo
 
2016 Feasibility Studies
The following Generator Interconnection Studies have been requested.

Study Number Date Requested Purpose of Study Remarks Report
FCS-2016-001 December 31, 2015 Feasibility Cluster Study Posted 3/16/2016 Download
FCS-2016-002 March 31, 2016 Feasibility Cluster Study Posted 6/30/2016 Download
FCS-2016-003 June 30, 2016 Feasibility Cluster Study Posted 10/31/2016 Download
FCS-2016-004 November 30, 2016 Feasibility Cluster Study Re-posted 7/11/2017 Download

Please send your requests to GIStudies@spp.org

If you have any questions, please submit a ticket on RMS.