RAPID CITY NON-DC TIE INJECTION POINT - History Log
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 3/23/2023 3:14:25 PM (CD) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 as a result of a planned maintenance outage from 3/23/2023 3:00:00 PM (CD) to 3/28/2023 12:00:00 AM (CD). |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 3/7/2023 5:23:28 PM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 3/2/2023 5:53:44 PM (CS) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 as a result of an unplanned maintenance outage from 3/2/2023 6:00:00 PM (CS) to 3/10/2023 6:00:00 PM (CS). |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 3/1/2023 5:22:47 PM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 2/23/2023 8:23:37 AM (CS) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie from west to east will be limited to 150 as a result of a planned maintenance outage from 2/20/2023 8:00:00 AM (CS) to 3/2/2023 5:00:00 PM (CS). |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 2/23/2023 8:23:16 AM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 2/23/2023 8:21:51 AM (CS) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie from west to east will be limited to 150 as a result of a planned maintenance outage from 2/20/2023 8:00:00 AM (CS) to 3/2/2023 5:00:00 PM (CS). |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 2/6/2023 2:49:00 PM (CS) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie from west to east will be limited to 150 as a result of a planned maintenance outage from 2/20/2023 8:00:00 AM (CS) to 2/23/2023 5:00:00 PM (CS). |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 2/6/2023 2:49:41 PM (CS) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 as a result of an emergency outage from 2/20/2023 8:00:00 AM (CS) to 2/23/2023 5:00:00 PM (CS). |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 2/2/2023 5:53:48 AM (CS) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie from west to east will be limited to 150 as a result of a planned maintenance outage from 2/13/2023 8:00:00 AM (CS) to 2/16/2023 5:00:00 PM (CS). |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 2/2/2023 5:51:58 AM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 2/1/2023 1:59:20 PM (CS) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie from west to east will be limited to 150 as a result of a planned maintenance outage from 2/13/2023 8:00:00 AM (CS) to 2/16/2023 5:00:00 PM (CS). |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 1/31/2023 8:21:45 AM (CS) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie from west to east will be limited to 150 as a result of a planned maintenance outage from 2/6/2023 8:00:00 AM (CS) to 2/9/2023 5:00:00 PM (CS). |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 12/28/2022 10:46:25 AM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 12/25/2022 8:18:52 PM (CS) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 as a result of an unplanned maintenance outage from 12/25/2022 8:00:00 PM (CS) to 12/26/2022 6:00:00 PM (CS). |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 12/25/2022 7:45:12 PM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 12/25/2022 6:06:12 PM (CS) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 as a result of an unplanned maintenance outage from 12/25/2022 6:00:00 PM (CS) to 12/26/2022 1:00:00 AM (CS). |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 12/15/2022 5:01:43 PM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 12/15/2022 11:27:48 AM (CS) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie from west to east will be limited to 150 as a result of a planned maintenance outage from 12/15/2022 3:57:00 AM (CS) to 12/16/2022 2:00:00 PM (CS). |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 12/15/2022 3:57:03 AM (CS) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie from west to east will be limited to 150 as a result of a planned maintenance outage from 12/15/2022 4:00:00 AM (CS) to 12/15/2022 11:00:00 AM (CS). |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 12/15/2022 3:56:50 AM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 12/15/2022 3:54:52 AM (CS) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie from west to east will be limited to 150 as a result of a planned maintenance outage from 12/15/2022 4:00:00 AM (CS) to 12/15/2022 11:00:00 AM (CS). |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 12/12/2022 8:57:00 PM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 12/9/2022 8:17:05 PM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 12/9/2022 7:50:20 PM (CS) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 as a result of a planned maintenance outage from 12/9/2022 4:17:00 PM (CS) to 12/10/2022 4:00:00 PM (CS). |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 12/9/2022 7:50:20 PM (CS) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 as a result of a planned maintenance outage from 12/9/2022 4:17:00 PM (CS) to 12/10/2022 4:00:00 PM (CS). |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 12/9/2022 4:17:35 PM (CS) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie from north to south will be limited to 0 as a result of a planned maintenance outage from 12/9/2022 3:43:00 PM (CS) to 12/10/2022 4:00:00 PM (CS). |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 12/9/2022 3:13:43 PM (CS) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 as a result of an unplanned maintenance outage from 12/9/2022 3:00:00 PM (CS) to 12/9/2022 9:00:00 PM (CS). |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
OUTAGE UPDATE Updated at 11/11/2022 4:32:12 AM (CS) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 as a result of a planned maintenance outage from 10/10/2022 9:00:00 AM (CS) to 12/9/2022 2:00:00 PM (CS). |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie from west to east will be limited to 100 as a result of a planned maintenance outage from 10/4/2022 8:00:00 AM (CD) to 10/8/2022 6:00:00 PM (CD).
OUTAGE UPDATE Updated at 10/20/2022 2:03:57 PM (CD) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 as a result of a planned maintenance outage from 10/10/2022 9:00:00 AM (CD) to 12/9/2022 2:00:00 PM (CD). |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie from west to east will be limited to 100 as a result of a planned maintenance outage from 10/4/2022 8:00:00 AM (CD) to 10/8/2022 6:00:00 PM (CD). The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 on 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 9/26/2022 1:15:19 PM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie from west to east will be limited to 100 as a result of a planned maintenance outage from 10/4/2022 8:00:00 AM (CD) to 10/8/2022 6:00:00 PM (CD). The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 on 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 9/19/2022 3:04:15 PM (CD) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie from west to east will be limited to 125 as a result of a planned maintenance outage from 9/26/2022 8:00:00 AM (CD) to 9/26/2022 5:00:00 PM (CD). |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 on 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 9/9/2022 1:51:02 PM (CD) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie from west to east will be limited to 100 as a result of a planned maintenance outage from 10/4/2022 8:00:00 AM (CD) to 10/8/2022 6:00:00 PM (CD). |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 on 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 8/26/2022 7:33:29 AM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 on 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 8/26/2022 3:55:31 AM (CD) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 as a result of an unplanned maintenance outage from 8/26/2022 12:01:00 AM (CD) to 8/26/2022 9:00:00 AM (CD). |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 on 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 8/19/2022 4:09:34 PM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 on 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 8/17/2022 3:51:35 PM (CD) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie from east to west will be limited to 150 as a result of a planned maintenance outage from 8/18/2022 8:00:00 AM (CD) to 8/18/2022 1:00:00 PM (CD). |
Transmission service across the Rapid City HVDC Tie is administered by Black Hills Power. SPP administers service to and from the Eastern terminal of this tie (RCEASTINJ). Information provided here represents status of the Eastern terminal of the Rapid City DC Tie as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 on 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 8/4/2022 12:24:58 PM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 on 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 8/1/2022 2:07:38 PM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 on 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 7/28/2022 1:55:57 PM (CD) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie from west to east will be limited to 150 as a result of a planned maintenance outage from 8/1/2022 8:00:00 AM (CD) to 8/1/2022 5:00:00 PM (CD). |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 on 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 7/8/2022 9:45:34 AM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 on 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 7/8/2022 9:44:45 AM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 on 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 7/8/2022 9:43:55 AM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 from 7/11/2022 @0900 through 7/14/2022 @1700 and again on 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 6/28/2022 3:33:22 PM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 from 04/25/2022 @1300 through 05/05/2022 @ 1700 for a planned Maintenance Outage. It will also be limited to 0 MW in both directions from 06/13/2022 @ 0800 through 06/17/2022 @ 1900 and again on 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 6/23/2022 8:28:53 AM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 from 04/25/2022 @1300 through 05/05/2022 @ 1700 for a planned Maintenance Outage. It will also be limited to 0 MW in both directions from 06/13/2022 @ 0800 through 06/17/2022 @ 1900 and again on 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 6/23/2022 8:08:25 AM (CD) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 100 as a result of an unplanned maintenance outage from 6/23/2022 8:08:00 AM (CD) to 6/23/2022 2:00:00 PM (CD). |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 from 04/25/2022 @1300 through 05/05/2022 @ 1700 for a planned Maintenance Outage. It will also be limited to 0 MW in both directions from 06/13/2022 @ 0800 through 06/17/2022 @ 1900 and again on 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 6/13/2022 1:36:18 PM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 from 04/25/2022 @1300 through 05/05/2022 @ 1700 for a planned Maintenance Outage. It will also be limited to 0 MW in both directions from 06/13/2022 @ 0800 through 06/17/2022 @ 1900 and again on 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 6/13/2022 1:36:13 PM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 from 04/25/2022 @1300 through 05/05/2022 @ 1700 for a planned Maintenance Outage. It will also be limited to 0 MW in both directions from 06/13/2022 @ 0800 through 06/17/2022 @ 1900 and again on 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 6/13/2022 7:35:37 AM (CD) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 as a result of an unplanned maintenance outage from 6/13/2022 7:35:00 AM (CD) to 6/17/2022 7:00:00 PM (CD). |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 from 04/25/2022 @1300 through 05/05/2022 @ 1700 for a planned Maintenance Outage. It will also be limited to 0 MW in both directions from 06/13/2022 @ 0800 through 06/17/2022 @ 1900 and again on 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 6/13/2022 7:34:51 AM (CD) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 as a result of an unplanned maintenance outage from 6/13/2022 7:34:00 AM (CD) to 6/16/2022 7:00:00 AM (CD). |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 from 04/25/2022 @1300 through 05/05/2022 @ 1700 for a planned Maintenance Outage. It will also be limited to 0 MW in both directions from 06/13/2022 @ 0800 through 06/17/2022 @ 1900 and again on 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 5/21/2022 6:38:36 AM (CD) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 as a result of an unplanned maintenance outage from 5/21/2022 6:38:00 AM (CD) to 6/1/2022 8:00:00 AM (CD). |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 from 04/25/2022 @1300 through 05/05/2022 @ 1700 for a planned Maintenance Outage. It will also be limited to 0 MW in both directions from 06/13/2022 @ 0800 through 06/17/2022 @ 1900 and again on 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 5/20/2022 3:17:55 PM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 from 04/25/2022 @1300 through 05/05/2022 @ 1700 for a planned Maintenance Outage. It will also be limited to 0 MW in both directions from 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 5/5/2022 6:36:57 PM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 from 04/25/2022 @1300 through 05/05/2022 @ 1700 for a planned Maintenance Outage. It will also be limited to 0 MW in both directions from 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 5/5/2022 5:48:46 PM (CD) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 as a result of a planned maintenance outage from 5/6/2022 5:48:46 PM (CD) to 5/6/2022 10:00:00 PM (CD). |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 from 04/25/2022 @1300 through 05/05/2022 @ 1700 for a planned Maintenance Outage. It will also be limited to 0 MW in both directions from 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 5/5/2022 5:48:27 PM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 from 04/25/2022 @1300 through 05/05/2022 @ 1700 for a planned Maintenance Outage. It will also be limited to 0 MW in both directions from 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 5/5/2022 5:47:28 PM (CD) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 as a result of a planned maintenance outage from 5/6/2022 5:47:28 PM (CD) to 5/6/2022 10:00:00 PM (CD). |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 from 04/25/2022 @1300 through 05/05/2022 @ 1700 for a planned Maintenance Outage. It will also be limited to 0 MW in both directions from 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 4/22/2022 3:22:15 PM (CD) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 as a result of a planned maintenance outage from 4/25/2022 1:00:00 PM (CD) to 5/5/2022 5:00:00 PM (CD). |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 from 04/25/2022 @1300 through 05/05/2022 @ 1700 for a planned Maintenance Outage. It will also be limited to 0 MW in both directions from 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 4/18/2022 6:20:53 AM (CD) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 as a result of an unplanned maintenance outage from 4/18/2022 2:36:00 AM (CD) to 5/23/2022 11:59:00 PM (CD). |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 from 04/25/2022 @1300 through 05/05/2022 @ 1700 for a planned Maintenance Outage. It will also be limited to 0 MW in both directions from 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 4/18/2022 6:07:15 AM (CD) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 as a result of an unplanned maintenance outage from 4/18/2022 2:36:00 AM (CD) to 4/18/2022 6:00:00 PM (CD). |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 from 04/25/2022 @1300 through 05/05/2022 @ 1700 for a planned Maintenance Outage. It will also be limited to 0 MW in both directions from 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 4/18/2022 2:36:45 AM (CD) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 as a result of an unplanned maintenance outage from 4/18/2022 2:36:00 AM (CD) to 4/18/2022 7:00:00 AM (CD). |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 from 04/25/2022 @1300 through 05/05/2022 @ 1700 for a planned Maintenance Outage. It will also be limited to 0 MW in both directions from 10/10/2022 @ 0900 through 12/09/2022 @ 1400.
OUTAGE UPDATE Updated at 3/22/2022 1:00:44 AM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 from 04/25/2022 @1300 through 05/05/2022 @ 1700 for a planned Maintenance Outage
OUTAGE UPDATE Updated at 3/10/2022 4:13:58 PM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 from 04/25/2022 @1300 through 05/05/2022 @ 1700 for a planned Maintenance Outage
OUTAGE UPDATE Updated at 3/10/2022 10:05:22 AM (CS) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 as a result of an unplanned maintenance outage from 3/10/2022 9:52:00 AM (CS) to 3/11/2022 11:00:00 PM (CS). |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP.
The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 from 04/25/2022 @1300 through 05/05/2022 @ 1700 for a planned Maintenance Outage
OUTAGE UPDATE Updated at 3/1/2022 8:49:21 AM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP. OUTAGE UPDATE Updated at 2/28/2022 8:57:56 AM (CS) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie in both directions will be limited to 0 as a result of an unplanned maintenance outage from 2/28/2022 8:57:00 AM (CS) to 3/4/2022 6:00:00 PM (CS). |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP. OUTAGE UPDATE Updated at 2/1/2022 12:41:56 PM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP. OUTAGE UPDATE Updated at 1/3/2022 8:55:25 AM (CS) - The RAPID CITY NON-DC TIE INJECTION POINT DC Tie from west to east will be limited to 0 as a result of a planned maintenance outage from 1/24/2022 10:00:00 AM (CS) to 2/3/2022 7:00:00 PM (CS). |
Transmission service across the Rapid City HVDC Tie is administered by WAPA. SPP administers service to and from the Eastern terminal of this tie. Information provided here represents status of the HVDC Tie and outage information as communicated to SPP. OUTAGE UPDATE Updated at 12/3/2021 10:14:08 AM – The RAPID CITY NON-DC TIE INJECTION POINT DC Tie has been returned to normal operation. |
|