OASIS Apps

- Curtailment Viewer
- DC Tie Viewer
- Price Discounts
- Price Matrix
- Transmission Load Relief

- SPP OASIS Archive Map
    > SPP OASIS Archive Page
    > Market System Status
    > Member Related Postings
    > FERC890 Items

- Studies Postings
 
SPP Logo
 
2017 Impact Studies
The following Generator Interconnection Studies have been requested.

Study Number Date Requested Purpose of Study Remarks Report
GEN-2017-009, GEN-2017-060, GEN-2017-082 November 16, 2018 Interim Availability Impact Study for Generation Interconnection Requests Posted 9/9/2020 Download
GEN-2017-069 July 18, 2017 Interim Availability Impact Study for Generation Interconnection Request Posted 10/7/2020 Download
GEN-2017-094 October 04, 2018 Interim Availability Impact Study for Generation Interconnection Request Posted 05/24/2019 Download
GEN-2017-179 August 27, 2018 Interim Availability Impact Study for Generation Interconnection Request Posted 7/3/2019 Download
PISIS-2017-001 May 31, 2017 Preliminary Interconnection System Impact Study #1 of 2017 No requests were entered in this queue cluster  
PISIS-2017-002 November 30, 2017 Preliminary Interconnection System Impact Study #2 of 2017 Posted 5/11/2018 Download

Please send your requests to GIStudies@spp.org

If you have any questions, please submit a ticket on RMS.